| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹24.2 LAccepted-AOC 60 ST NO 1 D GTB NAGAR NEAR KK ROAD BYPASS SHRI MUKTSAR SAHIB | ₹24.2 L Quoted ₹24.5 L | 1 | Accepted-AOC RANK 1 |
| 2 | 2₹29.7 L+₹5.3 L (21.5%)Rejected-Finance | ₹29.7 L+₹5.3 L (21.5%) | 2 | Rejected-Finance RANK 2 |
| 3 | 3₹36.4 L+₹11.9 L (48.8%)Rejected-Finance | ₹36.4 L+₹11.9 L (48.8%) | 3 | Rejected-Finance RANK 3 |
| Sl No | Description | Qty | Unit | JASKARAN SINGH GILL CONTRACTORS L1 | VIRK CONTRACTORS L2 | KARAMJIT SINGH CONTRACTOR L3 |
|---|---|---|---|---|---|---|
| 1.00 | Excavation by mechanical means(JCB or Hydraulic excavator) in trenches for pipe lines with straight or open cutting in streets or open area including and dressing sides levelling of beds of trenches to correct grade, cutting joint holes, refilling consolidation, , including the cost of , diversion for traffic, , crossing over trenches for access to the houses, watching, fencing, etc. and removal of surplus soil out side/inside the town involving lead upto 15 meter complete in all respect. | 1 | cum | 93 ₹93 Lowest | 93.78 ₹93.78 | 150 ₹150 |
| 2.00 | Earth work in excavation in foundations trenches etc. in all kinds of soil where Pick-Jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and sides of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within lead of 30 metres. | 1 | cum | 191 ₹191 Lowest | 191.74 ₹191.74 | 200 ₹200 |
| 3.00 | First class brick masonary laid in cement sand mortar 1.6 in foundation and plinth including supply recarriage of bricks cement . | 1 | cum | 6,800 ₹6,800 Lowest | 8,000 ₹8,000 | 8,500 ₹8,500 |
| 4.00 | 10mm thick cement plaster on sides walls | 1 | sqm | 175 ₹175 | 172.77 ₹172.77 Lowest | 220 ₹220 |
| 5.00 | 10mm thick cement plaster 1:4 on Floors and Top. | 1 | sqm | 134 ₹134 | 132.74 ₹132.74 Lowest | 160 ₹160 |
| 6.00 | Reinforced cement concrete 1:2:4 hand mixed but including steel reinforcement | 1 | cum | 10,500 ₹10,500 | 9,922.72 ₹9,922.72 Lowest | 10,200 ₹10,200 |
| 7.00 | Cement Conc.1:2:4 including supply, carriage & with stone ballast or shingle | 1 | cum | 5,500 ₹5,500 | 5,391.52 ₹5,391.52 Lowest | 5,700 ₹5,700 |
| 8.00 | Cement concrete 1:4:8 with brick ballast 40mm gauge mixing by manual means | 1 | cum | 4,194 ₹4,194 Lowest | 4,328.53 ₹4,328.53 | 4,700 ₹4,700 |
| 9.00 | Lowering, jointimg and cutting precast concrete NP-2 plain end pipes and collar with reinforcement, in trenches to correct gradient and alighnment, cutting of reinforcement cement concrete plain end pipes. Stringing in trenches, joining end and fixing collar with cement mortor 1:2 as per IS 458:2003 into trenches for all depths and laying out same to correct alignment, gradients,levels etc. complete in all repects. RCC Pipe NP-2 300 mm i/d pipe | 1 | metre | 149 ₹149 Lowest | 260 ₹260 | 350 ₹350 |
| 10.00 | Lowering, jointing and cutting precast concrete NP-2 plain end pipes and collar with reinforcement, in trenches to correct gradient and alighnment, cutting of reinforcement cement concrete plain end pipes. Stringing in trenches, joining end and fixing collar with cement mortor 1:2 as per IS 458:2003 into trenches for all depths and laying out same to correct alignment, gradients,levels etc. complete in all repects. RCC Pipe NP-2 150 mm i/d pipe | 1 | metre | 50 ₹50 Lowest | 70.52 ₹70.52 | 100 ₹100 |
Tender Value
₹41.8 L
EMD Value
₹83,690
Closing Date
9 Apr 2026, 9:00 amClosed
EXECUTIVE ENGINEER LDH CANAL AND GW DIVN WRD
EXECUTIVE ENGINEER LDH CANAL AND GW DIVN WRD DUGRI PHASE 1 NEAR DURGA MATA MANDIR LUDHIANA
Estimate for laying underground RCC Pipeline for the Water Course of Outlet RD 42500/TL of Kishanpura Distributary (Labour Component)
2026_WR_159161_4
439/28A
Open Tender
Civil Works - Canal
Item Rate
45 days
Kishanpura Distributary
Estimate for laying
underground RCC Pipeline for
the Water Course of Outlet RD
42500/TL of Kishanpura
Distributary (Labour
Component)
2 documents required · 2 mandatory
₹500
₹83,690
Yes
EXECUTIVE ENGINEER LDH CANAL AND GW DIVN WRD DUGRI
21 Apr 2026
3 Feb 2026
9 Apr 2026
3 Feb 2026
9 Apr 2026
3 Feb 2026
13 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation by mechanical means(JCB or Hydraulic excavator) in trenches for pipe lines with straight or open cutting in streets or open area including and dressing sides levelling of beds of trenches to correct grade, cutting joint holes, refilling consolidation, , including the cost of , diversion for traffic, , crossing over trenches for access to the houses, watching, fencing, etc. and removal of surplus soil out side/inside the town involving lead upto 15 meter complete in all respect. | 1 | cum | 1 | ₹1 |
| - | Earth work in excavation in foundations trenches etc. in all kinds of soil where Pick-Jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and sides of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within lead of 30 metres. | 1 | cum | 1 | ₹1 |
| - | First class brick masonary laid in cement sand mortar 1.6 in foundation and plinth including supply recarriage of bricks cement . | 1 | cum | 1 | ₹1 |
| - | 10mm thick cement plaster on sides walls | 1 | sqm | 1 | ₹1 |
| - | 10mm thick cement plaster 1:4 on Floors and Top. | 1 | sqm | 1 | ₹1 |
| - | Reinforced cement concrete 1:2:4 hand mixed but including steel reinforcement | 1 | cum | 1 | ₹1 |
| - | Cement Conc.1:2:4 including supply, carriage & with stone ballast or shingle | 1 | cum | 1 | ₹1 |
| - | Cement concrete 1:4:8 with brick ballast 40mm gauge mixing by manual means | 1 | cum | 1 | ₹1 |
| - | Lowering, jointimg and cutting precast concrete NP-2 plain end pipes and collar with reinforcement, in trenches to correct gradient and alighnment, cutting of reinforcement cement concrete plain end pipes. Stringing in trenches, joining end and fixing collar with cement mortor 1:2 as per IS 458:2003 into trenches for all depths and laying out same to correct alignment, gradients,levels etc. complete in all repects. RCC Pipe NP-2 300 mm i/d pipe | 1 | metre | 1 | ₹1 |
| - | Lowering, jointing and cutting precast concrete NP-2 plain end pipes and collar with reinforcement, in trenches to correct gradient and alighnment, cutting of reinforcement cement concrete plain end pipes. Stringing in trenches, joining end and fixing collar with cement mortor 1:2 as per IS 458:2003 into trenches for all depths and laying out same to correct alignment, gradients,levels etc. complete in all repects. RCC Pipe NP-2 150 mm i/d pipe | 1 | metre | 1 | ₹1 |
stage.html
html • 0.05 MB
technical_322736.pdf
techsummary_322736.pdf
finance_322736.pdf
BOQ Comparative Chart
xlsx
finsummary_322736.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.53 MB
BOQ_322736.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .