| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹64.2 LAccepted-AOC | L1 | Accepted-AOC L1 Tenderer | |
| 2 | L2₹66.0 L+₹1.9 L (2.88%)Rejected-Finance | L2 | Rejected-Finance L2 Tenderer |
Tender Value
₹65.0 L
EMD Value
₹65,000
Closing Date
24 Jan 2024, 3:00 pmClosed
The Additional Collector DRDA Chengalpattu
O/o The Additional Collector DRDA Chengalpattu
Providing Cement Concrete road 2 nos in Urapakkam habitation in Urapakkam village panchayat of Kattankolathur Panchayat Union of Chengalpattu District having pkg no.05 under IAF
2024_RDTN_409075_1
R.C.No.4368/2023/A14, dt.09.01.2024
Open Tender
Civil Works - Roads
Item Rate
90 days
Kattankolathur
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
₹65,000
O/o The Additional Collector DRDA Chengalpattu
11 Mar 2024
12 Jan 2024
24 Jan 2024
12 Jan 2024
24 Jan 2024
12 Jan 2024
18 Jan 2024
Amount
PART I : Providing Cement Concrete Road and RCC slab Culvert to Ghandhi Nagar Main Road in Urapakkam panchayats of Kattankolathur Panchayat Union EST AMT RS:34.64 Lakhs
CC Road : Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Centering with suttering for all cc works using MS sheet with cost and conveyance Incluidng all other labour charges etc complete
CC 1:4:8 mix using 40mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Supply and delivery of 90mm dia 10 KSC PVC pipe with cost and conveyance Incluidng all other labour charges etc complete
CC 1:1.5:3 mix using 20mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Supply and fixing of bituminous pad with cost and conveyance including all other labour charges etc complete
RCC Slab Culvert : Earth work excavation and depositing on bank with in initial lead of 10 m and initial lift of 2m in hard stiff clay, stiff black cotton soil, hard red earth,earth mixed with small sized boulders and hard gravelly soil as per SS 20B
Filling with river M. sand with cost and conveyance including all other labour charges etc complete
CC 1:4:8 mix using 40mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Centering with suttering for all cc works using MS sheet with cost and conveyance Incluidng all other labour charges etc complete Below GL
Above GL
Supply and fabrication of steel for all cc works using RTS rod with cost and conveyance including all other labour charges etc complete
RCC 1:1.5:3 mix using 20mm ISS HBG metal with cost and conveyance including all other labour charges etc complete Below GL
Above GL
PART II: Providing Cement Concrete Road to Selvaraj Nagar Periyar Salai in Urapakkam panchayats of Kattankolathur Panchayat Union EST AMT RS:30.31 Lakhs
CC Road : Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Centering with suttering for all cc works using MS sheet with cost and conveyance Incluidng all other labour charges etc complete
CC 1:4:8 mix using 40mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Supply and delivery of 90mm dia 10 KSC PVC pipe with cost and conveyance Incluidng all other labour charges etc complete
CC 1:1.5:3 mix using 20mm ISS HBG metal with cost and conveyance including all other labour charges etc complete
Supply and fixing of bituminous pad with cost and conveyance including all other labour charges etc complete
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}12%
BHARATHI
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .