| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹6.0 CrAdmitted-Finance B 163 SWARN JAYANTI PURAM GHAZIABAD GHAZIABAD GHAZIABAD GHAZIABAD UTTAR PRADESH 201001 | GHAZIABAD | UTTAR PRADESH | 201001 | ₹6.0 Cr | Admitted-Finance |
| 2 | ₹6.4 CrAdmitted-Finance FLAT NO 5 IIND FLOOR IIIRD B 2 NEHRU NAGAR GHAZIABAD UP 201001 | GHAZIABAD | GHAZIABAD | UTTAR PRADESH | 201001 | ₹6.4 Cr | Admitted-Finance |
| 3 | Rejected-Technical | - | Rejected-Technical NOT COMPLETE FULL FILLED TECHNICAL QUALIFICATION |
| Sl No | Description | Qty | Unit | CAPITAL ELECTECH PVT LTD | JSP Projects Private Limited |
|---|---|---|---|---|---|
| 1.00 | 33KV 3x300 sq mm XLPE cable | 2,700 | Mtr | 1,460 ₹39.4 L | 1,880 ₹50.8 L |
| 2.00 | 33KV ST/Th C/J kit 3x300 sq mm | 10 | No | 15,000 ₹1.5 L | 21,556 ₹2.2 L |
| 3.00 | 33KV End termination O/Door 3x300 sq mm | 8 | No | 6,000 ₹48,000 | 8,767 ₹70,136 |
| 4.00 | 33/11 KV Power T/F 5 MVA | 2 | No | 36,10,000 ₹72.2 L | 41,13,762 ₹82.3 L |
| 5.00 | 33 KV L.A. | 3 | No | 5,800 ₹17,400 | 7,673 ₹23,019 |
| 6.00 | 33 KV I/door J/C kit 3x300 sqmm | 6 | No | 5,800 ₹34,800 | 7,518 ₹45,108 |
| 7.00 | 33 KV O/door J/C kit 3x300 sqmm | 6 | No | 6,000 ₹36,000 | 7,917 ₹47,502 |
| 8.00 | 11 KV 3x70 sq mm XLPE cable | 30 | Mtr | 411 ₹12,330 | 525 ₹15,750 |
| 9.00 | 11 KV O/Door C/J kit 3x300 sq mm | 4 | No | 3,800 ₹15,200 | 4,000 ₹16,000 |
| 10.00 | 11 KV I/Door C/J kit 3x300 sq mm | 8 | No | 3,600 ₹28,800 | 3,864 ₹30,912 |
Tender Value
₹7.1 Cr
EMD Value
₹7.1 L
Closing Date
2 Dec 2020, 5:00 pmClosed
SE EUCC-V LESA LUCKNOW
Lesa Bhawan Near Residency Lucknow
CONSTRUCTION OF GIS BASED (GAS INSULATED SUB STATION) 33/11 KV SUBSTATION VIKARMADITYA MARG, LUCKNOW AND ITS ASSOCIATED WORKON TURNKEY BASIS
2020_MVVNL_533508_1
24/EUCC(V)/LESA/2020-21
Open Tender
Electrical Works
180 days
VIKARMADITY MARG, LUCKNOW
AS PER TENDER DOCUMENT
2 documents required · 2 mandatory
₹5,900
A/c.No. 10101985364,IFSC CODE No. SBIN0003347,SBI
₹7.1 L
28 Dec 2020
27 Nov 2020
3 Dec 2020
27 Nov 2020
2 Dec 2020
27 Nov 2020
33KV 3x300 sq mm XLPE cable
33KV ST/Th C/J kit 3x300 sq mm
33KV End termination O/Door 3x300 sq mm
33/11 KV Power T/F 5 MVA
33 KV I/door J/C kit 3x300 sqmm
33 KV O/door J/C kit 3x300 sqmm
11 KV 3x70 sq mm XLPE cable
11 KV O/Door C/J kit 3x300 sq mm
11 KV I/Door C/J kit 3x300 sq mm
11 KV end termination C/J kit for 3x70 sq mm
11/0.4 KV T/F 63 KVA
PVC Cable 3.5x70 sq mm
24 Volt Battery set with battery Charger
33 KV Line isolator 400 A
11 KV XLPE Cable 3x300 sq mm
11 KV XLPE Cable 3x185 sq mm
11 KV O/Door C/J kit 3x185 sq mm
11 KV I/Door C/J kit 3x185 sq mm
33 KV GIS panel set (2I/C+1B/C+1 B/R+2 O/G)
11 KV VCB Panel set(2I/C+1B/C+1B/R+8 O/G)
STP 11 M long
33 KV pin insulator
33 KV pin with nut
MS Round bar 32 mm
12.65 KV,1980 kVAr, 3-Phase, 50 C/s, Outdoor Type , Capacitor bank (for 1.98 Mvar Capacitor Bank) with all accessories and structure.
11 kV, 400 Amp, Off Load Isolator with earth switch and mounting structure.
9 kV, 10 kA,Station Class, Lightning Arrestors
Indoor Type Automatic Control Unit
Dismantling of existing building and cleaning of area
11 KV VCB Switchgear with complete arrangement for connection with existing 11 KV bus bar.
11 KV Smart Type Automatic RMU
Supply and Fixing of suitable size of pregalvenized, powder coated cable tray in control room/required place
Providingand fixing thermal insulation of ceiling (under deck insulation) with Resin Bonded Rockwool conforming to IS: 8183, density 48 kg/ m3, 50 mm thick, wrapped in 200 G Virgin Polythene bags fixed to ceiling with metallic cleats (50x50x3 mm) @ 60 cm and wire mesh of 12.5mm x 24 gauge wire mesh, for top most ceiling of building.
Cable stand with foundation
Neutral Stand structure with foundation
Structure for 33 KV Line Isolator with Plinth and foundation
Structure for 33 KV L.A. with Plinth and foundation
Structure for 11 KV L.A. with Plinth and foundation
60X8 mm Galvenized Flat for riser
Construction of Wiremesh fencing with toe wall
Cost of Power Transformer Plinth with Rail Piece 90 LBS -4 mtr long 2 nos .
T/F plinth for replacement of existing 11/0.4 KV distribution transformer with RCC Top 1.5x1.5x1.2 Mtr.
Opening of Jumpers of HT & LT connection and removal of earthing of 11/0.4 KV 400/630 KVA distibution transformers and dismantling from existing place and stacking safely at suitable place.
Erection and commissioning of dismantled 11/0.4 KV T/F 400/630 KVA complete in all respect
(Station T/F) Plinth with RCC Top 1.5x1.5x1.2 Mtr.
Filling of switchyard area by gravels 20-40 mm
Laying of interlocking tiless in switchyard and other required place
Rain water harvesting system for sub station
Installation of Complete Lighting System for switchyard, control room building, main gate and sub-station boundary including fans as per Detailed Technical Specifications
Painting of Structures in SS
T & P of Sub-Station & Switchgears including chair table and primary tools etc (As per Specification)
4.5 Kg. CO2 fire extinguisher, portable type
5 kg. Dry chemical powder fire extinguisher, portable type
Fire buckets (4 nos.) with stand filled with dry sand
Rubber matting 20 sq. mm. thick size (1 X 2 mtr.)
S/S name board (SMC) with stand
Protection Board complete
Construction of Fire wall,RCC framed with fire bricks in between transformers (4.5x0.345x4.00 ) Mtr
Fabrication, erection, grouting, plinthing & painting of double pole for 33 KV cable exposure on ST. Pole 11 Mtr long with fixing of necessary clamp channel ,angle 33 KV Pin & pin insulator making double ckt 3 phase 3 wire bus bar for separate cable with single core cable including electrode earthing , no plate,danger boared,barbed wire complete in all repect as per RESPO Norms .(All the material for fabrication shall be arranged by the contractor 11 M long ST Pole &33 KV pin insulator and 33 KV pin )
Earthing of substation complete as per specification (Indoor earthing)
Earthing of substation complete by round bar 32 mm dia complete as per specification and connectin of all switchyard equipment by GI Flat 50x6 mm (Outdoor switchyard earthing)
RCC Cable trench 850x800x150 mm with cover as per drawing
Control cable trench 150x300 mm With Cover
Control cable trench 300x300 mm with cover
Pipe Boring type earthing complete minimum 30 mtr deep from ground level complete Job with connection of quipment by 50x6 mm GI Strip
Laying of Single 11 KV 3x300 sq mm XLPE cable in constructed trench
Laying of LT PVC 3.5x70 sq mm cable from 11/0.4 KV 63 KVA transformer to LT Distribution panel
Laying of 11 KV 3x70 sq XLPE cable in constructed trench
Laying of D.CKT 11 KV 3x300 sq mm XLPE cable by digging of trench 1100 mm, deep, 750 mm wide its boxing with brick,sand,stone slab after laying of cable separation of cable by brick wall up to stone slab filling and proper levelling & ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor except 11 KV 3x300 sq mm XLPE cable)
Hoisting of following sizes of 33 KV single cable on existing/erected double pole including MS pipe 3 mtr long 6'' dia including jumpering,dressing of cable with required all necessary clamps and nut, bolts.(all the material shall be arranged by contractor)
33 KV XLPE Cable 3x300 sq mm
Hoisting of 33 KV 3x300 sq mm XLPE single cable on existing/erected cable stand/33 KV panel including jumpering,dressing of cable with required all necessary clamps and nut, bolts.(all the material shall be arranged by contractor)
Construction of plinth suitable for 11 KV Ring main Unit size (1.5x1.0x1.0 M) with civil material as per site requirement.
Making proper markig of 33 & 11 KV XLPE cable by markig tape/marking tag at proper interval (every 2 mtr underneath) marking tape /tag provided by contractor
Fixing of Cable marker on cable route and dipitching of feeder name and voltage onn cable marker for 33 KV cable.
Laying of 11 KV 3x300 sq mm XLPE Double cable by digging of trench 1000 mm, deep, 750 mm wide its boxing with brick,sand,stone slabafter laying of cable separation of cable by brick wall up to stone slab filling and proper levelling & ramming. The ferruling of cable also include in this work.(all the material shall be arranged by contractor except 11 KV XLPE cable 3x300 sq mm)
Laying of single circuit 11 KV 3x300 sq mm XLPE cable in HDPE pipe size 160 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work(MS Pipe shall be arranged by the contractor)
Laying of single circuit 11 KV 3x300 sq mm XLPE cable in GI pipe size 150 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work(all the material shall be arranged by contractor except 11 KV 3x300 sq mm XLPE cable)
Laying of single circuit 11 KV 3x300 sq mm XLPE cable in Hume pipe size 200 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work. (MS Pipe shall be arranged by the contractor)
Laying of single circuit 11 KV 3x300 sq mm XLPE cable by drilling method in HDPE PIPE 160 mm dia with drilling machine The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in such a manner that RESSPO norms have been followed.(all the material shall be arranged by contractor except 11 KV 3x300 sq mm XLPE cable)
Laying of single circuit 11 KV 3x300 sq mm XLPE cable by drilling method in with drilling machine The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in a manner that RESSPO norms have been followed.(all the material shall be arranged by contractor except 11 KV 3x300 sq mm XLPE cable)
Laying of D.CKT 33 KV 3x300 sq mm XLPE cable in digging of trench 1100 mm, deep, 650 mm wide its boxing with brick,sand,stone slabafter laying of cable separation of cable by brick wall up to stone slab filling and proper levelling& ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of S.CKT 33 KV 3x300 sq mm XLPE cable in digging of trench 1100 mm, deep, 650 mm wide its boxing with brick,sand,stone slabafter laying of cable separation of cable by brick wall up to stone slab filling and proper levelling& ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of single circuit 33 KV 3x300 sq mm XLPE cable in HDPE pipe size 160 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work(all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of single circuit 33 KV 3x300 sq mm XLPE cable in GI pipe size 150 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work(all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of single circuit 33 KV 3x300 sq mm XLPE cable in Hume pipe size 200 mm dia by digging of trench as per Norms. The ferruling of cable also include in this work.(all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of single circuit 33 KV 3x300 sq mm XLPE cable by drilling method in HDPE PIPE 160 mm dia with drilling machine The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in such a manner that RESPO norms have been followed.(all the material shall be arranged by contractor except 33 KV 3x300 sq mm XLPE cable)
Laying of single circuit 33 KV 3x300 sq mm XLPE cable by drilling method with drilling machine The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in a manner that RESPO norms have been followed.
Making proper markig of cable by markig tape/marking tag at proper interval (every 0.5 mtr underneath) marking tape /tag provided by contractor
Laying of single circuit 11 KV 3x185 sq mm XLPE cable in existing constructed trench and proper dressing and ferruling.
Laying of 11 KV 3x185 sq mm XLPE twin cable by digging of trench 900 mm, deep, 650 mm wide its boxing with brick,sand,stone slab after laying of cable separation of cable by brick wall up to stone slab filling and proper levelling & ramming.The ferruling of cable also include in this work. (all the material shall be arranged by contractor by except 11 KV 3x185 sq mm XLPE cable)
Laying of 11 KV 3x185 sq mm XLPE Single ckt cable by digging of trench 900 mm, deep, 650 mm wide & filling and proper levelling& ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor by except 11 KV 3x185 sq mm XLPE cable)
Laying of 11 KV 3x185 sq mm XLPE Single ckt cable in Hume pipe 200 mm dia by digging of trench 900 mm, deep, 650 mm wide & filling and proper levelling& ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor by except 11 KV 3x185 sq mm XLPE cable)
Laying of 11 KV 3x185 sq mm XLPE Single ckt cable in GI pipe by digging of trench 900 mm, deep, 650 mm wide & filling and proper levelling& ramming. The ferruling of cable also include in this work(all the material shall be arranged by contractor except 11 KV XLPE cable 3x185 sq mm)
Laying of 11 KV 3x185 sq mm XLPE Single ckt cable in HDPE pipe 160 mm dia by digging of trench 900 mm, deep, 650 mm wide & filling and proper levelling& ramming. The ferruling of cable also include in this work (all the material shall be arranged by contractor by except 11 KV 3x185 sq mm XLPE cable)
Laying of single circuit 11 KV 3x185 sq mm XLPE cable by drilling method in HDPE PIPE 160 mm dia with drilling machine The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in such a manner that RESPO norms have been followed.(all the material shall be arranged by contractor except 11 KV 3x185 sq mm XLPE cable)
Laying of single circuit 11 KV 3x185 sq mm XLPE cable by drilling method with drilling machine. The cable shall be laid at the depth 1.5 mtr. to 3.00 mtr. from the surface of the road the cable shall be laid in such a manner that RESPO norms have been followed.
Laying of following sizes of 33 KV and 11 KV cables in cable tray with proper dressing of cable
33 KV XLPE Cable 3x300 sq mm
11 KV XLPE Cable 3x300 sq mm
11 KV XLPE Cable 3x185 sq mm
Fixing of Cable marker on cable route and dipitching of feeder name and voltage on cable marker for 11 KV cable.
High Pressure testing of 33 KV and 11 KV cables as per Norms
33 KV XLPE Cable 3x300 sq mm
11 KV XLPE cable 3x300 sq mm
11 KV XLPE cable 3x185 sq mm
Hoisting of following sizes of 11 KV single cable on existing/erected double pole including MS pipe 3 mtr long 6'' dia including jumpering,dressing of cable with required all necessary clamps and nut, bolts.
11 KV XLPE Cable 3x185 sq mm
Hoisting of 11 KV XLPE cable 3x185 sq mm single cable in 11 KV RMU/ 11 KV VCB.
Hoisting of 11 KV XLPE cable 3x300 sq mm single cable in 11 KV VCB.
Hoisting of 11 KV XLPE cable 3x300 sq mm single cable at cable stand
LT Distribution panel for suitable for 63 KVA 11/0.4 KV transformer as per drawing
Price Schedule for construction of triple story with air-conditioned switch gear Room, air-conditioned building cum office and air-conditioned collection centre,boundary wall road drain culvert,Tubewell & other associated works and furnish building maintenance free by putting tiles on floor and walls and store room for J.E. on ground floor.
Supply of following auxiliary material
Office table ( 1200x750x600 mm) as per standard.
Armed Chair
Steel Almirah
Notice Board as per norms
Key Board
Load Chart Board
Line Chart Board
S/S Board
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.06 MB
TenderDocument.pdf
Tender Documents • 6.39 MB
BOQ_805570.xls
BOQ • 0.42 MB