| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAdmitted-Finance | ₹1.1 Cr | L1 | Admitted-Finance |
| 2 | L2₹1.1 Cr+₹2,959.92 (0.03%)Admitted-Finance | ₹1.1 Cr+₹2,959.92 (0.03%) | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | K.Venkatachalam L1 | K.Balamurugan L2 |
|---|---|---|---|---|---|
| 1.001.) Upgradation of the road from S.U Road to Deviyakurichi Eri Karai Via Vedhanayagapuram - Vadakumarai Road Km 0/0-0/600 | |||||
| 2.00 | Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-0/300 | 576 | Sqm | - | - |
| 3.00 | Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A. Km 0/0-0/600 | 128.25 | Cum | - | - |
| 4.00 | Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-0/600 | 64.13 | Cum | - | - |
| 5.00 | Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/600 | 226.13 | Cum | - | - |
| 6.00 | Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/600 | 169.6 | Cum | - | - |
| 7.00 | Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0- 0/600 | 169.6 | Cum | - | - |
| 8.00 | Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 0/600 | 2,261.25 | Sqm | - | - |
| 9.00 | Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 0/600 | 2,261.25 | Sqm | - | - |
| 10.00 | Hectametre Stone | 3 | Each | - | - |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
12 Aug 2020, 3:00 pmClosed
Additional Director/ Project Director
DRDA, SALEM
14th Finance Commission Grant (Additional) - Package No.01/2019-20 Thalaivasal Block No.of Road Works 05 - Salem District.
2020_RDTN_174089_9
Roc.No.1110/2020/A4
Open Tender
Civil Works - Roads
Item Wise
180 days
DRDA
As per tender schedule
3 documents required · 3 mandatory
₹0
₹1.1 L
DRDA, SALEM
18 Sept 2020
31 Jul 2020
12 Aug 2020
31 Jul 2020
12 Aug 2020
31 Jul 2020
3 Aug 2020
Amount
1.) Upgradation of the road from S.U Road to Deviyakurichi Eri Karai Via Vedhanayagapuram - Vadakumarai Road Km 0/0-0/600
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-0/300
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A. Km 0/0-0/600
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-0/600
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/600
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/600
Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0- 0/600
Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 0/600
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 0/600
Hectametre Stone
2.) Strengthening of the Road from Muyal Karadu to Kathir Nagar (Via) Periyar Nagar Milk Society Km 0/0-1/340
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-1/340
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m Km 0/0-1/340
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-1/340
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 1/0
Road Km 1/0-1/340
Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0-1/0
Road Km 1/0-1/340
Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 0/300
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 1/0
Road Km 1/0-1/340
Kilometer Stone
Hectametre Stone
3.) Upgradation of the road from Manivilundan Colony Siruvachur Road to Chinna Kamadappan Kovil via Sivasangarapuram Limit Km 0/0-0/645
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-0/645
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A. Km 0/0-0/645
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-0/645
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/645
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/645
Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0- 0/645
Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 0/645
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 0/645
Hectametre Stone
4.) Strengthening of the Road from Navalur Veeraganur Road to Theru Kadu (Via) T.V Road Km 0/0-0/608
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-0/608
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m Km 0/0-0/608
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-0/608
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0- 0/608
Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0-0/608
Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 0/608
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 0/608
Hectametre Stone
5.) Strengthening of the Road from Siruvachur Mechanic Kadu to Dhasan Kadu Km 0/0-1/0
Clearing Scrub jungle including cutting all trees and other vegetation and depositing them beyond the road as directed by the departmental officers Including all labour charges etc., complete. KM 0/0-1/0
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m Km 0/0-1/0
Providing and Laying Gravel to 100mm compacted thick including cost & conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by Power roller to achieve the required Proctor density at 100% compaction . Km 0/0-1/0
Providing and laying Water Bound Macadam Grading - II ( 75mm to 22.40mm)IRC HBGmetal consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively)and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) Km 0/0-1/0
Providing and laying Water Bound Macadam Grading - III(63mm to11.20mm)IRC HBG of 75mm consolidated thickness consisting of clean, crushed aggregates mechanincally interlocked by rolling and bonding together with screening binding material of 0.24 cum for 10 sqm (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 20 & 6% repectively) and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer as per clause 405 of MORD revision I(Mix -in - place method) Rate for 10sqm.. Km 0/0-1/0
Applying TACK COAT over WBM surface at 4Kg / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp. Km 0/0- 1/0
Providing and layiing pre-mix carpet 20mm thickness using 0.18cum of 13.2 IRC machine crushed metal 0.09cum of 11.2mm IRC machine crushed metal with 14.60Kg of Bitumen for pre-mixing 10 sqm of pre-mix carpet and laying separately Seal coat type "A" using .09 cum of 6.70mm IRC HBG chips with 9.80 Kg of Bitumen for 10sqm including cost and conveyance of materials to the departmental metric gauge for pre-measurement heating the bitumen boiler heating the aggregate and mixing them with bitumen in mini hot mix plant for pre-mix carpet and rolling by 80-100 KN power roller including labour charges for spreading hire and fuel charges for mini hot mix plant, bitumen boiler, all other tools and plants employed etc., complete . Km 0/0- 1/0
Kilometer Stone
Hectametre Stone
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
K.Balamurugan
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
01.pdf
Tender Documents • 0.48 MB
BOQ_208505.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .