₹9,100
Closing Date
28 Sept 2026, 2:00 pmDue tomorrow
SE/ES/NCTPS-I
Superintending Engineer Electrical System NCTPS I Chennai 120
NCTPS I ES Circle EM I division S Dn III -ESP Unit I Dismantling Lifting of ESP LT Switchgear Panel upto 2 5 feet and strengthening the base support frame in Unit I to protect from water flooding stagnation due to heavy rain during Annual overhau
2026_EB_706466_1
CE/NCTPS-I/SE/ES/WC-59/2026-27
Open Tender
Power/Energy Projects/Products
Works
30 days
NCTPS-I
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹9,100
Yes
21 Sept 2026
21 Sept 2026
29 Sept 2026
21 Sept 2026
28 Sept 2026
21 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Charges for Racking Out all the modules & breakers from the panel and shifting the module out side the switch gear room. Total no. of modules and breakers-84 Nos. (8Modules or breaker can be rack out and transported outside per shift). | 10.5 | Shifts | 1,913.45 | ₹20,091.23 |
| 2 | Charges for erection of scaffolding arrangements required for cable trays modification, Bus duct modification and cable laying including cost of scaffolding materials at a height of above 6m area up to 5mtr length. | 2 | Nos | 8,179.6 | ₹16,359.2 |
| 3 | Charges for temporary supporting arrangements for cables, cable trays and ESP 1A & 1B bus (to length of 10Mtr ) | 2 | Nos | 10,159.6 | ₹20,319.2 |
| 4 | Charges for removing and replacing of all the top and side cover plate of main bus bar chamber, removal of bus bar from the supporting insulator and removal of male contact, supporting insulator in ESP 1A & 1B Bus. | 1 | No | 91,590.4 | ₹91,590.4 |
| 5 | Charges for removal of existing damaged bottom base structure angle for LT panel by gas cutting in ESP 1A & 1B Bus. | 1 | No | 6,193 | ₹6,193 |
| 6 | Dismantling & Relaying of up to 7C x 1.5 / 2.5 sq.mm copper control cable. (10 cable x 5M x 2) | 100 | Meter | 28.4 | ₹2,840 |
| 7 | De-termination&termination ,glanding of up to 7C x 1.5 / 2.5 sq.mm copper control cable . | 10 | Nos | 160 | ₹1,600 |
| 8 | Dismantling & relaying of 3C x 180 sq.mm Armoured Aluminium power cable .(32 cable x 5M x 2) | 320 | Meter | 108.25 | ₹34,640 |
| 9 | Determination &Termination of 2C x 180 sq.mm Armoured Aluminium power cable . | 32 | Nos | 463 | ₹14,816 |
| 10 | Charges for loosening and removing the bolt and nuts of the LT switchgear panel fixed with adjacent panel Lifting the panel up to 2.5 feet by using chain block hydraulic trolley and hydraulic jacks. | 1 | No | 1,48,757.4 | ₹1,48,757.4 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.09 MB
BOQ_849072.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .