| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.7 CrAdmitted-Finance | -1.00% | ₹2.7 Cr | L1 | Admitted-Finance |
| 2 | L2₹2.8 Cr+₹8.1 L (3.03%)Admitted-Finance | +2.00% | ₹2.8 Cr+₹8.1 L (3.03%) | L2 | Admitted-Finance |
| 3 | Not Admitted-Fee/PreQual/Technical LOWER SICHEY NEAR FOREST CHECK POST GANGTOK 737101 EAST SIKKIM | GANGTOK | EAST SIKKIM | SIKKIM | 737101 | - | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹2.7 Cr
EMD Value
₹5.4 L
Closing Date
16 Jun 2026, 3:00 pmClosed
Executive Engineer
Executive Engineer FTR HQR SSB Siliguri
Construction of Intial Infrastructure at Bn HQ of 69th Bn SSB , Pakyong under Frontier Siliguri SH 07 Nos. SPT Structures i.e JBK 01 No , Admn Block 01 No, QG,QM Store 01 No, Misc Store 01 No , SOs Accom.01 No , Comdt Resi 01and toilet block 01No
2026_SSB_910266_1
FTR-SLG/39/26
Open Tender
Civil Works
Percentage
270 days
FTR HQR Siliguri
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹5.4 L
FTR HQR SSB Siliguri
24 Aug 2026
28 May 2026
17 Jun 2026
29 May 2026
16 Jun 2026
29 May 2026
1 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.Ordinary rock | 442.24 | cum | 679.6 | ₹3,00,546.3 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. | 142.5 | cum | 354.58 | ₹50,527.65 |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lif. | 426.9 | cum | 266.99 | ₹1,13,978.03 |
| 4 | Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift. | 62.62 | cum | 954.22 | ₹59,753.26 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-Ill) derived from natural sources: 8 graded stone aggregate 40 mm nominal size derived from natural sources) | 43.42 | cum | 9,279.3 | ₹4,02,907.21 |
| 6 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor etc., up to floor five level, excluding the cost of centering, shuttering and finishing:1:3:6 (1 cement : 3 coarse sand (zone-Ill) derived from natural sources: 6 graded stone aggregate 20 mm nominal size derived from natural sources) | 17.8 | cum | 12,683.99 | ₹2,25,775.02 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | 126.9 | sqm | 1,147.65 | ₹1,45,636.79 |
| 8 | Making plinth protection 50 mm thick of cement concrete 1:3:6 (1 cement : 3 coarse sand (zone-Ill) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) over 75 mm thick bed of dry brick ballast 40 mm nominal size, well rammed and consolidated and grouted with fine sand, including necessary excavation, levelling & dressing & finishing the top smooth. | 145.57 | sqm | 1,020.7 | ₹1,48,583.3 |
| 9 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3(1 cement: 1.5 coarse sand (zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 42.12 | cum | 12,322.12 | ₹5,19,007.69 |
| 10 | Reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement:1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 10.66 | cum | 14,783.89 | ₹1,57,596.27 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.40 MB
BOQ_956682.xls
BOQ • 0.55 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .