| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹11.4 CrAccepted-AOC | ₹11.4 Cr | L-1 | Accepted-AOC OK |
| 2 | L-2₹13.5 Cr+₹2.1 Cr (18.3%)Rejected-Finance | ₹13.5 Cr+₹2.1 Cr (18.3%) | L-2 | Rejected-Finance Being the second lowest bidder hence rejected |
| 3 | L-3₹14.5 Cr+₹3.1 Cr (27.1%)Rejected-Finance | ₹14.5 Cr+₹3.1 Cr (27.1%) | L-3 | Rejected-Finance Being the third lowest bidder hence rejected |
Tender Value
₹14.9 Cr
EMD Value
₹24.9 L
Closing Date
24 Sept 2025, 4:00 pmClosed
Executive Engineer
HIMUDA Division Jarja Nahan Dist Sirmour HP
Housing Colony at Basal, Distt. Solan H.P. SH- Construction of 2 Nos. Twin Towers Block No. 26 and 27 24 Nos. 3BHK flats with Parking and Attic Floor including Internal Water Supply, Sanitary Installation, Co 2 Nos. 13000 Liter Capacity
2025_HIMUD_114806_1
HIMUDA ND CB ETENDER 2024 2713-22 DT 15.09.2025
Open Tender
Civil Works
Percentage
548 days
Solan
Please refer Tender documents.
9 documents required · 9 mandatory
₹5,900
₹24.9 L
Shimla
2 Jan 2026
15 Sept 2025
25 Sept 2025
15 Sept 2025
24 Sept 2025
15 Sept 2025
20 Sept 2025
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Cutting/excavation in earth work by mechanical means (Hydraulic Excavator/manual means in all heights and depth in all kind of soil including saturated soil comprising of pick wok, jumper work , chiselling/wedging out of soft and hard rock and their intermiate classification of soils including dewatering wherever required, setting out to required lines, levels as shown shown on the drawing as directed by the engineer in charge at site, according to the HPPWD specification of 1990 vol-1 as sorting out use ful and un-useful material and stacking the same in all lead and lift and levelling of excavated earth on dumping sites (to be arranged by the contractor at his own risk and cost including payment of prescribed dumping charges of municipal committee/local body if any) through all modes of transportation including head load, animal load and mechanical transportation to maximum possible extends in all leads means along with levelling fine dressing and all labour, machinery, materials, tools equipments and safty measure and incidentels necessary to complete the work by mechanized means and labour (if any required). All useful materials such as stone, shingles, aggregate and slates shall be sorted along road site and lift through all modes of transportation and used/removed a sper direction of the Engineer- in -Charge. Any loss to the private and public property during the course execution will be restored by the contractor whatsoever the nature of the same may be. The usable aggregates/ boulders /cutstones shall be taken in MAS Account and further will be issued to the contractor as per issue rate mentioned under clause-43. | 6,700.62 | Per Cum | 738.85 | ₹49,50,753.09 |
| 2 | Excavation work by mechanical means (Hydraulic excavator)/ manual means in foundation trenches or drains in all depth, in all kind of soil including saturated soil comprising of pick wok, jumper work , chiselling/wedging out of soft and hard rock and their intermiate classification of soils including dewatering wherever required, setting out to required lines, levels as shown shown on the drawing as directed by the engineer in charge at site, according to the HPPWD specification of 1990 vol-1 as sorting out use ful and un-useful material and stacking the same in all lead and lift and levelling of excavated earth on dumping sites (to be arranged by the contractor at his own risk and cost including payment of prescribed dumping charges of municipal committee/local body if any) through all modes of transportation including head load, animal load and mechanical transportation to maximum possible extends in all leads means along with levelling fine dressing and all labour, machinery, materials, tools equipments and safty measure and incidentels necessary to complete the work by mechanized means and labour (if any required). All useful materials such as stone, shingles, aggregate and slates shall be sorted along road site and lift through all modes of transportation and used/removed a sper direction of the Engineer- in -Charge. Any loss to the private and public property during the course execution will be restored by the contractor whatsoever the nature of the same may be. The usable aggregates/ boulders /cutstones shall be taken in MAS Account and further will be issued to the contractor as per issue rate mentioned under condition No.46 of NIT Form-6. | 2,915.21 | Per Cum | 823.1 | ₹23,99,509.35 |
| 3 | Excavating trenches of required width for pipes, cables,etc including excavation for sockets, and dressing of sides, ramming of bottoms, upto all depth, including getting out the excavated soil, and then returning the soil as required, in layers upto all depth, including consolidating each deposited layer by ramming, watering, etc. and disposing of surplus excavated soil as directed, in all lead and lifts. | 95.67 | Per Cum | 328.5 | ₹31,427.6 |
| 4 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete including carriage of material in all leads & lifts. | 94.8 | Per Cum | 1,481.45 | ₹1,40,441.46 |
| 5 | Stone soling properly handpacked filling interstices with Kharanja stone and consolidating with power road roller to the required gradient and caomber including spreading watering and rolling of binding materials moorum or earth etc. complete as per HP.PWD specification. 100 mm spread thickness (finished work including materials and labour)including carriage of material in all leads & lifts. | 355.5 | Per Cum | 1,225.35 | ₹4,35,611.93 |
| 6 | Providing & applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.7kg per square metre on damp proof course after cleaning the surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil Including carriage of material in all leads and lifts. | 1,171.18 | Per Sqm | 151.35 | ₹1,77,258.09 |
| 7Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering including carriage of material in all leads and lifts. All work up to plinth level | |||||
| 7.01 | 1:4:8 (1 cement : 4 coarse sand): 8 graded stone aggregate 40 mm nominal size) | 230.55 | Per Cum | 5,453.35 | ₹12,57,269.84 |
| 7.02 | 1 : 6 : 12 (1 cement : 6 coarse sand :12 graded stone aggregate 40 mm nominal size) | 371.01 | Per Cum | 5,025.6 | ₹18,64,547.86 |
| 7.03 | 1:2:4 (1 cement : 2 coarse sand) : 4 graded stone aggregate 20 mm nominal size) | 24.48 | Per Cum | 6,621 | ₹1,62,082.08 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.65 MB
NIT.pdf
Tender Documents • 2.63 MB
BOQ_167440.xls
BOQ • 0.40 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .