Tender Value
₹20.0 L
EMD Value
₹2.4 L
Closing Date
26 Oct 2026, 11:00 am
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
BDO KAUSHAMBI
OFFICE BDO KAUSHAMBI
VIKAS KHAND KAUSHAMBI MEIN VIDEO KANFRENCIG KAKSH KA NIRMAN KARYA
2026_RDUP_1191838_1
833/etender/2026-27 Dated 30.09.2026
Open Tender
Civil Works
Percentage
90 days
BDO KAUSHAMBI
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
Yes
BDO KAUSHAMBI
₹2.4 L
Yes
3 Oct 2026
3 Oct 2026
26 Oct 2026
3 Oct 2026
26 Oct 2026
3 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation in ordinary soil (loam clay or sand) including lift upto 1.50 metre and lead upto 30 M. Including filling watering and ramming of excavated earth into the trenches of into the space between the building and the sides of foundation, trenches or into the plinth and removal & disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 m from the foundation trenches. SI.No. 251. | 16.69 | cum. | 160 | ₹2,670.4 |
| 2 | Concrete with 4 Cm gauge brick ballast fine sand of 1.25 F.M. and cement in proportion of 8:4:1 in foundations and under floors including supply of all materials, labour, tools & plants etc. required for proper completion of work. SI No.275. | 2.79 | cum. | 3,900 | ₹10,881 |
| 3 | M-150 Class Brick Work 1:6 Cement and Fine Sand Mortar in foundation and plinth including supply of all materials, labour & tools & plants etc. required for proper completion of work. SI No. 305 | 8.55 | cum. | 5,100 | ₹43,605 |
| 4 | R.C.C. Work with cement approved coarse sand and 2 Cm. Gauge approved stone grit in proportions of 1:2 :4 in plinth beam excluding supplyof reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra. SI No. 283 | 1.09 | CUM | 8,500 | ₹9,265 |
| 5 | M-150 Class Brick Work 1:6 Cement and Fine Sand Mortar in super structure 9" thick wall including supply of all materials, labour & tools & plants etc. required for proper completion of work. SI No. 303.+309+310 | 11.16 | CUM | 5,723 | ₹63,868.68 |
| 6 | R.C.C. Work with cement approved coarse sand and 2 Cm. Gauge approved stone grit in proportions of 1:2 : 3 in D/W lintels etc. excluding supplyof reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra. SI No. 283 | 0.72 | CUM | 8,500 | ₹6,120 |
| 7 | R.C.C. Work with cement approved coarse sand and 2 Cm. Gauge approved stone grit in proportions of 1:1.5:3 in lighter beams excluding supplyof reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra.SI No.285 | 2.62 | CUM | 9,800 | ₹25,676 |
| 8 | R.C.C. Work with cement approved coarse sand and 2 Cm. Gauge approved stone grit in proportions of 1:1.5:3 in Slabs etc. excluding supplyof reinforcement and its bending but including its fixing and binding the same with 24 B.W.G.G.I. Binding wire and including necessary centering and shuttering etc. and supply of all materials, labour, T&P etc. required for proper completion of the work including cost of binding wire. The rate excludes making of drip course which shall be paid extra.SI No.284 | 5.88 | CUM | 9,300 | ₹54,684 |
| 9 | 20 mm thick plaster on walls in 1:4 cement & fine sand on ROOF including all material labour & T&P etc required as SI no.597 | 133 | SQM | 216 | ₹28,728 |
| 10 | 12 mm thick plaster on walls in 1:6 cement & fine sand onPLAIN faces ( INNER SIDE )including all material labour & T&P etc required as SI no.13.12D | 99.89 | SQM | 162 | ₹16,182.18 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
BOQ_2249695.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .