| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹34.0 LAdmitted-Finance | ₹34.0 L | L1 | Admitted-Finance |
| 2 | L2₹48.0 LAdmitted-Finance | ₹48.0 L | L2 | Admitted-Finance |
| 3 | L3₹1.4 CrAdmitted-Finance | ₹1.4 Cr | L3 | Admitted-Finance |
| 4 | Rejected-Technical | - | - | Rejected-Technical incomplete conditions of e tender |
| 5 | Rejected-Technical | - | - | Rejected-Technical incomplete conditions of e tende |
| Sl No | Description | Qty | Unit | THERMO FAB ENGINEERS L3 | Dehu Engineering (India) Private Limited L2 | UMA ENVIRO ENGINEERING AND CONTRACTORS L1 |
|---|---|---|---|---|---|---|
| 1.00Supply of Field Internals of all Three Fields of existing ESP Installed at 145TPH/110Kg/cm2 Capacity Boiler | ||||||
| 1.01 | COLLECTING ELECTRODE TTR,TBR, 1.2 THK,A= 10395MM LONG(EFF.HT=10.55 M) quantity: 458 nos. | 1 | Each | 41,14,008 ₹41.1 L | 7,100 ₹7,100 | 9,800 ₹9,800 |
| 1.02 | e_TUBE 44.5 O/D,TTR,TBR,80 PIN SPACING,A=11235 MM LONG,NO OF SPIKE=256 NOS Quantity: 437 nos. | 1 | Each | 25,07,287 ₹25.1 L | 2,500 ₹2,500 | 4,800 ₹4,800 |
| 1.03 | TOP HANGER,TTR FOR C.E.- 480 LENGTH FOR 7 NO.OF C.E,A=3654 MM quantity:66 nos. | 1 | Each | 6,73,200 ₹6.7 L | 7,500 ₹7,500 | 2,500 ₹2,500 |
| 1.04 | BOTTOM HANGER,TTR FOR C.E.-480 LENGTH FOR 7 NO.OF C.E,A=3480 MM quantity: 66 nos. | 1 | Each | 3,36,600 ₹3.4 L | 3,900 ₹3,900 | 11,500 ₹11,500 |
| 1.05 | TIE BAR - LONG, 400 SPACING FOR e-TUBE BOTTOM GUIDE FRAME 06 nos. | 1 | Each | 11,475 ₹11,475 | 1,100 ₹1,100 | 8,000 ₹8,000 |
| 1.06 | e-TUBE BOTTOM GUIDE FRAME 10 GP [ TTR ] 400 SPACING, 3.5 M FIELD quantity: 3 nos. | 1 | Each | 1,53,000 ₹1.5 L | 50,000 ₹50,000 | 1,12,000 ₹1.1 L |
| 1.07 | e-TUBE BOTTOM GUIDE FRAME 11 GP [ TTR ] 400 SPACING, 3.5 M FIELD quantity: 3 nos. | 1 | Each | 1,72,125 ₹1.7 L | 60,000 ₹60,000 | 1,12,000 ₹1.1 L |
| 1.08 | CE bracket & Hardware quantity: 01 no. | 1 | Each | 12,750 ₹12,750 | 80,000 ₹80,000 | 80,000 ₹80,000 |
| 1.09 | SUPPORT INSULATOR (120KV)- INDIGENOUS, CYLINDERICAL Quantity: 02 nos. | 1 | Each | 76,500 ₹76,500 | 40,000 ₹40,000 | 35,000 ₹35,000 |
Tender Value
₹1.5 Cr
EMD Value
₹2.5 L
Closing Date
9 Sept 2025, 11:00 amClosed
GM
RAMALA SAHKARI CHINI MILLS LTD., RAMALA (BAGHPAT)
Supply and erection of internals of existing ESP of 145TPH/110kg/sq.cm. capacity
2025_RSCML_1071149_1
768/C/P/2025-26 dated 03.09.2025
Open Tender
Miscellaneous
30 days
RAMALA SAHKARI CHINI MILLS LTD., RAMALA (BAGHPAT)
please refer tender documents
3 documents required · 3 mandatory
₹590
RAMALA COOP SAHKARI CHINI MILL
₹2.5 L
9 Sept 2025
3 Sept 2025
9 Sept 2025
3 Sept 2025
9 Sept 2025
3 Sept 2025
3 Sept 2025 - 9 Sept 2025
Supply of Field Internals of all Three Fields of existing ESP Installed at 145TPH/110Kg/cm2 Capacity Boiler
COLLECTING ELECTRODE TTR,TBR, 1.2 THK,A= 10395MM LONG(EFF.HT=10.55 M) quantity: 458 nos.
e_TUBE 44.5 O/D,TTR,TBR,80 PIN SPACING,A=11235 MM LONG,NO OF SPIKE=256 NOS Quantity: 437 nos.
TOP HANGER,TTR FOR C.E.- 480 LENGTH FOR 7 NO.OF C.E,A=3654 MM quantity:66 nos.
BOTTOM HANGER,TTR FOR C.E.-480 LENGTH FOR 7 NO.OF C.E,A=3480 MM quantity: 66 nos.
TIE BAR - LONG, 400 SPACING FOR e-TUBE BOTTOM GUIDE FRAME 06 nos.
e-TUBE BOTTOM GUIDE FRAME 10 GP [ TTR ] 400 SPACING, 3.5 M FIELD quantity: 3 nos.
e-TUBE BOTTOM GUIDE FRAME 11 GP [ TTR ] 400 SPACING, 3.5 M FIELD quantity: 3 nos.
CE bracket & Hardware quantity: 01 no.
SUPPORT INSULATOR (120KV)- INDIGENOUS, CYLINDERICAL Quantity: 02 nos.
GASKET FOR CYLINDRICAL SUPPORT INSULATOR FOR 510 OD, 5 THK, NON-ASBESTOS quantity: 04 nos.
SHAFT INSULATOR 1016 MM quantity: 06 nos.
Rapper coil quantity: 06 nos.
Quantity: 06 nos.
TIC Quantity: 02 nos.
RTD quantity: 01 no.
Hypalon Boot quantity: 12 nos.
Worm gear clamp (Big end) quantity: 12 nos.
Worm gear clamp (small) Quantity: 12 nos.
Row card quantity:01 no.
Column card quantity: 01 no.
HMI quantity: 01 no.
DC Thyristor unit quantity: 01 no.
Dismantling, Erection/Fitting, Commisning and testing of Field Internals of all Three Fields of Thermax Make ESP Installed at 145TPH/110Kg/cm2 Capacity Boiler and Macke the ESP Complete leak proof. field supervision, tools and tackle and free technical support/helth checkup during the sesion (free off Cost) will be in the scope off the contractor . The work include 1. replacement of all the internals of 3 fields. 2. Alignment of all three fields. 3. Repairing of side casing, Ilet/outlet nozzles , hopper vibrator, doors etc.
Dehu Engineering (India) Private Limited (BID ID -5518786)
THERMO FAB ENGINEERS (BID ID -5517351)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid