Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹20.7 LAdmitted-Finance | -0.12% | ₹20.7 L | L1 | Admitted-Finance |
| 2 | L2₹20.7 LAdmitted-Finance | -0.08% | ₹20.7 L | L2 | Admitted-Finance |
| 3 | L3₹20.7 LAdmitted-Finance | -0.05% | ₹20.7 L | L3 | Admitted-Finance |
Tender Value
₹20.7 L
EMD Value
₹41,459
Closing Date
29 May 2026, 3:30 pmClosed
Executive Engineer
Office of the Executive Engineer, Burdwan Division, Social Sector, P.W.Dte., Jagatberh, Surya Nagar, Sripally, Burdwan, Pin-713103.
Construction of Oxygen Manifold Unit at Tertiary Cancer Care Centre of Burdwan Medical College and Hospital, Purba Bardhaman. (Civil work) Project ID HF252649943S000
2026_WBPWD_5013920_1
WBPWD/SS/EE/BDN/ NIT_01/ 2026_2027
Open Tender
CIVIL WORKS
180 days
Burdwan Medical College and Hospital
Please refer Tender documents.
4 documents required · 4 mandatory
₹41,459
Yes
O/O EE, Burdwan Division ,Social Sector , PWDte
15 Jun 2026
12 May 2026
1 Jun 2026
13 May 2026
29 May 2026
18 May 2026
18 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars. (a) In ground floor including roof. | - | Cum | 1,956 | - |
| 2 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | 1 | %Cum | 11,927 | ₹11,915.07 |
| 3 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. | 70 | Sq.M | 324 | ₹22,680 |
| 4 | (I) Cement concrete with graded stone ballast (40 mm size excluding shuttering) In ground floor,(A) [Pakur Variety] (a) 1:3:6 proportion | 10 | Cu.m | 4,702.53 | ₹47,025.3 |
| 5 | Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. a) Pakur Variety | - | Cu.M | 5,122.38 | - |
| 6 | Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) (c) Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work | - | Sq.M | 363 | - |
| 7 | Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation, basement and upto roof of ground floor/upto 4 m (i) Tor steel/Mild Steel Tor Steel Rods/HYSD/Fe 415/Fe 500/Fe 500 D(JSW/JSPL/SHYAM/SRMB/BMASL/ELECTROSTEEL/SSL) In Ground floor | - | MT | 54,800.27 | - |
| 8 | (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) (B) Do - by fine sand | - | %Cu.m | 64,086 | - |
| 9 | Brick work with 1st class bricks in cement mortar (1:6) (a) In foundation and plinth | - | Cu.M. | 4,767.06 | - |
| 9.01 | Brick work with 1st class bricks in cement mortar (1:6) (b) In superstructure, ground floor | - | Cu.M. | 4,990.06 | - |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.14 MB
STANDARD_BID_DOCUMENT_2911.pdf
Tender Documents • 0.54 MB
BOQ_5081803.xls
BOQ • 0.37 MB