| 1.01 | Loading and unloading of RSJ 36' above poles . | 3 | each | 1,800 ₹2,124 |
| 2.01 | Excavation of pole pit above 9.14m poles steels joist 30' length. | 3 | per pit | 2,250 ₹2,655 |
| 3.01 | Erection of poles above 9.14m poles steels joist 30' length. | 3 | per pole | 2,400 ₹2,832 |
| 4.01 | Loading and unloading of 9m poles | 9 | per pole | 5,400 ₹6,372 |
| 5.01 | Excavation of 9m pole pit on normal ground | 9 | per pit | 6,750 ₹7,965 |
| 6.01 | Erection of 9m pole on normal ground | 9 | per pole | 7,200 ₹8,496 |
| 7.01 | Transportation of 9m poles from road side to pole pit upto 2 KM | 12 | per pole | 9,600 ₹11,328 |
| 8.01 | Loading and unloading of 8m poles | 20 | per pole | 8,000 ₹9,440 |
| 9.01 | Excavation of 8m pole pit on normal ground | 20 | per pit | 10,000 ₹11,800 |
| 10.01 | Erection of 8m pole on normal ground | 20 | per pole | 11,000 ₹12,980 |
Tender Value
Refer Docs
EMD Value
₹2,815
Closing Date
29 Dec 2025, 2:00 pmClosed
EE/TKY
TNEB TKY
Imp Estimate for replacement 11 KV AB switch into centre rotating switch 3 nos in 11 KV Bethelpuram in amathanpothai 4 pole str under Eraniel section in various works in various section in Eraniel c and I section Thuckalay division
2025_EB_632248_1
EE/D/TKY/ETW 18/Dt.15.12.2025
Open Tender
Electrical Works
90 days
EE/TKY
As Specified tender
3 documents required · 3 mandatory
₹0
₹2,815
Yes
6 Mar 2026
15 Dec 2025
30 Dec 2025
16 Dec 2025
29 Dec 2025
16 Dec 2025
16 Dec 2025 - 29 Dec 2025
Loading and unloading of RSJ 36' above poles .
Excavation of pole pit above 9.14m poles steels joist 30' length.
Erection of poles above 9.14m poles steels joist 30' length.
Loading and unloading of 9m poles
Excavation of 9m pole pit on normal ground
Erection of 9m pole on normal ground
Transportation of 9m poles from road side to pole pit upto 2 KM
Loading and unloading of 8m poles
Excavation of 8m pole pit on normal ground
Erection of 8m pole on normal ground
Transportation of 8m poles from road side to pole pit upto 2 KM
Drilling of Slotted Holes
Transporting of Line materials from Section office to workspot upto 20 KM .
Erection of V cross arm
Erection of tapping channel cross arm
Erection of HT pin insulator
Fixing of HT TI fittings
Fixing of top channel
Fixing of cross bracing
Erection of alignment of centre rotating AB switch
Providing jumpering
Dismantling of of top channel
Dismantling of cross bracing
Dismantling of 11 KV AB switch
Dismantling of jumpering
Dismantling and fixing of HT pin insulator
Changing of pinpoint to cutpoint
Dismantling of stay set
Erection of stay set
For ordinary tree clearance and Throng bushes & trees.
Erection of earth wire trenches and paving of earth wire, Erection of 2 Nos. earth pipe and giving earth connection, Earthing of all metal parts, LAS etc., including neutral connection .
Dismantling of earth wire trenches and paving of earth wire, dismantling of 3 Nos. earth pipe and remove earth connections.
Dismantling and Refixing of V cross arm 3.5'
Dismantling and Refixing of tapping channel cross arm
Dismantling and Refixing of HT pin insulator with pin 11KV
Dismantling and Refixing of HT TI fittings
Stringing of 11 KV lines for ACSR 7/3.35 mm conductor
Dismantling and Reerection of HT ACSR 7 / 4.09 conductor.
Dismantling and Reerection of LT ACSR 7 / 3.35 conductor.(HT)
Dismantling and Reerection of ACSR 7 / 2.59 conductor.(LT)
Dismantling and Refixing of LT pin insulator
Dismantling and Refixing of LT shackle
Erection of 11KV single pole structure
Erection of additional support for single pole DT including painting
Erection of 63KVA Distribution Transformer
Loading & unloading of Distribution Transformer below 250 KVA
Erection of Single phase Service connection
Dismantling and erection of 1*40W tube light in complete set
Excavation of of stay pit on normal ground
Erection of stay set
Fixing of LT three phase cross arm
Fixing of LT pin insulator
Fixing of shackle
Erection of Street light Switching point arrangement
Dismantling and Refixing of three phase cross arm
Dismantling and Refixing of single phase cross arm
Dismantling of poles above 8m without congrete in damaged condition including grill seperation etc.
Congreting with 1:4:8 mix using 40mm jelly including curing (material +labour) sleeve congreting
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.75 MB
Tendernotice_2.pdf
PDF • 1.45 MB
BOQ_756434.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid