| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹272.7 CrAccepted-AOC SUITE 4A 2 5 SARAT BOSE ROAD KOLKATA WB 700020 | KOLKATA | KOLKATA | WB | 700020 | ₹272.7 Cr | L1 | Accepted-AOC BEING L1 |
| 2 | L2₹344.7 CrRejected-Finance | ₹344.7 Cr | L2 | Rejected-Finance NOT BEING L1 |
| 3 | Rejected-Technical | - | - | Rejected-Technical The bidder does not fulfill the eligibility criteria as per NIT. |
Tender Value
₹248.0 Cr
EMD Value
₹50 L
Closing Date
14 Jul 2023, 5:00 pmClosed
GM CMC NCL
CMC DEAPRTMENT NCL HQ SINGRAULI
Planning, Design, Engineering, Construction and other works for Coal Handling Plant at Khadia project as per NIT
2023_NCL_280513_1
GM(CMC)/NCL/NIT/KHD CHP/105 Date 31.05.2023
Turnkey
Civil Works - Others
2555 days
KHADIA OCP
AS PER NIT
8 documents required · 8 mandatory
₹50 L
NCL HQ SINGRAULI
8 Jan 2024
31 May 2023
15 Jul 2023
31 May 2023
14 Jul 2023
7 Jun 2023
31 May 2023 - 3 Jul 2023
6 Jun 2023
Amount
A. WORK & SERVICES
Detailed survey of the area, within the battery limits & submission of reports
Sub soil exploration, field and laboratory testing of samples & submission of reports
3. Design Engineering Cost
Preparation and submission of system engineering drawings as per system requirements
GA & detail engineering designs and drawings of all civil and structurals included in the system and scope of works
G.A. & detailed engineering designs and drawings including working and maintenance manuals of : i) All individual equipment ( Mechanical & Electricals) ii) Dust Control & Pressurisation system. iii) Fire-fighting and plant cleaning system. iv) Chutes & Liners v) Communication system vi) Power Supply System vii)Illumination system. ix) Plant control system x) OHE System x) Any other system/unit to match the scope of work & requirement
Documentation as per tender specification
B. CIVIL & STRUCTURAL WORKS
I. Civil and structural work
Truck Receving Hopper (4x100 Te) including RCC retaining wall
Truck Receving Platform including Pavement over approach ramp
Conveyor Gantry/Gallery with supporting structures
Transfer House/Drive Houses , Sampling House
15000 Te Over Ground Bunker including maintenance bay
2x 500 Te Surge Hopper including liftwell
RCC Rail Over Bridge for 190T dumper including ramp on both side, wing walls and ramp for coal transport road
Temporary diversion of dumper road to workshop
CTR and LMV road near Bunker area
II. Developmental work and infra-structure
CHP Office Complex: CHP office, Rest Shelter, First Aid centre, Time & Security office, LMV/Car Parking Shed and Scooter/motor cycle Shed.
Store cum maintenance workshop
1 nos. Pump house
2 Nos. Electrical Sub-station building
Lighting Mast
Internal Approach road/ Service road 3.75m Wide (All Transfer houses, over Ground Bunker, Loading Stations etc. shall be connected with 3.75 m wide carriage way)
Drain
RCC Hume Pipe Culvert
RCC Culvert
Boundary Wall with gate
PVC Over Head Tank
Ground water reservoir
Filterred Water supply distribution
Collection sumps and arrangement for conveying of Industrial Effluent to existing ETP
Sewerage
Landscaping and Arboriculture
Site Development (includes Embankment for road, chanellising of nallah, levelling and storm water drains)
C. PLANT & MACHINERY ( SUPPLY)
C.(a) SUPPLY : MECHANICAL
CONVEYORS
BELTING
C. EQUIPMEMT
Receiving Section Mechanical Equipment
Mechanical Equipment in Storage Section
Mechanical Equipment at Transfer house
Mechanical equipment at Loading Complex
OHE Equipment including mechanical, electrical and civil requirement
Other mechanical equipment
Dust suppression system with piping & other accessories. Condition monitoring system, Safety & firefighting system , and other misc. equipment/utility for any more item required to complete the project
C.(b) SUPPLY : ELECTRICAL
I. ELECTRICAL
Substation- A (SS-1)
Substation-A(SS-1) Power receiving arrangment from substation A(SS-1) with Lightning Arrester and Isolator with earth switch as required. 6.6/0.433 kV, 750 KVA Distribution transformer-2nos. 6.6/0.230 V (L-L), 100 kVALighting Transformer-2nos. 220V Lead Acid Battery complete with Battery Charging unit.-1 no. 6.6 kV 3 Phase, 3 Wire Switchboard 1A & 1B (Indoor ) Comprising of Incomer VCB, Buscoupler VCB and Outgoing VCBs/VCPs complete with metering and protection as required 415V,Aluminium Bus-duct as required. MCC at Substation-A Comprising of Incomer ACB, Buscoupler ACBs and Outgoing ACBs/MCCB/SFU/ Contactor as required. 6.6 kV and 415 V Capacitor with Automatic power factor correction of required capacity Banks for power factor improvement as required. 6.6 kV Double Circuit Overhead line comprising of AAAC ’Wolf’ equivalent Conductor for power supply as required. Fire detection, Alarm and Protection system.
Substation-B (SS-2)
Substation-B(SS-2) Power receiving arrangment from substation B(SS-2) with Lightning Arrester and Isolator with earth switch as required. 6.6/0.433 kV, 1000KVA Distribution transformer-2 nos. 6.6/0.230 V (L-L), 100 KVA Lighting Transformer-2 nos. 220V Lead Acid Battery complete with Battery Charging unit.-1 no. 6.6 kV 3 Phase, 3 Wire Switchboard 2A (Indoor ) Comprising of Incomer VCB, Buscoupler VCB and Outgoing VCBs/VCPs, Metering and protection as required 415V,Aluminium Bus-duct as required. MCC at Substation-C Comprising of Incomer ACB, Buscoupler ACBs and Outgoing ACBs/MCCB/SFU/ Contactor as required. 6.6 kV and 415 V Capacitor with Automatic power factor correction of required capacity Banks for power factor improvement as required. 6.6 kV Double Circuit Overhead line comprising of AAAC ’Wolf’ equivalent Conductor for power supply as required. Fire detection, Alarm and Protection system.
C. Cables
Power Cables
Control & Signalling Cables
Lighting Cables & wires
Communication Cables
D. Earthing
Plant Equipment Earthing
Structures Earthing
Earthing for Lightning Protection
Tranformer neutral Earthing
Welding Sockets and Electical & Diesel Welding Set
PLC System for Control & Automation,Interlocks, Signalling and instrumentation of entire CHP.
Remote and sequence control equipment & Accessories
Cable Trays, Cable Racks, Cable Trenches, Cable Voults etc.
Illumination System and Luminaires, Lighting poles & Towers, Lighting DBs etc.
DG sets for Emergency Power Supply.-2 nos.
Exhaust Fan, Ceiling Fan, Air Conditioner, insulating Mats etc.
Computers and Peripherals
Communication System
Traffic Control Console
C1 ERECTION, INSTALLATION & COMMISSIONING
Erection of mechanical equipment
Erection of electrical equipment
Erection of other plant and machining etc.
Trial run, and commissioning of the plant
C2 . OTHERS ITEM
Drinking water system consisting of tanks, pipes, valves, taps etc.
Plant cleaning system
Any other item left out for completion of the project
C3 . MAINTENANCE AND TRAINING
Operation of the plant for five years as described in Tender document
Maintenance of the plant for five years as described in Tender document
Training of the employer personnel as per tender document
Total impact of GST for the purpose of CTC
M/s HAMTEK TECHNOLOGIES INDIA PRIVATE LIMITED
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Download all tender documents and submit your bid