Loading…
Loading…
Tender Value
₹2.3 Cr
EMD Value
₹2.6 L
Closing Date
2 Jan 2026, 11:00 amClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
TRACK
14 conditions · 3 needing a document upload
For works costing more than Rs.50 lakhs - The tenderer must have minimum average annual contractual turnover of V/N or 'V' which ever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
A1 - Any track work
22 conditions · 3 needing a document upload
Submission of Annexure-V under Document Verification Certificate- As per Advance Correction Slips to GCC - 2022, the tenderers shall submit copy of certificate stating that they are not liable to be disqualified and all their statements/documents submitted along with bid are true and factual. Standard format of the certificate to be submitted by the bidder in form of Annexure V. Non-submission of the above Certificate(s) by the bidder shall result in summarily rejection of his/their bid.
Submission of Annexure-V(A) under Document Verification Certificate : In case of other than Company/Proprietary firm, Annexure-V(A) shall also be submitted by the each member of a Partnership Firm/Joint Venture (JV) /Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc., as the case may be. Non-submission of the above Certificate (s) by the bidder shall result in summarily rejection of his/their bid.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Copies of the following documents are to be uploaded: (i) Details such as Name of the tenderer/ Contractor, Validity of DSC, Complete address with pin code, Contact Number (ii) Copy of PAN Card (iii) Copy of GSTIN card
A copy of NEFT form duly filled in the details as necessary to be uploaded. (The Tenderer/ Contractor not having NEFT form may down load the empty NEFT form available in document site)
The tenderer shall clearly specify whether the tender is submitted on his own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) / Registered Society / Registered Trust / Hindu Undivided Family( HUF) / Limited Liability Partnership (LLP)etc. The tenderer(s) shall enclose the attested copies of the requisite documents(including Power of Attorney, if opted) for constitution of their concern as per clause 14 of GCC Part I and as per a) Clause 17 of GCC Part I, for JV b) Clause 18 of GCC Part I, for Partnership firm
All the instructions furnished in the Technical compliance/ Commercial Compliance/ Check-list/ Undertakings are only indicative and not exhaustive; The Tenderer shall read the GCC/Tender documents for complete details.
The tenderer shall thoroughly go through the entire tender documents and strictly adhere to the instructions and directions given therein.
If the Tenderer(s) deliberately give(s) wrong information/ or create incorrect documents in his/their offer or create circumstances for the acceptance of his/their offer, the Railway reserves the right to reject such offer at any stage.
All terms and conditions in the tender documents are binding on the Tenderers
Railway reserves the right to accept or reject any or all the tenders and to award the work in whole or in part without assigning any reason.
Unreleased Bid Security, if any, held with the Railway Administration, shall not be adjusted towards the Bid Security to be remitted.
Bid Security shall be deposited either in cash through e-payment gateway or e-BG or submitted as Bank Guarantee bond from a scheduled bank of India or as mentioned in tender documents subject to exemptions provided under para5(1) (a) of Part-1 (ITT) of GCC.
In case of submission of Bid Security in the form of Bank Guarantee, the Original Bank Guarantee (other than e-BG) should be delivered in person to the Official nominated as indicated in the Tender document within 5 working days before the closing date of submission of bids.
MAS -GDR Section - Development of Ballast depot for increasing the ballast capacity at DVR in ADEN/SPE subdivision.
MAS52OF25260E~SR
MAS52OF25260E
Open
Works - General
6 Months
Chennai, Tamil Nadu
₹0
₹2.6 L
2 Jan 2026
9 Dec 2025
19 Dec 2025
147 items across 4 schedules · ₹2,22,40,308.3 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| Pulling & positioning of rails accurately on cess including supporting rails, providing required gap and squaring at ends for renewal preparation, as directed by Engineer in-charge. | — | — | — | — | |
| 1 | Up to 40 m long rail panel | RM | 600.00 | 10.18 | 6,108 |
| Dismantling and removing rail of all section & length from track, laid on any type & density of sleeper by removing fish plates, fastenings & fish bolts and other materials including stacking all released materials within an average distance of 500 metres as directed by Engineer in-charge. Note: 1.Cutting of rails shall be paid separately. 2.Work to be done under traffic block. | — | — | — | — | |
| 2 | For Through Rail Renewal work | TRM | 300.00 | 49.89 | 14,967 |
| 3 | For Casual/Scattered Rail Renewal work | RM | 715.00 | 39.41 | 28,178.15 |
| Insertion of rails of all types & length in track, laid on any type & density of sleeper to the specified gauge under traffic block. Rates include fastening of rail with sleepers with standard set of fastenings and fixing of fish plates and bolts or, if required, providing gap for welding and stacking of released material without infringement within 250m as directed by Engineer-in-Charge. Note: Rail drilling and cutting to be paid separately. | — | — | — | — | |
| 4 | For Casual/Scattered Rail Renewal work | RM | 715.00 | 41.74 | 29,844.1 |
| Replacement of any type of sleepers in track with PSC sleepers lying on cess or at Bridge Approaches for casual renewal at isolated locations with all fittings complete to specified gauge & cross level with contractor's tools including packing and dressing of ballast, as directed by Engineer in-charge. Released materials shall be neatly stacked and handed over at specified location within an average lead of 250 m or near either side of Bridge approaches as directed. | — | — | — | — | |
| 5 | Locations other than Ballasted Deck Bridge | Each | 330.00 | 526.76 | 1,73,830.8 |
| 6 | Lubrication of Elastic Rail Clips on PSC sleepers as per procedure prescribed in latest edition of IRPWM with Railway's grease. | ERC | 7447.00 | 2.69 | 20,032.43 |
| Gas cutting of rail of various sections with contractor's tools & plants, as directed by engineer in-charge : | — | — | — | — | |
| 7 | Rail section of 52Kg and above | Each | 20.00 | 123.43 | 2,468.6 |
| Assembling complete BG Turnout on staging, clear of infringements, to correct gauge and alignment as per standard drawings with all types of rail sections over PSC sleepers at specified locations, duly leading rails, special sleepers, switches, crossings with a maximum lead of 500m, all lift & crossing of track as required and testing points with S&T staff for throw of switch etc. at station yard after levelling surface complete including lubrication of all fastenings, complete in all respect. Note: 1.Rail cutting and Drilling shall be paid separately 2. Required P.Way fittings/fastenings shall be supplied at the SSE/P.Way stores. | — | — | — | — | |
| 8 | 1 in 12 Turnout | Set | 9.00 | 51,607.11 | 4,64,463.99 |
| Assembling all types of Switches on staging, clear of infringements, to correct gauge and alignment as per standard drawings with all types of rail sections over PSC sleepers at specified locations, duly leading rails, special sleepers, switches with a maximum lead of 500m, all lift & crossing of track as required including cutting, drilling, fixing of all components, fittings etc. with housing of tongue rails as per requirement of signaling including lubrication of fittings/fastenings, complete in all respect. Note: Required P.Way fittings shall be supplied at SSE/P.Way stores. | — | — | — | — | |
| 9 | Derailing Switch | Set | 4.00 | 9,684.93 | 38,739.72 |
| Manufacturing and Supply of Alumino thermic welding portions of 52Kg/60 Kg/60EI-R260 as approved by RDSO for welding of rails 52Kg/60Kg/60EI-R260 kg for 25mm gap by the process of AT welding along with complete accessories confirming to the specification laid down in Indian Railway Standard specification No.IRST-19-2020 up to date correction slips with Single shot crucible fitted with Automatic Tapping Thimble, 3 pieces pre fabricated mould (Zircon washed) manually pressed using compressed air petrol/LPG pre heating for execution of welding of rail joint as directed by the engineer in charge at site. Note: 1. The accessories along with welding portion shall be supplied as per Annexure-I of the IRUSSOR - 2021. 2. Rate is inclusive of transportation of above to SSE/P.Way stores. | — | — | — | — | |
| 10 | For 60Kg 90 UTS Rails | Each | 306.00 | 3,289.64 | 10,06,629.84 |
| 11 | 25mm gap 'in-situ' welding during traffic block using Railway's welding portion & Welder and finishing of weld to meet the prescribed tolerances and pass all stipulated tests with all required labour, materials, consumables, tools, equipments etc. to complete the work in all respect as per IR's "Manual for Fusion Welding of Rails by Alumino - Thermic Process" with latest correction slips, including marking of welded joint, painting weld collar with anticorrosive paint, restoration of track near weld joint to original position and fixing of joggled fish plate at new weld, to be removed after passing of weld in USFD test as directed by Engineer in charge. Note: 1. Only welding portion and related accessories as per Annexure - I and Welder shall be supplied by Railways. 2. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing. 3. Required nos. of Joggled fish plates shall be supplied by Railway at nearest P. Way Stores and the same shall be returned at nearest P. Way Store or at other location as per direction of Engineer-in-Charge after release from track. | Each | 258.00 | 1,806.57 | 4,66,095.06 |
| First or Second Through Packing of track of all sleeper density including giving a general lift, as desired to eliminate sag after Deep Screening work, lifting of track, lowering of track and major realignment of curves and formation rehabilitation as per procedure prescribed in latest edition of IRPWM. Note: General lift is normally 25 mm and isolated lift may be up to 50 mm. | — | — | — | — | |
| 12 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 715.00 | 153.04 | 1,09,423.6 |
| Third or subsequent Through Packing of track for all sleeper density including picking of slacks, as required after second through packing, subsequent to Deep Screening work as per procedure prescribed in latest edition of IRPWM. This item can also be used after lifting/regrading/realignment works also. Note: General lift is normally 25 mm and isolated lift may be up to 50 mm. | — | — | — | — | |
| 13 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 715.00 | 117.72 | 84,169.8 |
| 14 | Replacing existing glued joint rail with cut rails or with glued joint rail or insertion of glued joint by cutting existing track under traffic condition by cutting rails, refixing with all rail sleeper fastenings and providing required gaps for carrying out welding as an alternative to drilling holes or joining rails with fish plates duly drilling holes as required including stacking of released material and as directed by engineer in-charge. N o t e : (1) Drilling holes & rail cutting will be paid separately. (2) Transportation of materials to the site of work from supply points, if more than 250m, shall be paid separately. | Each | 55.00 | 1,999.79 | 1,09,988.45 |
| Dismantling of existing Turnout by removing switches, rails, crossings, check rails, sleepers and all fixtures and stacking all released materials, removing ballast and muck by excavating up to required depth, preparation of formation bed, laying of pre assembled Turnout by Railway's T-28 machine, linking of track with all fittings, filling up of ballast duly screened, packing, adjusting, opening & housing of switch, testing operation of switch assembly and attending track parameters, so as to make track fit for 20 kmph speed including disposing off muck to indicated places up to free lead after the block working etc. complete. Note: Rate includes making necessary preparation for T-28 machine movement like preparation of approaches, transportation and laying of wooden sleepers/blocks, etc. | — | — | — | — | |
| 15 | 1 in 8½ Turnout | Each | 2.00 | 58,982.87 | 1,17,965.74 |
| 16 | 1 in 12 Turnout | Each | 9.00 | 67,835.63 | 6,10,520.67 |
| Dismantling of existing switch by removing switches, sleepers, fixtures and stacking all released materials, removing ballast and muck by excavating up to required depth, preparation of formation bed, laying of pre-assembled switch by Railway's T-28 machine, linking of track with all fittings, filling ballast duly screened, aligning, packing, adjusting, opening & housing of switch, testing operation of switch assembly and attending track parameters so as to make track fit for 20 kmph speed including disposing off muck to indicated places after the block working etc. complete. Note: Rate includes making necessary preparation for T-28 machine working/movement such as providing and removing rail closures, preparation of approaches, transportation and laying of wooden sleepers/blocks, etc. | — | — | — | — | |
| 17 | 1 in 8½ Switch | Each | 2.00 | 25,230.77 | 50,461.54 |
| Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable with all lead & lift etc. complete as directed by Engineer in- charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) | — | — | — | — | |
| 18 | 60 Kg - 110/90 UTS - On Running Line | Each | 74.00 | 383.76 | 28,398.24 |
| Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in- charge. Rail Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. | — | — | — | — | |
| 19 | On Running Line | Each | 170.00 | 90.38 | 15,364.6 |
| 20 | Drilling holes of specified size for bond holes with 7.2mm dia drill twist to correct spacing and location on 60kg/52kg rails on cess or under traffic block with contractor's tools and plant, equipment, consumable, labour etc complete as directed by the Engineer in charge at site. | Each | 43.00 | 53.93 | 2,318.99 |
| Loading of rails of any section and length up to 13 metres in Wagons / Truck / trailer including lead up to 50 metres and lift up to 5 metres. | — | — | — | — | |
| 21 | I n Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer. | MT | 12.60 | 165.78 | 2,088.83 |
| Loading of tongue rail, stock rail, switch assembly and crossings of any section and length, SEJ, Glued joint etc. with / without P.Way fittings and fastenings, in Wagon / Truck / trailer including lead up to 250 metre and lift up to 5 metre. | — | — | — | — | |
| 22 | I n Wagon where mechanical handling is possible and traffic block is not required or in Truck/trailer. | MT | 199.00 | 161.36 | 32,110.64 |
| Loading, unloading and hauling of 52Kg / 60Kg rail more than 13 metre and up to 39 metre length by Railway's Rail Dolly / Dip Lorry to the nominated location under traffic and line protection in case road carriage is not possible for different leads and lift up to 5 metre. | — | — | — | — | |
| 23 | For lead beyond 500 metre and up to 1 Km | MT | 12.60 | 701.48 | 8,838.65 |
| 24 | Extra to Items no. 171042 for lead beyond 1 Km for every subsequent Km or part thereof and up to 10 Km | MT | 12.60 | 87.8 | 1,106.28 |
| Unloading of rails of any section and length up to 13 metre, in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/trailer including lead up to 50 metre, lift up to 5 metre and stacking in prescribed manner. | — | — | — | — | |
| 25 | From Wagon where mechanical handling is possible a n d traffic block is not required or in Truck / trailer. | MT | 12.60 | 121.63 | 1,532.54 |
| Loading of 52kg / 60kg PSC line and special sleepers beyond 2.75 metre length including existing fittings and fastenings in Depot / Station / Mid-section between stations in a neat manner to departmental material train (DMT) or contractor's / Railway's Truck/trailer with crane or any other means including crossing of one track with free lead up to 250 metre and lift up to 5 metre, if required with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 26 | I n Wagon/Truck / trailer where mechanical handling is possible and traffic block is not required. | MT | 606.00 | 160.92 | 97,517.52 |
| Loading, leading and unloading of PSC Sleepers of 52Kg / 60Kg by Railway's Rail Dolly/ Dip Lorry to the nominated location under traffic in case road carriage is not possible for different leads and lift up to 5 metres. | — | — | — | — | |
| 27 | For lead beyond 500 metre and up to 1 Km | MT | 94.05 | 492.16 | 46,287.65 |
| 28 | Extra to Items no. 172032 for lead beyond 1 Km for every subsequent Km or part thereof and up to 10 Km | MT | 94.05 | 51.4 | 4,834.17 |
| Loading, leading and unloading of all types of P.Way fittings and all other miscellaneous m a t e r i a l except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. | — | — | — | — | |
| 29 | Lead beyond 100 Km and up to 150 Km | MT | 38.00 | 993.34 | 37,746.92 |
| 30 | Extra for every Km per MT beyond 150 Km over item no. 172047 | MT-Km | 760.00 | 3.3 | 2,508 |
| Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. | — | — | — | — | |
| 31 | Lead beyond 100 Km and up to 150 Km | MT | 817.60 | 865.12 | 7,07,322.11 |
| 32 | Extra for every Km per MT beyond 150 Km over item no. 172057 | MT-Km | 327152.00 | 3.3 | 10,79,601.6 |
| Unloading of 52kg / 60kg PSC special sleepers beyond 2.75 metre length in Depot / Station / Mid-section between stations in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track and lead up to 50 metre & lift up to 5 metre with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 33 | From Truck / Trailer | MT | 606.00 | 124.87 | 75,671.22 |
| Unloading of Switches / Crossings / SEJ Rails / Glued Joints of any rail section and length with or without P.Way fittings & fastenings in neat manner for Railway usage from departmental material train (DMT) or contractor's / Railway's Truck/Trailer with lead up to 250 metre & lift up to 5 metres. | — | — | — | — | |
| 34 | From Truck / Trailer | MT | 199.00 | 172.41 | 34,309.59 |
| Collection, segregation and stacking of various scattered P.Way materials at nominated stacking location with serviceable and un-serviceable ones separately within a lead up to 500 metre and lift up to 5 metre including crossing o f track(s) wherever necessary as directed by Engineer-in-Charge. | — | — | — | — | |
| 35 | Rails, switches, crossings, SEJ, Glued Joints, Check Rails etc. | MT | 190.00 | 500.78 | 95,148.2 |
| 36 | All type of PSC sleepers | MT | 700.05 | 539.92 | 3,77,971 |
| 37 | P.Way fittings of all types and other similar loose items | MT | 38.00 | 430.26 | 16,349.88 |
| 38 | Supply and fixing in position pre-cast cement concrete Fouling Mark as per approved drawing at station yard, duly painting the top surface and slopes with white enamel paint in two coats and inscribed letters with black of Fouling Mark, complete in all respects with all labour, materials including cement, tools and plants etc. | Each | 11.00 | 563.39 | 6,197.29 |
| 39 | Galvanisation of Railway's stretcher bars, M.S.Liners, ERCs and Plate screws by hot dip process with Zinc Coating and mass of Zinc coating shall not be less than 705 g/sqm and galvanisation thickness shall not be less than 100 microns including necessary surface preparation as per Clause-4 of IS:2629-1985. Galvanisation shall be done as per IS:2629-1985 and IS:4759-1996 with Zinc conforming to IS:209-1992, duly taking all the measures for safeguarding against embrittlement of hot-dip galvanised iron and steel products as per IS:6158-1984 with all contractor's labour, material, tools, plant, all lead, lift and crossing of tracks etc. complete and as directed by the Engineer in-charge. | MT | 1.00 | 24,335.57 | 24,335.57 |
| Hiring of machinery for minor miscellaneous works for short duration including operator/driver, fuel, lubricants and consumable. The contractor shall arrange all statutory permits as required by rules and regulations prevailing in the area of work. Payment shall be made for actual working hours at site. | — | — | — | — | |
| 40 | JCB Backhoe Loaders 3DX Plus or similar with minimum 1.10 cum bucket capacity | Hour | 264.00 | 867.49 | 2,29,017.36 |
| 41 | Hydra or similar tyre mounted Pick-n- Carry crane of 12T capacity for misc. works of handling of material | Hour | 264.00 | 1,459.19 | 3,85,226.16 |
| 42 | Manufacturing and fixing buffer stop with Railway supplied rails, cutting, including bending of rails as per plan ,with all contractor's labour, materials, tools, plants etc. and all lead and lift including crossing of track where necessary and as directed by Engineer in charge at site. Note: Excavation, fixing rails in cement concrete, drilling of holes will be paid separately. | Each | 4.00 | 17,110.32 | 68,441.28 |
| Schedule total | ₹67,14,131.78 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
NEFTForm.pdf
ATTACHMENT
MOVEMENTOFVEHICLESNEARRAILWAYTRACK.pdf
ATTACHMENT
FORMATIONBUILDINGBRIDGEPWAYWORKSJULY2024_1.pdf
ATTACHMENT
ProcedureforLCModeofPayment.pdf
ATTACHMENT
GCCACS4.pdf
ATTACHMENT
AdvanceCorrectionSlipNo6IRGCC2022.pdf
ATTACHMENT
CTRTRRandTSRworks.pdf
ATTACHMENT
TRACKWORKSJULY2024.pdf
ATTACHMENT
GCCApril2022_compressed.pdf
ATTACHMENT
eTenderformApril2022.pdf
ATTACHMENT
AdvanceCorrectionSlipNo5IRGCC2022.pdf
ATTACHMENT
AdvancecorrectionslipNo3forGCC2022.pdf
ATTACHMENT
AdvancecorrectionslipNo2forGCC2022.pdf
ATTACHMENT
AdvancecorrectionslipNo1forGCC2022.pdf
ATTACHMENT
IRGCCACS9.pdf
ATTACHMENT
Advancedcorrectionslip7.pdf
ATTACHMENT
IRGCCACS8.pdf
ATTACHMENT
GCCCorrectionSlip10.pdf
ATTACHMENT
SNWupdated28NOV25.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .