Erection and Dismantling of Cuplok Scaffolding system Water washing descaling of furnace and D meter survey of boiler tubes bends along with replacement of eroded tubes bends of first and second pass of Boiler for Unit 1 500MW of BTPS
KPCL/2026-27/PS/WORK_INDENT4678
KPCL/2026-27/PS/WORK_INDENT4678
Open
Power stations
Two Tender Document System(Two Cover)
KPCL Superintending Engineer MM1 Office BTPS Bellary
9 documents required · 9 mandatory
Minimum financial turnover (civil engineering construction works) not less than two times the annual payments from this contract (Rs. xxxxx Lakhs)
Satisfactoriy completed (atleast 90%) as prime contractor at-least one such similar work of value not less than Rs. xxxxxxx (80% of estimated cost of tender)
Executed in any one year the following minimum quantities of work (Cement Concrete - xxxx cum, Earthwork - xxxx cum, etc) (80% of peak rate of construction)
Tenderer or his identified Sub Contractor should possess valid Electrical License for executing building electrificatio works and should have executed similar electrical works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one year
Tenderer or his identified Sub Contractor should possess valid license for executing water supply / sanitary engineering works and should have executed similar works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one year
Owning the following key and critical equipment for this work (xxxx, xxxx, xxxx)
Liquid assets and /or availability of credit facilities of no less than Rs. xxxxxx Lakhs (estimated cash flow for 3 months of peak construction period)
Total value of civl engineering works executed and payments received in the last five years (year-wise)
List of existing commitments and ongoing works
List of works for which tenders already submitted
Banker Details for reference
Construction equipment owned by the tenderer and equipment proposed to be deployed on this contract, if awarded
Reports on the financial standing of the tenderer, such as profit and loss statements and auditor’s reports for the last five years
Qualification and experience of the key technical and management personnel in permanent employment with the tenderer and those that are proposed to be deployed on this contract, if awarded
List of Financial Resources with Certificates
The intended bidder shall have proven experience as prime contractor in the field of Erection, Maintenance, Overhauling of Boiler works like Erection and Dismantling of Cup lock Scaffolding system, Water washing, descaling furnace, D meter survey of boiler tubes/ bends and replacement of eroded tubes/bends in TPS of 210 MW or above capacity in any one of the preceding five years. Satisfactorily completed similar nature of works in single or multiple work orders maximum 3 no. in any one year value not less than Rs. 58.03 Lakhs (exclusive GST) as a prime contractor and shall submit the copies of work orders and work done/experience certificate as documentary evidence, certified by the officer not less than the rank of Chief Engineer or equivalent and above for reference and verification. Work done of previous years shall be given weightage of 10% per year to bring them to present price level of the financial year in which tenders are invited
The annual turnover shall not be less than Rs. 232.10 Lakhs (exclusive GST) during any two of the preceding five financial years. (2021-22, 2022-23, 2023-24, 2024-25, and 2025-26).A certified copy of a statement of Profit & Loss accounts /Turn over certificate issued by chartered accountant shall be enclosed as documentary proof. Financial turnover of previous years shall be given weightage of 10% per year to bring them to the present price level of the financial year in which tenders are invited
The Bidder shall be an approved Special class IBR Repairer with approval from any state competent authority of Factories & Boiler. In case of award, the successful Bidder shall obtain the endorsement by department of FBIS of Karnataka State before starting the work
EMD of Rs 2,00,000/-shall be paid (Rs. Two lakhs only) through KPPP-portal
Registration of Establishment/firm/ company/ individual from Govt. department and Department of Labour
PF Registration with Regional Provident Fund Commissioner
Goods and Service Tax Registration certificate
PAN NUMBER
Valid labour license belonging to any region or for the Bellary region, and in event of successful bidder and placed work order the agency shall obtain LABOUR LICENSE pertaining to Bellary region only
Along with document pertaining to PQR, price bid the following annexures to be duly filled, signed & uploaded through e-portal Annexure-I General safety requirements Annexure-II : Tender form Annexure-III : Declaration of tender contents Annexure-IV: Statement of previous year experience Annexure-V: Declaration regarding contract termination. Annexure-VI : Consumables under contractors scope.Annexure-VII: Tools and plans under contractors scope.
₹2,910
₹2 L
19 Aug 2026
19 Aug 2026
28 Aug 2026
22 Aug 2026
21 Aug 2026
Erection and Dismantling of Cuplok Scaffolding system Water washing descaling of furnace and D meter survey of boiler tubes bends along with replacement of eroded tubes bends of first and second pass of Boiler for Unit 1 500MW of BTPS
Cleaning and assisting in conducting 'D'meter survey/ NDT of Water wall tubes/ bends around soot blowers.
Cleaning and assisting in conducting 'D'meter survey/ NDT of Water wall- tubes/bends around burner panels, corner tubes and inside the wind box.
Cleaning and assisting in conducting 'D'meter survey/ NDT of Div panellette coils, platen coils, Steam cooled spacer tubes & Radiant roof tubes.
Cleaning and assisting in conducting 'D'meter survey/ NDT of Water wall tubes at S panel /furnace bottom
Cleaning and assisting in conducting 'D'meter survey/ NDT of Divisional panellete ,Platen SH & Reheater coil header nipple welds in pent house
Cleaning and assisting in conducting 'D'meter survey/ NDT of Reheater front and rear coils, WW hanger tubes/ WW Screen tubes, Goose neck panel tubes & Extended WW tubes.
Replacement of tubes/ bends found eroded in Water wall tubes/ bends around soot blower/s panel, LTSH and economiser upper /intermediate/lower assy. Tubes/bends, hanger tubes, SCW tubes, BP Screen tube...
Replacement of tubes/ bends found eroded in Water wall tubes around burner panel/corner tubes /Extended WW tubes/ Divisional panellete/ Platen super heater/ steam cooled spacers tubes/Finish SH(front ...
Fin welding of water wall tubes/ bends in Water wall tubes/bends around Soot blowers, wind box area, Burner panel , corner tubes and steam cooled wall panels.
Reinforcement of eroded weld joints/area of water wall tubes.(PER JOINT EQUALS TO ONE NO)
Welding of scallopped bar plates at funace bottom,inside wind box plate rectification/welding and shroudings to the RH,SH, Screen Tubes and other coils .
Checking of alignment of Divisional panellete, SH Platen, RH front and rear coil assembly .
Realignment of SH divisional panellete & Platen SH coils with Spacer tube .
Rectification of boiler skin casing .
Loading and unloading of scaffolding materials from stores to site and placing at 10 mtr and 50 mtr elevation of boiler. (transport vehicle has to be arranged by the contractor) .
Erection of base of scaffolding at 12 mtr level neck .
Erection of cuploks structure and platforms above base from 12 mtr level to 70 mtr level all around the furnace including approach ladders .
Erection & dismantling of cuploks structure and full working platforms at 50 mtr of the furnace including approach ladders .
Shifting /changing/erection in the existing erected tiers between erection and dismantling period as per site requirement of different works .
Dismantling of cuploks structure and platforms above base from 12 mtr level to 70 mtr level all around the furnace including approach ladders .
Dismantling of base of scaffolding at 12 mtr level neck .
Loading and unloading of scaffolding materials from site to store and placing at designated area(transport vehicle has to be arranged by the contractor) .
Water washing and descaling of RH coils, rear arch area, EWW and Backpass extended floor panel are using high pressure furnace water wash pump .
Water washing and Descaling of furnace water wall and burner panels using high pressure furnace water wash pump) .
Water washing and Descaling of SH (div panellette, platen and Finish SH front rear) using high pressure furnace water wash pump) .
Slitting the tubes at fin welding at just below the bend, heating to the required temperature and correcting the bends.(PER JOINT EQUALS TO ONE NO)
Rectification of S panel structure and supports
Assisting in RLA works of boiler
Expert supervision and certification of Boiler Furnace Scaffolding
Arrangement of jet pump for hydraulic test
Clearing/removal of wool mattress/cotton waste/scrap
materials over boiler floors.(per day)
Assisting in Hydraulic test of Pressure parts system of boiler
Cleaning/removal of ash over the buck stay beams,wind box top and bottom, boiler floors,rear arch,pent house
Replacement of Tubes/bends cut for RLA study test in
Unit-1 boiler.(Per Joint)
Cleaning of ash accumulated in SCW(steam cooled wall), terminal tubes/upper/intermediate/lower bank coils , Economiser hanger tubes and Economiser upper/intermediate /lower bank coils.
Assisting in D meter survey/ NDT of LTSH coils/terminal tubes/bends
Assisting in D meter survey/ NDT of Economiser upper /intermediate/lower bank coils/bends and Hanger tubes of LTSH and Economiser
Assisting in D meter survey/ NDT of Steam cooled front, rear, side wall/BP Extended SCW including access door bends and LRSB insert bends.
Welding of tubes / bends of the coils removed for approach( For 3 joints)
Inspection /Rectification of casette baffles provided over the bends in LTSH and Economier coils of second pass.(For 3 no.s)
Inspection/rectification of shroudings over the bends/ tubes in the II pass boiler. (FOR 10 Coils)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
4678-tender document.pdf
Tender Document • 3.08 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .