Tender Value
₹8.4 L
EMD Value
₹8,420
Closing Date
20 Jun 2025, 12:00 pmClosed
Superintending Engineer
A 37 hydel colony Kavinagar Ghaziabad
Work related to transferring 33/11/LT/HT lines under the full deposit scheme head in the field of various 33/11 KV electricity sub -stations under the electricity distribution division, Modinagar.
2025_PVVNL_1047623_1
T-07/2025-26/EDC/GZB
Open Tender
Electrical Works
Item Rate
365 days
Superintending Engineer EDC GZB
Please refer tender document
2 documents required · 2 mandatory
₹1,180
Superintending Engineer
₹8,420
27 Jun 2025
11 Jun 2025
20 Jun 2025
11 Jun 2025
20 Jun 2025
11 Jun 2025
Amount
fo|qr forj.k [k.M] eksnhuxj ds vUrxZr fofHkUu 33@11 dsoh fo|qr midsUnzksa ds dk;Z{ks= esa iw.kZ tek ;kstuk en esa 33@11@,y0Vh0 ykbZuksa dks LFkkukUrfjr djus lEcU/kh dk;ZA
Carriage of fallowings from ESC. Modinagar/Ghaziabad to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
S.T Pole 13 Mtr. Long
S.T Pole 11 Mtr. Long
PCC Pole 11 Mtr. Long
PCC Pole 8.5 mtr Long.
Carriage of All line Material from store center Modinagar/Ghaziabad to j.e store Sub station as ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Erection of Single pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
S.T Pole 13 Mtr. Long
S.T Pole 11 Mtr. Long
PCC Pole 11 Mtr. Long
PCC Pole 8.5 mtr Long.
Erection of Double pole/Scation Pole support including complete 1 IT fittings as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
S.T Pole 13 Mtr. Long
S.T Pole 11 Mtr. Long
PCC Pole 11 Mtr. Long
PCC Pole 8.5 mtr Long.
Grouting of Single support shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
S.T Pole 13 Mtr. Long
S.T Pole 11 Mtr. Long
PCC Pole 11 Mtr. Long
PCC Pole 8.5 mtr Long.
Grouting of Double pole support shall be grouted with cement, sand and birck ballast/stone ballast in ratio 1:4:8 =30x3030 cms. including the cost of cement, sand, birck ballast/stone ballast, etc. as per actual size requirement, as per RESPO manual and as per direction of Engineer in charge including the cost of labour, T&P and carrier etc. required for proper completion of work.
S.T Pole 13 Mtr. Long
S.T Pole 11 Mtr. Long
PCC Pole 11 Mtr. Long
PCC Pole 8.5 mtr Long.
Carriage of All line Material from J.E store Sub station to Pit Site ACSR Weasel conductor, ABC conductor GI Wire, Earth Wire. M.S. Chanel, Angle, Stay & Earthig Rods, Barbed Wire. Disc Insulator etc.
Cutting /drilling /Welding of MS Angle iron for making guarding angle size 65x65x6/50x50x6 mm including the work of fixing the bracket on PCC/ST pole for construction of the line.
Carriage of 11 Kv CT/PT metering polemounted unit Varius ratio
Carriage and installation of 11 Kv Pilferresistant metering cubicle with out cable termination kit
Mounting of 11 KV CT/PT Unit Varius ratio
Making/Filling of 11 Kv Cable Jointing kit Varius size XLPE cable
Loading/Unloading & Carriage of T/F from ESC. BSR to pit site on kachcha pacaa road including loading and unloading chagres at both ends, rcquricd for proper completion of work, distance about to 60 Kms.
10/25 KVA T/F
63 KVA T/F
Fixing of 11 Kv Stay rod with Stay wire in proper way with Nozelling
Grouting of 11 Kv Stay rods
Laying, sagging. Stringing and binding and jumpering of 11 Kv XLPE cable 3*70 Square MM & Outher size newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
Laying, sagging. Stringing and binding and jumpering of ACSR Weisal , rabbit, dog newly erected pole as per RESPO manual and as per direction of supervising engineer. It includes the cost of labour, T&P, carrier etc. requried for proper completion of work.
ACSR weisal conductor
ACSR Rabbit/Dog conductor
ABC Cable 3*50 Square MM
ABC Cable 3*95 Square MM
Fixing of Earthing rod
Fixing of pin insulator
Fixing disc insulator
Fixing of Toff Channel
Fixing of X-arm 33/11 KV
Fixing of Top/Drop channel
Fixing of Sub station Angle.
Road Broken/Trench Digging with the help Road Cutter/Digging Machine/Tractor etc.
Mounting & Installation of T/F From D/P
10/25 KVA T/F
63 KVA T/F
The folloing material is required to be supplied by the contractor.
Holding clamp.
11 Kv Cable Jointing kit 3*70 Square mm XLPE cable
Double Pole clamp
F Clamp
LT Clamp
PG Clamp
J hook
Earth clamp
Stay clamp
Dead & clamps
Stay insulator for 11 Kv
Suspension clamps
LT Insulator
Bolt & nut off size.
M/S SURYA ELECTRICALS (BID ID -5260239)
Vivek Electricals (BID ID -5259276)
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .