| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹64.7 LAdmitted-Finance | -18.67% | ₹64.7 L | L1 | Admitted-Finance |
| 2 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹79.5 L
EMD Value
₹1.6 L
Closing Date
30 Jul 2026, 4:00 pmClosed
Executive Engineer
R and B Division Karan Nagar Srinagar
Conservation/ Restoration of the Historical Temple Bohri Mohalla Chattabal Srinagar
2026_PWDJK_316759_1
etendering NIT No. 23 Karan Nagar Sgr
Open Tender
Civil Works
Percentage
180 days
Chattabal
Please refer Tender documents.
4 documents required · 4 mandatory
₹1,600
Executive Engineer
₹1.6 L
24 Aug 2026
18 Jul 2026
31 Jul 2026
18 Jul 2026
30 Jul 2026
18 Jul 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Civil Part:-
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth upto 30 cm measured at a height of 1 m above ground level and removal of rubbish upto a distance of 50 m outside the periphery of the area cleared. | 329.18 | Sqm | 12.49 | ₹4,111.46 |
| 2 | Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position with hold fast lugs or with dash fasteners of required dia and length (hold fast lugs or with dash fasteners shall be paid for separately): Second class deodar wood | 0.98 | Cum | 1,51,248.45 | ₹1,48,223.48 |
| 3 | Providing plain colour coated sheets fixed with nails and GI limpet washer (including cost of all material ,leads, lifts and carriags etc upto site of work complete) with required Head load complete. Sample and shade to be approved at site incl. cost of overlaps, scaffolding etc finished measurement to be taken at site. | 316.73 | sqm | 1,250 | ₹3,95,912.5 |
| 4 | Dismanteling of existing CGI/PGI sheets incl. stacking of same as per the instructions at site complete job. | 3,408 | Sft | 6 | ₹20,448 |
| 5 | Providing and fixing precoated galvanized iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-charge) 0.50 mm (+ 0.05 %) total coated thickness with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. | 55.76 | sqm | 706.5 | ₹39,394.44 |
| 6 | Providing and fixing precoated galvanised steel sheet roofing accessories0.50 mm (+0.05 %) total coated thickness, Zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns using self drilling/ self tapping screws complete : Ridges plain (500 - 600mm) | 85 | Rm | 508.7 | ₹43,239.5 |
| 7 | Providing and fixing plained eaves boarding. 2nd class Deodar wood 2 300x40 mm (nominal size) | 43.9 | Rm | 1,453.5 | ₹63,808.65 |
| 8 | Providing and fixing 20mm thick wooden planks ceiling (frame work for base to be paid for separately) with M.S. screws3 1st class kail wood | 38.29 | sqm | 2,040.9 | ₹78,146.06 |
| 9 | Providing hoisting and fixing trusses/purlins /rafters /posts/ post-plates or like components including cost of screws etc. complete. First class Budloo/Fir wood | 6.78 | Cum | 1,26,976.45 | ₹8,60,900.33 |
| 10 | Providing wood work in frames of false ceiling, partitions etc. sawn and fixed in position :Budloo / Fir wood | 2.76 | Cum | 40,509.4 | ₹1,11,805.94 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.57 MB
BOQ_1034815.xls
BOQ • 0.46 MB
CorrigemdiumNIT23.pdf
PDF • 0.59 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .