| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.4 CrAccepted-AOC NOT APPLICABLE | FARIDABAD | HARYANA | 121004 | ₹2.4 Cr | L1 | Accepted-AOC Lowest rates |
| 2 | L2₹2.6 Cr+₹23.1 L (9.59%)Rejected-AOC GURDASPUR CITY | ₹2.6 Cr+₹23.1 L (9.59%) | L2 | Rejected-AOC High rates |
Tender Value
₹2.2 Cr
EMD Value
₹4.3 L
Closing Date
22 Jan 2024, 9:30 amClosed
Executive Engineer Lehal Canal Division Patiala
Lehal Canal Division WRD Punjab Patiala
Estimate for Remodelling of Bhagwanpura Distributary system with concrete Lining with 10 percent Enhanced Capacity offtaking at RD 90200/R of 2nd Patiala Feeder (Burj Branch at RD 0-24700)
2024_WR_114791_1
37 dated 01.01.2024
Open Tender
Civil Works - Canal
Item Rate
60 days
Sangrur
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,500
Yes
₹4.3 L
Yes
Lehal Canal Division WRD Punjab Patiala
6 Mar 2024
1 Jan 2024
22 Jan 2024
1 Jan 2024
22 Jan 2024
1 Jan 2024
11 Jan 2024
Amount
ordinary jungle clearance of both banks of running distributaries, minors and drains with discharge upto 1.5 cum/s
Earth work in excavation in foundations trenches etc. in all kinds of soil where Pick-Jumper work is not involved and not exceeding 2.0 metres depth including dressing of bottom and sides of trenches, stacking the excavated soil clear from the edge of excavation and subsequent filling around masonry in 15 cm, layers with compaction including disposal of all surplus soil as directed within lead of 30 metres
Dismantling brick work tile, masonry or tile lining
Excavation of soil ( any type ) using hydraulic excavator CK 90 excavation with hydraulic excavator of 0.9 cum capacity including cutting trimming bottom and side slopes in accordance with requirement of grades and cross sections, includingall lift and combined lead upto 60 mtr.
Extra for laying earth as per specification for compaction in 20 Cm. layers and dressing including the cost of rolling and watering as per P.W.D specifications.
Earth work for lip cutting for lining of irrigation channels inclusive of all allowance leads and dressing( as per earth work statement) (a) 0-1.5mt. depth
Providing and laying Cement concrete (M-15) sleepers in bed and side slopes below the joints of concrete lining mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specifications
Cement concrete lining 75mm. thick or less laid manually for irrigation channels, using cement concrete M-15 with cement content 325 kg/cum mixed in an automatic computerized Batching & Mixing Plant and transported to the site in transit mixers with an average lead of 1 Km(FOR TRAPEZOIDAL SECTION AND CUP SECTION OF ALL RADII)
Providing and laying Cement concrete (M-15) for coping mixed in automatic computerized batching and mixing plant and transported to the site in transit mixers including supply ,carriage, loading & unloading of material complete in all respect as per design/drawing and PWD specifications
Providing and laying LDPE 150 micron over sleeper on construction joints and expansion joints complete in all respect as per design/drawing and PWD specifications
Dag Belling single kassi stroke minimum 7.5 cm. depth complete in all respect as per design/drawing and PWD specifications
Dressing of earth work ((i)) New work or remodeling work.
Shuttering for faces of concrete foundations and foundation beam & plinth beam (vertical or battering)
Extra bitumen painting at 0.69 Kg. per sqm
Putting 1:3 (Cement:water) cement slurry with cement @ 2.25 kg per sqm on prepared bed and side slopes before laying concrete on bed and side slopes
Filling construction joints with special impervious hot pour 12.5mm wide.
Filling expansion joints with special impervious hot pour 12.5mm wide.
Dressing side slopes and preparation of sub grade for lining.
Excavation of Soil using Hyraulic Excavator and hydraulic Tractor Trolly I/C cutting and loading in Trolly and transporting to the embankment locations with all lifts and leads Disposal/carraige from (a)0 upto 450m
(b) 450m upto 1Km (pacca)
(c) 450m upto 1Km (katcha)
(d) 1 km to 10 km ( pacca)
(e) 1 km to 10 km ( katcha)
Cement concrete 1:3:6 with stone ballast or shingle mixing by mechanical means using concrete mixer volumetric type
Reinforced cement concrete M-20 mechanically batch mixed using batch type concrete mixer as per IS:1791 and vibrated by needle vibrator but excluding steel reinforcement centring and shuttering in foundation and plinth.
Cold twisted detormed (Ribbed/ Tor steel) Bars (Fe 500 grade as per IS 1786-2008) , for R.C.C works, where not including in the complete rate of RCC including bending and binding placing in position complete
Earth work involved in dismantling Open flume, A.P.M. or O.S.M. type Outlets (including excavation, refilling , consolidation and dressing ) With H upto 0.5 m
Dismantling outlets including removal of dismantled material involving lead upto 100 metres. Dismantling O.F., A.P.M. Or O.S.M. type outlets involving dismantling cement masonry and removing of precast R.C. Slab With H upto 0.5 m
Adjusting A.P.M. to the correct Y and fixing in position:- In case of new outlet where no dismantling and reconstructing of gullet wall is involved
Extra labour for dressing bricks On O.F. and A.P.M. type outlets With H upto 0.5 m
Cement concrete 1:4:8 with brick balast 40mm gauge mixing by mechanical means using concrete mixer volumetric type
Reinforced cement concrete M-20 mechanically batch mixed using batch type concrete mixer as per IS:1791 and vibrated by needle vibrator but excluding steel reinforcement centring and shuttering in foundation and plinth.
First class burnt brick work laid in cement sand mortar 1:3 in foundation and plinth
Cold twisted detormed (Ribbed/ Tor steel) Bars (Fe 500 grade as per IS 1786-2008) , for R.C.C works, where not including in the complete rate of RCC including bending and binding placing in position complete
MS GARGA ASSOCIATES
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .