| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 CrAccepted-Finance | ₹2.1 Cr | L1 | Accepted-Finance Being L1 |
| 2 | L2₹2.4 Cr+₹30.5 L (14.5%)Accepted-Finance | ₹2.4 Cr+₹30.5 L (14.5%) | L2 | Accepted-Finance Being L2 |
| 3 | L3₹2.6 Cr+₹47.3 L (22.5%)Accepted-Finance | ₹2.6 Cr+₹47.3 L (22.5%) | L3 | Accepted-Finance Being L3 |
| 4 | L4₹2.7 Cr+₹55.2 L (26.2%)Accepted-Finance | ₹2.7 Cr+₹55.2 L (26.2%) | L4 | Accepted-Finance Being L4 |
Tender Value
₹1.4 Cr
Closing Date
12 Mar 2021, 10:00 amClosed
Executive Engineer
Construction Division APWD Kamorta
C o footpath and coaltar road upto seashore and cc footpath within Kakana village Kamorta SW C o CC footpath 03 m wide for a length of 1048 m and 1.20 m wide for a length of 857 m i c 04 nos 1x1 m RCC box culvert and toe wall cum drain 5th call
2021_APWD_2449_1
13/Revised/NIT/(KMT)/2020-21
Open Tender
Civil Works - Others
Works
270 days
Kakana Kamorta
Please refer tender document
4 documents required · 4 mandatory
₹0
Exempted
15 Mar 2021
24 Feb 2021
12 Mar 2021
24 Feb 2021
12 Mar 2021
24 Feb 2021
24 Feb 2021 - 11 Mar 2021
Amount
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil.
Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m.
Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size).
1:3:6 (1 Cement : 3 coarse sand (zone-III) : 6 graded stone aggregate 20 mm nominal size).
1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size)
Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement :
1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size).
Centering and shuttering including strutting, propping etc. and removal of form for:
Foundations, footings, bases of columns, etc. for mass concrete
Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.
Suspended floors, roofs, landings, balconies and access platform
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.
Thermo-Mechanically Treated bars of grade Fe-500D or more.
Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete.
40 mm thick with 20 mm nominal size stone aggregate
12 mm cement plaster of mix :
1:4 (1 cement : 4 fine sand)
AG Construction
Shri Paresh Chandra Dhar
M/S M. R. D. CONSTRUCTION
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .