Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.1 LAccepted-AOC NO 6 76 EAST STREET THOPPUR MADURAI 625008 | MADURAI | MADURAI | TAMIL NADU | 625008 | ₹3.1 L | L1 | Accepted-AOC Work awarded |
| 2 | L2₹3.4 LRejected-Finance DOOR NO 7 121 SURVEY NO 7 121 K PUDUR | VELLORE | TAMIL NADU | 632001 | ₹3.4 L | L2 | Rejected-Finance Bidder Quoted an amount greater than the L1 |
| 3 | L3₹3.6 LRejected-Finance 3 358 A BAGAWATH SINGH ROAD PARAMAKUDI RAMANATHAPURAM 623707 | PARAMAKUDI | RAMANATHAPURAM | TAMIL NADU | 623707 | ₹3.6 L | L3 | Rejected-Finance Bidder Quoted an amount greater than the L1 |
| 4 | L4₹3.7 LRejected-Finance 520C MAIN ROAD WARD NO 12 METTU STREET ELAMBALUR PERAMBALUR | PERAMBALUR | PERAMBALUR | TAMIL NADU | 621220 | ₹3.7 L | L4 | Rejected-Finance Bidder Quoted an amount greater than the L1 |
| Sl No | Description | Qty | Unit | C RAJASEKARAN L1 | guadalupe associates L3 | S MURUGAN L4 | KDM BUILDERS AND CONTRACTORS L2 |
|---|---|---|---|---|---|---|---|
| 1.00Construction of new toilets (2 Nos) with drainage facilities to the existing Samayanallur Divison Office building located at TNEB Samayanallur campus. | |||||||
| 1.01 | Clearing light jungle including cost of all materials, labour, lead, lift, etc., complete. | 100 | sqm | 4.5 ₹450 | 6 ₹600 | 7 ₹700 | 9 ₹900 |
| 1.02 | Earthwork excavating and depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders Clearing juliflora jungle with uprooting including cost of all materials, labour, lead, lift, etc., complete. | 9.2 | cum | 234 ₹2,152.80 | 260 ₹2,392 | 260 ₹2,392 | 243 ₹2,235.60 |
| 1.03 | Supplying and filling of M-sand in foundation and basement with watering and consolidation as per specn. including cost of all materials, labour, lead, lift, etc., complete. (As instructed by the Engineer at site) | 0.7 | cum | 1,620 ₹1,134 | 1,600 ₹1,120 | 1,790 ₹1,253 | 1,710 ₹1,197 |
| 1.04 | Providing PCC 1:3:6 mix using 40 mm HBGS Jelly for foundation including cost of materials, labour charges, lead, lift etc, complete (without formwork) | 1.5 | cum | 4,500 ₹6,750 | 5,700 ₹8,550 | 5,770 ₹8,655 | 5,310 ₹7,965 |
| 1.05 | RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (without formwork). | 1.2 | cum | 8,100 ₹9,720 | 9,100 ₹10,920 | 9,090 ₹10,908 | 9,000 ₹10,800 |
| 1.06 | RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Column up to Basement) | 0.15 | cum | 8,100 ₹1,215 | 9,100 ₹1,365 | 12,320 ₹1,848 | 2,000 ₹300 |
| 1.07 | RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Grade Beam) | 1.1 | cum | 8,100 ₹8,910 | 12,400 ₹13,640 | 12,320 ₹13,552 | 10,000 ₹11,000 |
| 1.08 | RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Column above Basement, up to Ground floor Roof level) | 0.55 | cum | 8,100 ₹4,455 | 12,500 ₹6,875 | 12,320 ₹6,776 | 5,000 ₹2,750 |
| 1.09 | RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Roof beam) | 0.5 | cum | 8,100 ₹4,050 | 12,450 ₹6,225 | 12,460 ₹6,230 | 10,000 ₹5,000 |
Tender Value
₹3.8 L
EMD Value
₹3,759
Closing Date
5 Jan 2026, 2:00 pmClosed
SE/MEDC/TNPDCL/MADURAI
O/o SE/MEDC/TNPDCL/K.PUDUR/MADURAI
Construction of new toilets (2 Nos) with drainage facilities to the existing Samayanallur Division Office building located at TNEB Samayanallur campus
2025_EB_633934_1
SE/MEDC/MDU/ET/WC/23/2025-26, Dt 12.12.25
Open Tender
Civil Works - Buildings
90 days
Samayanallur
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹3,759
Yes
1 Apr 2026
18 Dec 2025
6 Jan 2026
18 Dec 2025
5 Jan 2026
18 Dec 2025
Construction of new toilets (2 Nos) with drainage facilities to the existing Samayanallur Divison Office building located at TNEB Samayanallur campus.
Clearing light jungle including cost of all materials, labour, lead, lift, etc., complete.
Earthwork excavating and depositing on bank with initial lead of 10m & initial lift of 2m in hard stiff clay stiff black cotton hard red earth, shales, murram, gravel stoney earth, earth mixed with small size boulders Clearing juliflora jungle with uprooting including cost of all materials, labour, lead, lift, etc., complete.
Supplying and filling of M-sand in foundation and basement with watering and consolidation as per specn. including cost of all materials, labour, lead, lift, etc., complete. (As instructed by the Engineer at site)
Providing PCC 1:3:6 mix using 40 mm HBGS Jelly for foundation including cost of materials, labour charges, lead, lift etc, complete (without formwork)
RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (without formwork).
RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Column up to Basement)
RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Grade Beam)
RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Column above Basement, up to Ground floor Roof level)
RCC 1:1.5:3 (M-20) using 12-20mm HBS metal (machine crushed) metal for foundation including cost of all material, lead, lift, etc, complete, but excluding cost of steel reinforcement (with formwork) (Roof beam)
Brick work in CM 1:5 using II class ground moulded chamber burnt bricks of size 9" x 4 3/8" x 2 3/4 " for basement and superstructure including cost of all materials, labour, lead, lift, curing, etc., complete. (As instructed by the Engineer at site)
Flooring with PCC 1:3:6 mix using 40mm HBS metal for flooring (machine crushed metal) including cost of all materials labour lead, lift, etc., complete. (As instructed by the Engineer at site)
RCC 1:1 1/2:3 (M 20) using 12mm to 20 mm HBS metal (machine crushed) for roof slab concrete of 130 mm thick with formwork including cost of all materials, labour, lead, lift, centering shuttering , curing, etc., complete. But excluding cost of steel reinforcement.
Plastering with CM.1:5 mix using 12mm thick for inside & outside walls, including cost of all materials, labour, lead, litf, etc, complete.
Plastering with CM 1:3 mix 12 mm thick for ceiling, sunshade etc., including cost of materials, labour, lead, lift, watering, curing, etc., complete.
Dadooing with glazed tiles of best approved quality of make johnson, neycer etc, over CM 1:3, 12mm thick including cost of all materials, labour, lead, lift, etc., complete. (As instructed by the Engineer at site)
Flooring with approved Vitrified tiles 600x600mm of approved Quality, design & colour (Johnson or equivalent make)laid in cement mortar 1:3 -20mm thick including pointing with same coloured cement using 0.4kg/sqm, finishing the joints, including cost of all materials, water charges,labour, lead, lift, etc. complete.
Providing one coarse of pressed tiles of 20x20x2cm embedded with CM 1:3 mixed with crude oil at 10% by weight of cement and pointed with same oiled mortor including all material, labour, lead, lift etc complete
Colour washing two coats with Exterior Plastic Emulsion paint over one coat of Plastic Emulsion primer for outside wall including cost of all materials, labour, lead, lift, etc., complete.
Colour washing two coats with Plastic Emulsion paint over one coat of Plastic Emulsion primer for inside wall including necessary plaster of parry's two coats cost of all materials, labour, lead, lift, etc., complete.
Dismantling of Brickwork of existing wall as instructed by Engineer at site instincluding cost of all materials, lead, lift, labour, cost of binding wire, etc., complete.
Supplying and fabricating and placing in position of MS / RTS steel reinforcement for RCC works including labour for cutting, bending, tying and fixing in position as per specification including cost of all materials, lead, lift, labour, cost of binding wire, etc., complete.
Supplying and fixing of Pin Headed / Fluted / Figured Glass 3mm thick with MS frame for Ventilators including cost of all materials, lead, lift, etc., complete.
Supplying and fixing in position of PVC door shutter made of Single Panel laminated Plastic section of size 200 x 20 mm and PVC extraced shutter frame of size 24 x 60 mm including cost of 3 nos 85 mm butt hinges for single leaf door of size 0.80 x 2.00 m with 2 No aluminium handle and 2 nos 150 x 2 mm aluminium towel bolt hinges etc., complete.
Supplying and fixing in position of 32mm dia pvc pipe of 10 kg/sq.cm pressure from the approved manufacturer Apollo, chemplast, avanplast, valarmathi, usha, vimal etc., confirming to IS 4985 of 1968, 4984 of 1970 including cost of all special fixtures labour lead, lift, etc., complete.
Supplying and fixing in position of 25mm dia pvc pipe of 10 kg/sq.cm pressure from the approved manufacturer Apollo, chemplast, avanplast, valarmathi, usha, vimal etc., confirming to IS 4985 of 1968, 4984 of 1970 including cost of all special fixtures labour lead, lift, etc., complete.
Supplying and fixing of 1000 lit capacity sintex tank of approved quality including cost of labour for fixing etc., complete(As instructed by the engineer at site)
Refilling with excavated soil other than sand in foundation and sides of masonry, consolidation as per std. specn. With water including all labour, lead, lifts. etc, complete.(As instructed by the engineer at site)
Removing the excess earth and Refilling to the basement area as instructed by field engineer including all labour lead, lift, etc., complete.
Supplying and filling of Red gravel in the basement filling, labour for filling, watering and consolidation, including cost of all materials, lead, lifts, labour, etc., complete.( As instructed by the engineer at site)
Wiring with 2x1.50 sq.mm PVC unsheathed copper multistand cable of 1100 V grade in suitable pvc rigid pipe in wall or ceiling with pvc accessories with TW switch box in flush with wall covered with hylum sheet of 3mm thick with painting of suitable colour with continuous earth wire connection of 14 SWG TC wire for light and Fan points (SD 23)( As instructed by the engineer at site)
Wiring with 2x1.5 sq.mm (22/0.3) PVC insulated SC unsheathed Cu.conductor of 1100 V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories in in flush with wall, with 150mm x 100mm x 113mm TW switch box with 3 mm thick hylum sheet cover for 5 A 3 Pin non interlocking CS plug with continuous earth wire connection of 14 SWG TC wire and making good of the concealed portion with suitable colour for concealed PVC Plug point.(SD38) ( As instructed by the engineer at site)
Supplying and fixing 20W 4 Feet LED Fitting with LED including cost of all materials, labour charges, T&P, lead, lift, etc., complete.
Providing PVC down fall pipe using 110mm dia 4 Kg / Sqcm, PVC pipe and pvc clamp line supreme etc., including fixing PVC washer type door bend & shoe, in correct position and connecting from the roof slab including cost of all materials, labour, transport lead, lift, etc., complete, including pvc accessories and washers.
Supplying of PVC Screw Down Tap Heavy Type 20mm dia in water supply arrangement ncluding cost of all materials, labour, transport lead, lift, etc., complete, including pvc accessories and washers.
Supplying and fixing of Oval Shape Wash Hand Basin of size 560 x 450mm including cost of all materials, labour, transport lead, lift, etc., complete, including pvc accessories and washers.
Supplying and fixing in positon Indian Water Closet (Oriya type) of size 580 x 440mm white glazed earthern ware of approved quality and brand with "P" or "S" trap conforming to BIS with sand cushion and forming flooring alround the closet using 40mm HBG jelly in PCC concrete 1:3:6, 100mm thick and finishing the top to the required slope and including giving necessary connection to PVC pipes by dismantling floor slab and making good the dismantled portion to the original condition with leakages etc., complete
Supplying, fixing and laying of 110 mm dia PVC pipe 6 Kg/cm2 of ISI brand for sanitary arrangements including cost of all materials labour lead,lift etc complete.(Below ground level).
Supply of Rcc ring 4'-0" dia outer to outer and 1'-0" depth including cost of rings, transporting charges,lead,lift,etc, complete.
Labour charges for erection of RCC rings into the septic tank pit including cost of all materials,labour ,rope ,pully and props etc ,complete.
Supply and fixing Rcc Circular cover slab 4'-0" dia outer to outer 40mm thick including cost of all materials labour , transporting charges,lead,lift,etc,complete.
GST for bidders within Tamilnadu
GST for bidders outside Tamilnadu
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.80 MB
BOQ_758518.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid