Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.5 CrAdmitted-Finance I G NAGAR JAGATHPURA JAIPUR RAJ 30201 | 30201 | ₹13.5 Cr | L1 | Admitted-Finance |
| 2 | L2₹13.8 CrAdmitted-Finance 1 513 VIDHYADHAR NAGAR JAIPUR 302039 RAJASTHAN | JAIPUR | RAJASTHAN | 302039 | ₹13.8 Cr | L2 | Admitted-Finance |
| 3 | L3₹15.3 CrAdmitted-Finance | ₹15.3 Cr | L3 | Admitted-Finance |
| Sl No | Description | Qty | Unit | Dullar Real Estate Pvt. Ltd L3 | LNA Infraprojects Pvt. Limited L2 | M/s Kishan Sahay Meena L1 |
|---|---|---|---|---|---|---|
| 1.00 | Polished Blue Kota Stone flooring skirting, laid over 20 mm thick base of C.M. 1:4 and joint/Spacer 25 mm wide 9 mm deep marble chip mix with marble chips of approved color & 4 mm to 7 mm nominal size laid in White cement, marble chips 2:3 (2-Cement:3-marble chips) by volume. including cost of all material labour ,hire charges and power required.Each slab surrounded by 25 mm terazzo (Marble Chips + white cement mix) spacer in situ all around slab. including rubbing and polishing complete. Area of each slab up to 2001 to 5000 Sq. Cm. Light Shade Pigment With White Cement. (Area of total floor to be measured) up to floor 3 levels | 4,748.25 | P.Sqm | 1,500 ₹71.2 L | 1,050 ₹49.9 L | 801 ₹38.0 L |
| 2.00Providing and Fixing Backstop unit (Basketball poles). There shall be two (2) backstop units, and each consisting of the following parts: • One (1) backboard. • One (1) basket ring with a ring mounting plate. • One (1) basket net. • One (1) basket support structure. • Padding etc. with following specifications The backboards shall be made of a suitable transparent material (of a tempered safety glass), made in one (1) piece, non reflective, with a flat front surface and shall: • Have a protective framework of the backboard support structure around the outer edge. • Be manufactured such that, if broken, the pieces of glass do not split off. The backboards shall measure 1,800 mm (+ a maximum of 30 mm) horizontally and 1,050 mm (+ a maximum of 20 mm) vertically. All lines on the backboards shall be: • In white, 50 mm in width. The borders of the backboards shall be marked with a boundary line and an additional rectangle behind the ring as follows: • Outside dimensions: 590 mm (+ a maximum of 20 mm) horizontally and 450 mm (+ a maximum of 8 mm) vertically. • The top edge of the base of the rectangle shall be level with the top of the ring and 150 mm (- 2 mm) above the bottom edge of the backboard. Basket ring: The rings shall be made of solid steel and shall: • Have an inside diameter of a minimum of 450 mm and a maximum of 459 mm. • Be painted orange within the following Natural Colour System (NCS) FIBA approved spectrum : 0080-Y70R 0090-Y70R 1080-Y70R • Have its metal a minimum of 16 mm and a maximum of 20 mm in diameter. The net shall be attached to each ring in 12 places. The fittings for the attachment shall: • Not have any sharp edges or gaps, • Have gaps smaller than 8 mm, to prevent fingers from entering, • Basket net. The nets shall be made of white cord and shall be: • Suspended from the rings. • Manufactured so that they check the ball momentarily as it passes through the basket. • No less than 400 mm and no more than 450 mm in length. • Manufactured with12 loops to attach it to the ring. The upper section of the net shall be semi-rigid to prevent: • The net from rebounding up through or over the ring, creating possible entanglement. The ball from becoming trapped in the net or rebounding back out of the net. | ||||||
| 2.10Backboard support structure: The rigidity of the backboard support structure with ring shall fulfil the requirements of the EN 1270 norms.The visible vibration of the backboard support unit shall end a maximum of four (4) seconds after a dunk shot. | ||||||
| 2.20 | Padding: The backboard and backboard support structure must be padded. The padding shall be of a single solid colour and shall be the same colour on both backboards and support structures. The padding shall be 20 to 27 mm thick from the front, back and side surface of the backboards. The padding shall be 48 to 55 mm thick from the bottom edge of the backboards.The padding shall cover the bottom surface of each backboard and the side surface to a distance of 350 to 450 mm from the bottom. The front and back surface must be covered to a minimum distance of 20 to 25 mm from the bottom of each backboard. All padding shall: • Be constructed so as to prevent limbs from being trapped. • Have a maximum indentation factor of 50%. This means that when a force is applied suddenly to the padding, the indentation in the padding does not exceed 50% of its original thickness. | 1 | P.Set | 50,000 ₹50,000 | 25,000 ₹25,000 | 1,00,001 ₹1.0 L |
| 3.00 | P & F of Chhatri of Jodhpur white ashlar stone over all 1.20 mtr. Height & base 0.45x0.45 mtr. with ornamantal Dasa, Pillars, Margole, Galat Chajja with Dome & Kangoora as per design & drawing as per instruction of Engineer-incharge | 2 | Each | 50,000 ₹1 L | 15,000 ₹30,000 | 11,551 ₹23,102 |
Tender Value
₹13.9 Cr
EMD Value
₹27.7 L
Closing Date
20 May 2023, 6:00 pmClosed
Superintending Engineer
RSAMB Circle P and M Jaipur
Construction of Govt. Minority Boys Residential School 200 Bedded at Sawaimadhopur Distt. Sawaimadhopur
2023_RSAMB_332788_1
RSAMB/Circle PnM JPR/NIT-01/2023-24
Open Tender
Civil Works
450 days
Sawai Madhopur
Please refer Tender documents.
5 documents required · 5 mandatory
₹5,000
EE RSAMB Tonk
₹27.7 L
Yes
RSAMB Circle P and M Jaipur
30 May 2023
27 Apr 2023
23 May 2023
27 Apr 2023
20 May 2023
12 May 2023
8 May 2023
Amount
Polished Blue Kota Stone flooring skirting, laid over 20 mm thick base of C.M. 1:4 and joint/Spacer 25 mm wide 9 mm deep marble chip mix with marble chips of approved color & 4 mm to 7 mm nominal size laid in White cement, marble chips 2:3 (2-Cement:3-marble chips) by volume. including cost of all material labour ,hire charges and power required.Each slab surrounded by 25 mm terazzo (Marble Chips + white cement mix) spacer in situ all around slab. including rubbing and polishing complete. Area of each slab up to 2001 to 5000 Sq. Cm. Light Shade Pigment With White Cement. (Area of total floor to be measured) up to floor 3 levels
Providing and Fixing Backstop unit (Basketball poles). There shall be two (2) backstop units, and each consisting of the following parts: • One (1) backboard. • One (1) basket ring with a ring mounting plate. • One (1) basket net. • One (1) basket support structure. • Padding etc. with following specifications The backboards shall be made of a suitable transparent material (of a tempered safety glass), made in one (1) piece, non reflective, with a flat front surface and shall: • Have a protective framework of the backboard support structure around the outer edge. • Be manufactured such that, if broken, the pieces of glass do not split off. The backboards shall measure 1,800 mm (+ a maximum of 30 mm) horizontally and 1,050 mm (+ a maximum of 20 mm) vertically. All lines on the backboards shall be: • In white, 50 mm in width. The borders of the backboards shall be marked with a boundary line and an additional rectangle behind the ring as follows: • Outside dimensions: 590 mm (+ a maximum of 20 mm) horizontally and 450 mm (+ a maximum of 8 mm) vertically. • The top edge of the base of the rectangle shall be level with the top of the ring and 150 mm (- 2 mm) above the bottom edge of the backboard. Basket ring: The rings shall be made of solid steel and shall: • Have an inside diameter of a minimum of 450 mm and a maximum of 459 mm. • Be painted orange within the following Natural Colour System (NCS) FIBA approved spectrum : 0080-Y70R 0090-Y70R 1080-Y70R • Have its metal a minimum of 16 mm and a maximum of 20 mm in diameter. The net shall be attached to each ring in 12 places. The fittings for the attachment shall: • Not have any sharp edges or gaps, • Have gaps smaller than 8 mm, to prevent fingers from entering, • Basket net. The nets shall be made of white cord and shall be: • Suspended from the rings. • Manufactured so that they check the ball momentarily as it passes through the basket. • No less than 400 mm and no more than 450 mm in length. • Manufactured with12 loops to attach it to the ring. The upper section of the net shall be semi-rigid to prevent: • The net from rebounding up through or over the ring, creating possible entanglement. The ball from becoming trapped in the net or rebounding back out of the net.
Backboard support structure: The rigidity of the backboard support structure with ring shall fulfil the requirements of the EN 1270 norms.The visible vibration of the backboard support unit shall end a maximum of four (4) seconds after a dunk shot.
Padding: The backboard and backboard support structure must be padded. The padding shall be of a single solid colour and shall be the same colour on both backboards and support structures. The padding shall be 20 to 27 mm thick from the front, back and side surface of the backboards. The padding shall be 48 to 55 mm thick from the bottom edge of the backboards.The padding shall cover the bottom surface of each backboard and the side surface to a distance of 350 to 450 mm from the bottom. The front and back surface must be covered to a minimum distance of 20 to 25 mm from the bottom of each backboard. All padding shall: • Be constructed so as to prevent limbs from being trapped. • Have a maximum indentation factor of 50%. This means that when a force is applied suddenly to the padding, the indentation in the padding does not exceed 50% of its original thickness.
P & F of Chhatri of Jodhpur white ashlar stone over all 1.20 mtr. Height & base 0.45x0.45 mtr. with ornamantal Dasa, Pillars, Margole, Galat Chajja with Dome & Kangoora as per design & drawing as per instruction of Engineer-incharge
Bidder Name
Amount
Dullar Real Estate Pvt. Ltd(GSTN-08AABCD6980C1ZP)
LNA Infraprojects Pvt. Limited(GSTN-08AADCL1585B1ZQ)
M/s Kishan Sahay Meena(GSTN-NA)
LNA Infraprojects Pvt. Limited
Dullar Real Estate Pvt. Ltd
LNA Infraprojects Pvt. Limited
Dullar Real Estate Pvt. Ltd
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.96 MB
Tendernotice_2.pdf
PDF • 0.49 MB
Tendernotice_3.pdf
PDF • 0.34 MB
Tendernotice_4.pdf
PDF • 0.12 MB
Tendernotice_5.pdf
PDF • 0.43 MB
Tendernotice_6.pdf
PDF • 0.03 MB
Bid-Doc-Minority-SWM.pdf
Tender Documents • 0.51 MB
BOQ_590547.xls
BOQ • 1.21 MB
Tech-Bid-SWM.pdf
Tender Documents • 0.43 MB
Download all tender documents and submit your bid