Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 CrAccepted-Finance | ₹1.9 Cr | L1 | Accepted-Finance LER |
| 2 | L2₹2.1 Cr+₹14.9 L (7.72%)Accepted-Finance | ₹2.1 Cr+₹14.9 L (7.72%) | L2 | Accepted-Finance AER |
| 3 | Rejected-Technical | - | - | Rejected-Technical EMD NOT ENCLOSED - REJECTED |
Tender Value
Refer Docs
EMD Value
₹3.9 L
Closing Date
2 Dec 2020, 3:00 pmClosed
THE PROJECT DIRECTOR DRDA, DINDIGUL
THE PROJECT DIRECTOR DRDA, DINDIGUL
Dindigul District - PMGSY-III Batch-I 2020-2021 - Thoppampatti block - TN-05-159
2020_RDTN_101900_1
TN05159
Open Tender
Civil Works - Roads
Item Rate
180 days
DINDIGUL
Dindigul District - PMGSY-III Batch-I 2020-2021 - Thoppampatti block - TN-05-159
5 documents required · 5 mandatory
₹0
₹3.9 L
THE PROJECT DIRECTOR DRDA, DINDIGUL
18 Feb 2021
23 Oct 2020
2 Dec 2020
23 Oct 2020
2 Dec 2020
23 Oct 2020
16 Nov 2020
Amount
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes, shrubs, saplings and trees of girth upto 300 mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000 m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per Technical Specification Clause 201 in area of thorny jungle
PICKING BT Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of scarified material with a lift upto 3 m and lead upto 1000 m as per Technical Specification Clause 301.4.
Excavation for roadwork in soil with hydraulic excavator and Tippers with disposal upto 1000m Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross-sections, and transporting to the embankment location with a lift upto 1.5 m and lead upto 1000 m as per Technical Specification Clause 302.3
Construction of Embankment with Material Obtained from Roadway Cuttting Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Filling with Cut Earth)
Construction of subgrade and earthen shoulders with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 (Using Borrow PIt earth)
Gravel Shoulder Construction of Embankment with approved materials deposited at site from road way cutting and excavation from drain and foundation of other structures graded and compacked to meet requirment of Tables 300.1 and 302 as per Technical specification Clause 301.5 (Gravel Shoulder)
Waterproofing of the shoulder surface by spraying 1kg of Terrasil or Equivalent and 1kg of Zycobond or Equivalent in the ratio of 1:1:200 with Potable Water and spraying on the surface @ 3ltrs/sqm and compacting with a static roller. Complete job, finished work to be measured
WATER BOUND MACADAM - III Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness, hand packing, rolling with three wheel 80-100 kN static roller in stages to proper grade and camber, applying and brooming, crushable screening to fill-up the interstices of coarse aggregate, watering and compacting to the required density Grading 3 as per Technical Specification Clause 405. (Grading III)
CONTROL SECTION PRIMER COAT Providing and applying primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.85 kg/sqm using mechanical means as per Technical Specification Clause 502
TACK COAT Providing and applying tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 to 0.30 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.
PREMIX CARPET Providing, laying and rolling of open-graded premix carpet of 20 mm thickness composed of 13.20mm to 5.6 mm aggregates either using penetration grade bitument or emusion to required line, grade and level to serve asa wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 KN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical specification Clause508
SEAL COAT Providing and laying seal coat sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A or Type B or Type C as per Technical Specification Clause 510..
NEW TECHNOLOGY PRIME COAT (High porosity) Providing and applying primer coat with cationic bitumen emulsion(water based) modified with Nanotechnology based Penetrative Reactive Water-soluble Organosilane material (forming water clear solution) qualifying as per the test, on prepared surface of granular base including cleaning of road surface and prime coat-mix made using 100 part Cationic Bitumen Emulsion (Grade CSS-1) and 200 parts of Nanotechnology Solution (1 kg Terraprime :200 liter water (≤1000ppm TDS) and spraying at the rate of 1.35 Kg/sqm using mechanical means as per Technical Specification.
PREMIX CARPET Providing, laying and rolling of 20mm thick open-graded Premix Carpet using Bituminous (penetration grade/modified bitumen) Binder with Nanotechnology based Organosilane Reactive Aggregate modifier material qualifying as per the test at the rate of 1 Kg per 1 ton of Binder. Providing, laying and rolling of open-graded premix carpet of 20mm thickness composed of 13.2 mm to 5.6 mm aggregates either using penetration grade or emulsion grade with Nanotechnology based material to required line, grade and level to serve as wearing course on a previously prepared base, including mixing in a suitable plant, laying and rolling with a three wheel 80-100 kN static roller capacity, finished to required level and grades to be followed by seal coat of either Type A or Type B or Type C as per Technical Specification Clause 508. (ref:Mord pg.no 5-24)
SEAL COAT Providing and laying of Seal coat modified with Nanotechnology based Organosilane Reactive Aggregate modifier material qualifying as per the test at the rate 1 Kg per 1 ton of Binder and sealing the voids in a bituminous surface laid to the specified levels, grade and cross fall using Type A, Type B and Type C as per technical specification Clauses 510.
Provision of Rumble strips with Premix Bituminous Carpet 'Provision of 15No. Rumble strips covered with premix bituminous carpet, 15-20mm high at centre, 250mm wide placed at 1m centre to centre at approved locations to control speed, marked with white strips of road marking paints
Providing and Fixing Name Board
Providing and Fixing 'Logo of PMGSY Project
Providing and Fixing 'Citizen Information Board' of PMGSY Project
Providing and Fixing 'Maintenance Information Board' of PMGSY Project
Providing and Fixing 'Cautionary, Mandatory and Informatary sign board Providing and fixing of Retro Reflected Cautionary, Mandatory signs with definitioin plate made ot of high inten sity Grade Prismatic sheeting conforming to IRC -67:2010 & ASTM D 4956-09, Type IV Specification and Fixed over 1.50m thick Aluminum sheet fixed on back support Frame of 25mm x 25mm x 3mm Mild streel angle and supported on a mild steel angle ion post 75mm x 75mm x 6 mm firmly fikxed to the ground by mean of properly designed foundation with M-15 grade cement concrete 45cm x 45cm x 60cm below ground level etc complete including 7 years warreanty for the Retro Reflective sheets as per clause 6.90 of IRC 67-2010 Specification (As per MORT & spec.NO.801)
90 Cm Equilateral traingle (Cautionary) Sign Board
60 Cm Circular (Mandatory) Sign Board
Chevron Signs 90cm Octagon (Curves)
Reflector
Road marking with hot applied Thermo plastic compound 2.5mm thickness per 250gm
Kilometre Stone Reinforced Cement concrete M15 Kilometre stone / local stone of standard design as per IRC : 8 fixing in position including painting and printing, etc as per drawing and Technical specification Clause 1703
(ii) Ordinary Kilometer stone (precast)
(iii) 200m stone (precast)
(iv) Guard stone (precast)
Construction of 1.50m Span RCC slab culvert at Ch 375 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 840 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 1530 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 1770 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 3232 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Dismantling, clearing away and carefully stacking materials useful for re-use of cut stone slabs
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 3550 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 3780 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Construction of 1.50m Span RCC slab culvert at Ch 4252 m
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurecomprisingofmasonry,cementconcrete,woodwork,steelwork,includingT&Pandscaffoldingwherevernecessary,sortingthedismantledmaterial,disposalofunerviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000masper Technical Specification Clause 202
Dismantlingofexistingstructureslikeculverts,bridges,retainingwallsandotherstructurescomprisingofbrickmasonry,includingdisposalofunserviceablematerialandstackingtheserviceablematerialwithallliftandleadof1000 m as per Technical Specification Clause 202.
Removing all types of Humepipes and stacking within a lead of 1000m including earthwork and dismantling of masonary works as per technical specification clause 202
Earth work excavation for structures as per drawing and technical specification clause 305.1 including setting out construction of shoring and bracing removoal of stupms and other materials and disposal up to a lead of 50m dressing of sides and bottom and back filling in trenches with excavated suitable material as per clause No.3000 of MoRD
Supplying and filling foundation and Basement with sand filling sand in layer not more than 15cm thick well ramped., watershhed and compacted complete with standard specification
Cement concrete 1:2.5:5 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Below sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:2:4 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
Cement concrete 1:1.5:3 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick compacting etc., complete complying with standard specifications and as directed (Above sill)
SupplyingandFabricatingandplacinginpositionMSsteelorRibbedTorSteelforallReinforcedCementConcreteworksasperthedesigngivenincludingcostofsteelandbindingwireinallfloorsetc,Completecomplyingwithstanardspecification.(MSrodorRTSbarwillbesupplieddepartmentallyatsectionstoresandcostwillberecoverdatissuerate).thebindingwireshallsuppliedby the contactor.
ProvidingandFixing20mmthickCompressibleFiberBoardinexpansionjointcompleteasperDrawingandMORDTechnicalSpecification.
ProvidingandfixingTarPaperforbearingBetweenBedBlock&Deck slab
Providing Weepholes in brick masory/stone masonry plain / reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1 (v) 20 (H) towards drawing face complete as per drawing and technical specification clauses 614, 709, 1204, 3.7
Gravelfillingbetweenbodywallincludingcostandconveyanceofgravel,labourforfilling,wateringandcompactingetccompletecomplyingwithstandardspecificationandasdirectedbythedepartmental officer.
Routine maintenance after completion of Construction work
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
v.periyasamy
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .