| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹7.5 LAdmitted-Finance | -10.10% | ₹7.5 L | L1 | Admitted-Finance |
| 2 | L2₹8.1 L+₹66,442.40 (8.90%)Admitted-Finance | -2.10% | ₹8.1 L+₹66,442.40 (8.90%) | L2 | Admitted-Finance |
| 3 | L3₹8.3 L+₹83,053 (11.1%)Admitted-Finance | -0.10% | ₹8.3 L+₹83,053 (11.1%) | L3 | Admitted-Finance |
Tender Value
₹8.3 L
EMD Value
₹83,053
Closing Date
13 Aug 2026, 12:00 pmClosed
CHIEF ENGINEER CIVIL
NAGAR NIGAM AGRA
Zone-1, Chhatta, Shahdara (Trans-Yamuna) Work regarding the installation of tethering posts and the repair of the fodder store gate at the gaushala (cowshed).
2026_DOLBU_1175044_1
10-07-2026/NAGAR NIGAM AGRA/24-07-2026/23
Open Tender
Construction Works
Percentage
30 days
AGRA
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
NAGAR NIGAM
₹83,053
18 Sept 2026
6 Aug 2026
13 Aug 2026
6 Aug 2026
13 Aug 2026
6 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in Excavation in foundation in ordinary soil (loam, clay or sand) including, lift up to 1.50 m and lead up to 30m and including filling watering and ramming of excavated the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the engineer-in-charge up to a distance of 30 M form the foundation trenches. (Rate including Royalty of earth also) (4-Chapter S.I.NO.- 251) | 32.4 | Cum | 150 | ₹4,860 |
| 2 | Cartage of Malva, Silt, sludge kankar and other disposable organic material etc. all complete with labour T&P including cartage of 8 km. (Chapter No.3 Si.No.8) | 32.4 | Cum | 230.1 | ₹7,455.24 |
| 3 | Providing and laying Cement Concrete in 1:5:10 (1 cement :5 fine sand 10 Stone ballast 40 mm gauges) and curing complete, including cost of form work in foundation and floors. (5-Chapter Sr.No.1) | 3.6 | Cum | 5,325 | ₹19,170 |
| 4 | Class-150 Brick Work in 1:4 Cement and Coarse Sand, mortar in foundation and plinth including supply of all materials, labor and tools and plants, etc. Required for proper completion of the work. ( Chapter No. 06 Sr.No. 2) | 12.25 | Cum | 5,650 | ₹69,212.5 |
| 5 | 12mm thick cement plaster in single coat of fair side of single of half brick wall for interior plastering up to floor two level including internal rounded angles chamfers and rounded angles not excluding 80mm in girth and finished even and smooth. No extra for mixing any additive.
(c) 1 Cement : 4 Coarse sand.
(Chapter No.13 Si.No.582(ii)) | 35 | Sqm | 200 | ₹7,000 |
| 6 | Providing and applying plaster of paris putty of 2 mm thickness over plastered surface to prepare the surface even and smooth complete. including curing the cost of all material, labour, T&P etc. complete. (Chapter No.15 Si.No.1) | 35 | Sqm | 130 | ₹4,550 |
| 7 | Finishing walls with Acrylic Smooth exterior paint of required shade: New work (Two or more coat applied @ 1.67 Itr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm) supply of all labour material and T&P required for proper completion of work. (Chapter No.15 Si.No.17) | 35 | Sqm | 140 | ₹4,900 |
| 8 | Providing and laying Cement Concrete in 1:2:4 of not less than strength of M-15 stone grit (20 mm nominal size) approved coarse sand and cement. Curing complete including of cost of form work in foundation and floors.(5-Chapter Sr.No.6 Si.No..4.1.3) | 25.2 | Cum | 6,600 | ₹1,66,320 |
| 9 | Mild Steel work in built up tubular ( round, square or rectanglar hollow tubes etc.) trusses etc., including cutting, hoisting, fixing in position and applying priming coat of approved steel perimer, including welding and bolted with special shaped washers etc. complete. (Chapter No.10 Si.No.8) | 150 | Kg | 105 | ₹15,750 |
| 10 | Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in and an overall rates) brought for proper completion of the work and including supply of steel, its wastage bend hooks and authorized over lapping shall be measured up to floor two level.
(b) 10mm to 12mm tor.
(Chapter No. 10 S.I. No. 504(B)) | 2,242.8 | Kg | 85 | ₹1,90,638 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.02 MB
BOQ_2208064.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .