| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.7 CrAdmitted-Finance | ₹2.7 Cr | L1 | Admitted-Finance |
| 2 | Rejected-Technical | - | - | Rejected-Technical Technically Non-Responsive |
| Sl No | Description | Qty | Unit | Pulen Barman L1 |
|---|---|---|---|---|
| 1.00 | Medium Jungles: Clearing medium jungles and trees up to 15 cm. girth including cutting, uprooting roots and stumps, removing them from the site of the work, etc. complete as directed.(When 30% to 60 % of the area is covered by shrubs, trees etc.) | 1,760 | sqm | 17.31 ₹30,465.6 Lowest |
| 2.00 | Felling trees including uprooting roots and stumps up to 50 cm. below ground, cutting into pieces and removing the same from the site of work etc. complete as directed.
Trees above 0.50 m and up to 1 m girth: | 280 | each | 248.08 ₹69,462.4 Lowest |
| 3.00 | Cutting bamboo, uprooting roots & stumps including removing them from the site of work, etc.complete as directed. | 812 | sqm | 673.18 ₹5,46,622.16 Lowest |
| 4.00 | Uprooting bamboo clumps where bamboo already removed including removing stumps to a minimum distance of 30 m etc., complete as directed. | 705.6 | sqm | 346.28 ₹2,44,335.17 Lowest |
| 5.00 | Earth work in embankment by tractor trailer carriage by Mechanical means with locally available ordinary/normal soil excluding sandy and rocky soil free from roots & vegetation and filling in uniform layers not exceeding 25 cm thick including ploughing or roughening or benching the seats, removing all debries, breaking clods up to 4cm cube, dressing as per design section and compaction with three wheel static roller of 80-100 KN capacity in layers not exceeding 30 cm in thickness and core cutter soil test at every layer and every 500m distance, etc. complete as directed.
For initial Lead up to 1.00 Km for all lifts. | 64,229.56 | Cum | 277.53 ₹1,78,25,629.79 Lowest |
| 6.00 | Turfing with grass sods of largest possible rectangles of 12 cm. minimum thickness placed closely including dressing earth pegging with Jati bamboo split, watering till the grass grows for a lead up to 90 m and all lifts, etc. complete as directed. | 28,413.27 | sqm | 30.18 ₹8,57,512.49 Lowest |
| 7.00 | Collection of sand gravel from approved quarry containing 60% sand and 40% gravel free from disintegrated and flaky pieces of vegetation and other deleterious matters, adherent coating etc. including stacking in suitable stacks at quarry site etc. complete as directed. | 2,804 | cum | 1,929.91 ₹54,11,467.64 Lowest |
| 8.00 | Labour charge for laying of soling stone, brick bats, broken stone metal, sand gravel etc. on approach road including ramming dressing the seat and local carriage of materials up to a distance of 60 m complete as directed. | 2,804 | cum | 225.19 ₹6,31,432.76 Lowest |
| 9.00 | Construction of whole bamboo single palisading with matured Jati bamboo stacks 7.5 cm to 100 mm dia., 15 cm clear apart 1.20 m to 1.80 m above ground and 1.00 m to 1.20 m below ground with Jati bamboo inclined struts fixed 1.2 m to 1.5 m apart tied with three rows of horizontal half Jati bamboo kamies with cane/wire of 16 G to 18 G etc. complete as directed.(Using Bhaluka Bamboo at the rate of 8.67 nos./Rm & Jati Bamboo at the rate of 2.40 nos./Rm) | 890 | Rm | 1,358.08 ₹12,08,691.2 Lowest |
| 10.00 | Serviceable empty cement bags | 15,893 | each | 10.17 ₹1,61,631.81 Lowest |
Tender Value
₹2.7 Cr
EMD Value
₹5.5 L
Closing Date
12 Feb 2026, 2:00 pmClosed
Chief Engineer, WRD, Assam
O/o the Chief Engineer, WRD, Assam, AWC Basistha, Ghy 29
Construction of embankment on L/B of river Tihu from Nizkhana PWD Bridge to Charabari.
2026_DoWR_50681_1
NALBARI/2025-26/SOPD-G/I
Open Tender
Civil Works
Works
180 days
Nalbari
Please refer Tender documents.
2 documents required · 2 mandatory
₹5,000
₹5.5 L
Yes
2 Jul 2026
31 Jan 2026
12 Feb 2026
31 Jan 2026
12 Feb 2026
7 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Medium Jungles: Clearing medium jungles and trees up to 15 cm. girth including cutting, uprooting roots and stumps, removing them from the site of the work, etc. complete as directed.(When 30% to 60 % of the area is covered by shrubs, trees etc.) | 1,760 | sqm | 17.31 | ₹30,465.6 |
| 2 | Felling trees including uprooting roots and stumps up to 50 cm. below ground, cutting into pieces and removing the same from the site of work etc. complete as directed.
Trees above 0.50 m and up to 1 m girth: | 280 | each | 248.08 | ₹69,462.4 |
| 3 | Cutting bamboo, uprooting roots & stumps including removing them from the site of work, etc.complete as directed. | 812 | sqm | 673.18 | ₹5,46,622.16 |
| 4 | Uprooting bamboo clumps where bamboo already removed including removing stumps to a minimum distance of 30 m etc., complete as directed. | 705.6 | sqm | 346.28 | ₹2,44,335.17 |
| 5 | Earth work in embankment by tractor trailer carriage by Mechanical means with locally available ordinary/normal soil excluding sandy and rocky soil free from roots & vegetation and filling in uniform layers not exceeding 25 cm thick including ploughing or roughening or benching the seats, removing all debries, breaking clods up to 4cm cube, dressing as per design section and compaction with three wheel static roller of 80-100 KN capacity in layers not exceeding 30 cm in thickness and core cutter soil test at every layer and every 500m distance, etc. complete as directed.
For initial Lead up to 1.00 Km for all lifts. | 64,229.56 | Cum | 277.53 | ₹1,78,25,629.79 |
| 6 | Turfing with grass sods of largest possible rectangles of 12 cm. minimum thickness placed closely including dressing earth pegging with Jati bamboo split, watering till the grass grows for a lead up to 90 m and all lifts, etc. complete as directed. | 28,413.27 | sqm | 30.18 | ₹8,57,512.49 |
| 7 | Collection of sand gravel from approved quarry containing 60% sand and 40% gravel free from disintegrated and flaky pieces of vegetation and other deleterious matters, adherent coating etc. including stacking in suitable stacks at quarry site etc. complete as directed. | 2,804 | cum | 1,929.91 | ₹54,11,467.64 |
| 8 | Labour charge for laying of soling stone, brick bats, broken stone metal, sand gravel etc. on approach road including ramming dressing the seat and local carriage of materials up to a distance of 60 m complete as directed. | 2,804 | cum | 225.19 | ₹6,31,432.76 |
| 9 | Construction of whole bamboo single palisading with matured Jati bamboo stacks 7.5 cm to 100 mm dia., 15 cm clear apart 1.20 m to 1.80 m above ground and 1.00 m to 1.20 m below ground with Jati bamboo inclined struts fixed 1.2 m to 1.5 m apart tied with three rows of horizontal half Jati bamboo kamies with cane/wire of 16 G to 18 G etc. complete as directed.(Using Bhaluka Bamboo at the rate of 8.67 nos./Rm & Jati Bamboo at the rate of 2.40 nos./Rm) | 890 | Rm | 1,358.08 | ₹12,08,691.2 |
| 10 | Serviceable empty cement bags | 15,893 | each | 10.17 | ₹1,61,631.81 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.20 MB
nalbari_bid.pdf
Tender Documents • 0.66 MB
BOQ_80661.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .