Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.8 CrAccepted-AOC FR 92 6 PHASE II SAILASHREE VIHAR CHANDRASEKHARPUR BBSR 751021 | KHORDHA | ODISHA | 751021 | ₹1.8 Cr | L1 | Accepted-AOC The work order has been issued to M/S SARALA ENGINEERINGWORKS |
| 2 | L2₹1.9 Cr+₹13.2 L (7.43%)Rejected-Finance | ₹1.9 Cr+₹13.2 L (7.43%) | L2 | Rejected-Finance Quoted amount is higher than L1 bidder |
Tender Value
₹1.7 Cr
EMD Value
₹1.7 L
Closing Date
14 Aug 2023, 5:00 pmClosed
CGM PC IDCO BBSR
IDCO Tower Saheed Nagar Janpath BBSR
Extension of 33kV line for providing power supply to Ms Wonderla Holidays Ltd.at- Revenue Plot no. 822,823 and 833 Village Kumbhara basta,Khordha. having CD 2000 KVA under electrical section Khordha-II ,Khordha
2023_IDCO_91025_2
PC/EST/E-71/2023-24
National Competitive Bid
Electrical Works
Item Rate
90 days
Kumbharabasta Khordha
Please refer tender documents
2 documents required · 2 mandatory
₹11,800
₹1.7 L
Yes
7 Dec 2023
25 Jul 2023
16 Aug 2023
25 Jul 2023
14 Aug 2023
25 Jul 2023
Amount
Part A: SITC of 1 KM, 33kV 1CX400 Sq. MM. XLPE U/G cable
Supply portion
Supply & lying of 33kV, 1Core, 400sqmm Aluminium, XLPE insulation UG Cable (SC rating of cable in kA- 37.7kA and SC rating of Armour in kA-20kA)
Supply of Straight through jointing kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, aluminium UG Cable kits for 1Core
Supply of Outdoor termination kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, HT UG Cable kits for 1Core
Supply of Indoor termination kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, HT UG Cable kits for 1Core
Supply of materials for High Density Polyethelene (HDPE) pipe 110mm diameter, PE 80- PN8 for laying of 33kV UG cable
Supply of RMU 33KV 3WAY 630A (2ISLTR+ 1BKR) (LLV)
Earthing
Earthing Conductor: 50X6 mm (2.4kg./mtr.) GI Flat for equipment, structure etc.)
Pipe Earthing 40mm. GI Pipe
FRTU and OFC for RMU SCADA Automation
Pre-Wired FRTU Panel with FRTU
Managed Layer2 Ethernet Switch (FRTU Panel)
Networking Accessories
CMR with Mounting Base for Digital Inputs
Interposing Relay for Digital Output
Battery Charger
Battery
4G Modem cum Router
Instrumentation Cable 12 C X 0.5 mm2, Armored cable for Status and Indications
Instrumentation Cable 7 C X 1.5 mm2, Armored for Control Output
Twisted Pair Shielded & Over all shielded Instrumentation Cable 5 P X 1.0 mm2, Armored for Analog Input
4 C X 2.5 mm2 Copper cable for extension of CT & PT
2 C X 4 mm2 Cable for DC Power Supply
4P X 0.36 mm2, Armored Communication Cable for MFM
Armored CAT6 SFTP Cable
Un-Armored CAT6 SFTP Cable
Multi Function Meter
Erection
Erection, Commissioning & Testing of 33kV new line by 3X1Core, 400sqmm, XLPE UG cable with one spare
Laying, Commissioning & Testing of 33kV, 1Core, 4Runs, 400sqmm, XLPE insulation (extruted type) UG cable (with one single 1core, 400sqmm, XLPE cable as spare) in trefoil formation by open trench method.
Erection of Straight through jointing kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, aluminium UG cable kits
Erection of Outdoor termination kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, HT UG cable kits
Erection of Indoor termination kits Heat Shrinkable type suitable for 33kV, 1Core, 400sqmm, HT UG cable kits
Laying of 110mm dia PE 80-PN8, HDPE pipe inside open trench.
Erection, Commissioning, Wiring and Testing of 33kV RMU
Erection of RMU 33KV 3WAY 630A (2ISLTR+ 1BKR) (LLV)
FRTU and OFC for RMU SCADA Automation
Services of FRTU Panel, Communication and Other Supplied System
Civil Work
Earth work excavation of soil
Earth work excavation of hard rock
Back filling with excavated soil outside and above the trench
Damage of asphalt/tar road and other utilities and reconstructing to bring to its original shape after laying of cable in open trench (1mtr. width)
Civil works for Prefabricated RCC foundation with supply of all materials
Prefabricated RCC foundation of 33kV RMU
Supply of GI Fencing with Gate around each RMU
Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of GI flat around pipe .
Supply and erection of GI Pipe of dia. 150mm, Class-B (8Mtr.)
Supply and Erection of Cable Route Marker along the cable route at an interval of 30mtrs with civil works
PART B: SITC of 1.71 CKM 3ph 3w 33KV OH line over 13mtr long H Pole with 100 mm2 AAAC
33 KV DP Without Isolator
Supply and Erection of 13 Mtr. Long (GI) H-Pole. Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Top Channel 100X50X6mm, 9.56 KG/Mtr., each channel length 3.25 mtr., 2 no's channel required =( 2x9.56x3.25). Complete in all respect.
Supply, fabrication and installation ofFish Plate 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280)
Supply, fabrication and installation of Double Pole Belting Channel 75X40X 4.8mm., 7.14KG/Mtr., each channel length 1.96 Mtr., 5 no's channel required =( 5x7.14x1.96)
Supply, fabrication and installation of 50x50x6mm.GI Bracing Angle, 4.5Kg./mtr., each angle length 3.432 mtr., 4 nos angle required = (4*4.5*3.432)
Supply and installation of Danger Plate, 2 no's.
Supply and installation of Back Clamp for danger Plate 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 2 no's = (2x0.59x0.510)
Supply of H.T. Stay clamp, 50x8 mm. flat, 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair)
Supply of H.T. Stay set (Complete )
Supply of H.T. Stay Insulator Type-C (2 No's.)
Supply of 7/8 SWG Stay Wire 15kg /stay
Supply of Gi Pipe Earthing 40mm. 3 Mtr. Long
Supply and installation of 50x6mm GI Flat for earthing, 2.36kg/mtr., (2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 5x2.36
Supply and installation of GI barbed wire anticlimbing device 3 Kg. Per support
Supply and installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 8 no's = (8x0.59x0.510)
SITC of 33KV pin insulator polymer. Complete in all respect as per the specification and direction of EIC.
SITC of H W fitting(B&S) 90KN,4 Bolt. Complete in all respect as per the specification of EIC.
SITC of Disc insulator (B&S) 90 KN polymer. Complete in all respect as per the specification and direction of EIC.
Supply and installation of PG Clamp for 100 sq.mm AAA conductor. Complete in all respect.
Supply and fixing of GI Nut , Bolt & Washer of different sizes (12.261 Kg each DP without Isolator). As requiered.
Black Paint
Yellow Colour Paint for Background
Civil Work
Fixing of 33KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.)
Concreting ratio 1:1.5:3 (500mmX500mmX2200mm) = 0.55Cu.mtr
Couping ratio 1:1.5:3 with dimension ( 500X500X450)= 0.1125 Cu mtr
Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of GI flat around pipe .
33 KV DP With Isolator
Supply and Erection of 13 Mtr. Long H-Pole
Supply, fabrication and installation of Top Channel 100X50X6mm, 9.56 KG/Mtr., each channel length 4.3 mtr., 2 no's channel required =( 2x9.56x4.3)
Supply, fabrication and installation of Fish Plate 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 6 no's required = (6x2.36x0.280)
Supply, fabrication and installation of Insulator Support Cahnnel 75X40X 4.8mm., 7.14KG/Mtr., each channel length 4.3 Mtr., 1 no's channel required =( 1x7.14x4.3)
Supply, fabrication and installation of Isolator Support Cahnnel 75X40X 4.8mm., 7.14KG/Mtr., each channel length 4.3 Mtr., 2 no's channel required =( 2x7.14x4.3)
Supply, fabrication and installation of Double Pole Belting Channel 75X40X 4.8mm., 7.14KG/Mtr., each channel length 4.3 Mtr., 4 no's channel required =( 4x7.14x4.3)
Supply, fabrication and installation of 50x50x6mm.GI Bracing Angle, 4.5Kg./mtr., each angle length 4.927 mtr., 4 nos angle required = (4*4.5*4.927)
Supply, fabrication and installation of Isolator Operating Down Pipe Support Cahnnel 75X40X 4.8mm., 7.14KG/Mtr., each channel length 0.8 Mtr., 1 no's channel required =( 1x7.14x0.8)
Down Pipe Diagonal Support Angle, 4.5Kg./mtr., each angle length 0.388mtr., 1 nos angle required = (1*4.5*0.388)
Supply, fabrication and installation of Down Pipe Base Support Angle, 4.5Kg./mtr., each angle length 0.34mtr., 1 nos angle required = (1*4.5*0.340)
Supply, fabrication and installation of Isolator Support Side Cahnnel 100X50X6mm, 9.56 KG/Mtr., each channel length 0.5 mtr., 2 no's channel required =( 2x9.56x0.5)
Supply and installation of Danger Plate, 2 no's.
Supply and installation of Back Clamp for danger Plate 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 2 no's = (2x0.59x0.510)
Supply of H.T. Stay clamp, 50x8 mm. flat, 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair)
Supply of H.T. Stay set (Complete )
Supply of H.T. Stay Insulator Type-C (2 No's.)
Supply of 7/8 SWG Stay Wire 15kg /stay
Supply of Gi Pipe Earthing 40mm. 3 Mtr. Long
Supply and installation of 50x6mm GI Flat for earthing, 2.36kg/mtr., (15 Mtr. For L.A, 4 Mtr for Isolator Body, 2.5 mtr. For mesh formation and 2.5 mtr. For raising)= 24x2.36
Supply and installation of GI barbed wire anticlimbing device 3 Kg. Per support
Supply and installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 8 no's = (8x0.59x0.510)
SITC of Lightning Arrester(30KV,10KA) (Station Class,class-2)
SITC of 33 KV 1250 AMP Double break (Turn & twist center rotating) isolator without earth switch with Pl(Polymer)
SITC of 33KV pin insulator polymer
SITC of H W fitting(B&S) 90KN,4 Bolt
SITC of Disc insulator (B&S) 90 KN polymer
Supply and installation of PG Clamp for 100 sq.mm AAA conductor
Supply and installation of PG Clamp for 80 sq.mm AAA conductor (For existing line T-off point)
Supply and fixing of GI Nut , Bolt & Washer of different sizes (22.15 Kg each DP with Isolator)
Black Paint
Yellow Colour Paint for Background
Civil Work
Fixing of 33KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.)
Concreting ratio 1:1.5:3 (500mmX500mmX2200mm) = 0.55Cu.mtr
Couping ratio 1:1.5:3 with dimension (500X500X450)= 0.1125 Cu mtr
Construction Earthing chamber including installation of earthing pipe.Making earthing chamber including excavation , soil treatment with bentonide powder , calculation of earth resistance, including Installation of 3Mtr GI Pipe 40mm/50mm including welding of GI flat around pipe .
33 KV Cut Point with 180 Degree Angle
Supply and Erection of 13 Mtr. Long H-Pole. Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Straight Cross Arm Channel 100 x 50 x 6 mm, 9.56 KG/mtr, each channel length 1.7 Mtr., 2 No's of Channel = (2x 9.56x1.7). Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Fish Plate 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 8 no's required = (8x2.36x0.280). Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Straight Cross Arm Top Channel 100 x 50 x 6 mm, 9.56 KG/mtr, each channel length 0.306 Mtr., 2 No's of Channel = (2x 9.56x0.306). Complete in all respect as per the specification and direction of EIC.
Supply and installatuion of Danger Plate, 1 no's. Complete in all respect as per the specification and direction of EIC.
Supply and installation of Back Clamp for danger Plate 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 1 no's = (1x0.59x0.510). Complete in all respect as per the specification and direction of EIC.
Supply and installation of GI barbed wire anticlimbing device 3 Kg. Per support. Complete in all respect as per the specification and direction of EIC.
Supply and installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510). Complete in all respect as per the specification and direction of EIC.
SITC of 33KV pin insulator polymer. Complete in all respect as per the specification and direction of EIC.
SITC of H W fitting(B&S)90KN,4 Bolt. Complete in all respect as per the specification and direction of EIC.
SITC of Disc insulator (B&S)90 KN polymer. Complete in all respect as per the specification and direction of EIC.
SITC of Earthing of Support ( Coil Type ). Complete in all respect as per the specification and direction of EIC.
No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing
PG Clamp for 100 sq.mm AAA conductor
GI Nut , Bolt & Washer of different sizes (4.879 Kg each 180 deg. Cut point)
Black Paint
Yellow Colour Paint for Background
Civil Work
Concreting ratio 1:1.5:3 (500mmX500mmX2200mm) = 0.55Cu.mtr
Couping ratio 1:1.5:3 with dimension ( 500X500X450)= 0.1125 Cu mtr
33 KV Cut Point with 90Degree Angle
Supply and Erection of 13 Mtr. Long (GI) H-Pole. Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Straight Cross Arm Channel 100 x 50 x 6 mm, 9.56 KG/mtr, each channel length 1.7 Mtr., 4 No's of Channel = (4x 9.56x1.7). Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Fish Plate 50x6 mm., 2.36 kg/Mtr., each 0.280 mtr. length, 16 no's required = (16x2.36x0.280). Complete in all respect as per the specification and direction of EIC.
Supply, fabrication and installation of Straight Cross Arm Top Channel 100 x 50 x 6 mm, 9.56 KG/mtr, each channel length 0.306 Mtr., 4 No's of Channel = (4x 9.56x0.306). Complete in all respect as per the specification and direction of EIC.
Supply and installation of Danger Plate, 1 no's. Complete in all respect as per the specification and direction of EIC.
Supply and installation of Back Clamp for danger Plate 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 1 no's = (1x0.59x0.510). Complete in all respect as per the specification and direction of EIC.
Supply and installation of GI barbed wire anticlimbing device 3 Kg. Per support. Complete in all respect as per the specification and direction of EIC.
Supply and installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510). Complete in all respect as per the specification and direction of EIC.
SITC of 33KV pin insulator polymer (4 No's each 90 Deg. Cut point). Complete in all respect as per the specification and direction of EIC.
SITC of H W fitting(B&S)90KN,4 Bolt. Complete in all respect as per the specification and direction of EIC.
SITC of Disc insulator (B&S)90 KN polymer. Complete in all respect as per the specification and direction of EIC.
SITC of Earthing of Support ( Coil Type ). Complete in all respect as per the specification and direction of EIC.
Supply and installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing. Complete in all respect as per the specification and direction of EIC.
Suply and intallation of PG Clamp for 100 sq.mm AAA conductor. Complete in all respect as per the specification and direction of EIC.
Supply of H.T. Stay clamp, 50x8 mm. flat, 3.14Kg/Mtr., 0.511 Mtr. Length, 2 no's qty. required ( 1 Pair).
Supply of H.T. Stay set (Complete )
Supply of H.T. Stay Insulator Type-C (2 No's.)
Supply of 7/8 SWG Stay Wire 15kg /stay
supply and installation GI Nut , Bolt & Washer of different sizes (11.31 Kg each 90 deg. Cut point). As required.
Black Paint
Yellow Colour Paint for Background
Civil Work
Concreting ratio 1:1.5:3 (500mmX500mmX2200mm) = 0.55Cu.mtr
Couping ratio 1:1.5:3 with dimension ( 500X500X450)= 0.1125 Cu mtr
Fixing of 33KV line Complete stay set includes 1) Turn Buckle Assembly 2) Stay Rod & Stay plate 3) Stay Insulator 4) Stay Wire. 5)Stay clamps with Nuts & bolts, including excvation, supply of 0.5Cum cement concrete foundation 1:2:4 size (500mmx500mmx800mm) using 20mm BHG metal with all labour and material (Excavation of earth will be done of size 500X500X1500 mm.)
33 KV Pin Points
Supply and Erection of 13 Mtr. Long (GI) H-Pole. Complete in all respect as per the specification and direction of EIC.
Supply and installation of 33 KV V cross Arm (GI) 22Kg each. Complte in all respect as per the specification and direction of EIC.
Supply and installation of Top bracket 100x50x6mm GI channel ( 300mm each). Complete in all respect as per the specification and direction of EIC.
Supply and installation of Danger Plate, 1 no's. Complte in all respect as per the specification and direction of EIC.
Supply and installation of Back Clamp for danger Plate 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 1 no's = (1x0.59x0.510). Complte in all respect as per the specification and direction of EIC.
Supply and installation GI barbed wire anticlimbing device 3 Kg. Per support
Supply and installation of Back Clamp for anticlimbing device 25X3 mm. flat, 0.59Kg/Mtr. Flat of 0.510mtr length 4 no's = (4x0.59x0.510). Complte in all respect as per the specification and direction of EIC.
SITC of 33KV pin insulator polymer. Complte in all respect as per the specification and direction of EIC.
SITC of Earthing of Support ( Coil Type ). Complte in all respect as per the specification and direction of EIC.
Supply and installation of No-8 GI wire (Dia 4.6mm) 0.131 KG/ Mtr.- 2 Mtr. For connecting pole with Coil earthing
Supply and fixing of GI Nut , Bolt & Washer of different sizes (1.45 Kg/ Pin Point)
Supply, paving and stringing of 100 mm2 AAAC. Complte in all respect as per the specification and direction of EIC.
Black Paint
Yellow Colour Paint for Background
Civil Work
Concreting ratio 1:1.5:3 (500mmX500mmX2200mm) = 0.55Cu.mtr
Couping ratio 1:1.5:3 with dimension ( 500X500X450)= 0.1125 Cu mtr
PART C: Construction of 33 KV Line Protecting Guarding for road crossing
Supply, fabrication and installation of Guarding Channel 75x40x4.8 mm, 7.14 KG/Mtr., each channel length 2.2 mtr., 4 no's channel required =( 2x7.14x2.2) ( For Single Pole). Complte in all respect as per the specification and direction of EIC.
Supply and installation of No-6 GI wire (0.192 kg/mtr.) for Main String. Complte in all respect as per the specification and direction of EIC.
Supply and installation of No-8 GI wire (0.131 kg/mtr.) for lacing. Complte in all respect as per the specification and direction of EIC.
Supply and installation of Eye Bolt (236mm, 16mm dia, 1.577kg/mtr.). Complte in all respect as per the specification and direction of EIC.
Supply of Gi Pipe Earthing 40mm. 3 Mtr. Long
Supply and installation of 50x6mm GI Flat for earthing, 2.36kg/mtr., (15 mtr For raising)= 15x2.36. Complte in all respect as per the specification and direction of EIC.
Civil Work
Installation of Earth Pit, Charcoal, Salt etc. including construction of earthing chamber (Size: 2'x2') and RCC slab cover.complete in all respect as per the specification and direction of EIC.
POWER FRIENDS
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .