Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹6.5 LAdmitted-Finance JAYANT NEAR JAI HIND SCHOOL LAXMI MARKET SINGRAULI 486890 MADHYA PRADESH INDIA | SINGRAULI | MADHYA PRADESH | 486890 | ₹6.5 L | L1 | Admitted-Finance |
| Sl No | Description | Qty | Unit | SARWESHWARI ENTERPRISES L1 |
|---|---|---|---|---|
| 1.00Name and scope of work : Removal of wornout Undercarriage Assembly , repairing of track and carrier roller mounting & fitment of New Undercarriage assembly in 09 Nos. BD355 Dozers of capacity 410HP working at OWS and NWS Dozer Section on need basis at Nigahi Project. Maximum likely manpower to be deployed per shift : 06Nos. (Skilled 03 , Semi-skilled 03) | ||||
| 2.00 | Cost/ charges for dismantling of track chain and frame aseembly for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 10,000 ₹90,000 Lowest |
| 3.00 | Cost/ charges for dismantling and fitting of idler assembly for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 10,000 ₹90,000 Lowest |
| 4.00 | Cost/ charges for dismantling and fitting of track rollers ( LHS and RHS) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 13,000 ₹1,17,000 Lowest |
| 5.00 | Cost/ charges for dismantling of carrier roller, bracket mounting of carrier roller, equalizer bar pad and fitting of bracket mounting of carrier roller, equalizer bar pad and carrier roller ( LHS and RHS) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 3,500 ₹31,500 Lowest |
| 6.00 | Cost/ charges for repairing of segment groove and fitting of sprocket segment both size (18 nos.) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 9,400 ₹84,600 Lowest |
| 7.00 | Cost/ charges for mounting of undercarriage assembly including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 13,000 ₹1,17,000 Lowest |
| 8.00 | Cost/ Charges for thread tapping of track roller mounting bolts 60 numbers thread making for each Dozer. Total numbers of thread making for 09 nos. Dozer is 60x9=540 nos. (One no. thread tapping time is approx. 0.5 hours) | 540 | Nos. | 110 ₹59,400 Lowest |
| 9.00 | Cost/ charges for repairing of track frame for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | 9 | job | 7,000 ₹63,000 Lowest |
| 10.00 | Total impact of GST for the purpose of CTC | 1 | Nos | - |
Tender Value
₹8.1 L
EMD Value
₹10,100
Closing Date
14 Apr 2026, 11:00 amClosed
GM(EXCV)NCL, NIGAHI PROJECT
OFFICE OF GENERAL MANAGER (EXCV) NCL, NIGAHI PROJECT, PO-NIGAHI , DISTT-SINGRAULI (MP)
Removal of wornout Undercarriage Assembly , repairing of track and carrier roller mounting , fitment of New Undercarriage assembly in 09 Nos. BD355 Dozers of capacity 410HP working at OWS and NWS Dozer Section on need basis at Nigahi Project
2026_NCL_357656_1
NGH/EXCV/TENDERS/25-26/111
Open Tender
Excavation Department Work
Item Rate
365 days
NCL NIGAHI PROJECT
AS PER NIT
4 documents required · 4 mandatory
₹10,100
7 May 2026
27 Mar 2026
15 Apr 2026
27 Mar 2026
14 Apr 2026
28 Mar 2026
27 Mar 2026 - 3 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Name and scope of work : Removal of wornout Undercarriage Assembly , repairing of track and carrier roller mounting & fitment of New Undercarriage assembly in 09 Nos. BD355 Dozers of capacity 410HP working at OWS and NWS Dozer Section on need basis at Nigahi Project. Maximum likely manpower to be deployed per shift : 06Nos. (Skilled 03 , Semi-skilled 03) | - | - | - | - |
| - | Cost/ charges for dismantling of track chain and frame aseembly for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ charges for dismantling and fitting of idler assembly for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ charges for dismantling and fitting of track rollers ( LHS and RHS) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ charges for dismantling of carrier roller, bracket mounting of carrier roller, equalizer bar pad and fitting of bracket mounting of carrier roller, equalizer bar pad and carrier roller ( LHS and RHS) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ charges for repairing of segment groove and fitting of sprocket segment both size (18 nos.) including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ charges for mounting of undercarriage assembly including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Cost/ Charges for thread tapping of track roller mounting bolts 60 numbers thread making for each Dozer. Total numbers of thread making for 09 nos. Dozer is 60x9=540 nos. (One no. thread tapping time is approx. 0.5 hours) | - | Nos. | - | - |
| - | Cost/ charges for repairing of track frame for both sides including labour charges, contractor profit etc. (labour consisting of Skilled Fitter, Skilled welder and Semi skilled Helper manpower) for 09 Nos. Dozers | - | job | - | - |
| - | Total impact of GST for the purpose of CTC | - | Nos | - | - |
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 3.94 MB
ANNEXURESANDOTHERIMPORTENTDOCUMENT.pdf
Tender Documents • 0.27 MB
UNDERTAKINGASPERANNEXURE-II.pdf
Tender Documents • 0.08 MB
BOQ_370520.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .