Tender Value
₹9.6 Cr
EMD Value
₹14.4 L
Closing Date
27 Aug 2026, 11:00 amClosed
Mangalore Electricity Supply Company Limited
Shivakumar G V
Reconductoring and Realignment
MESCOM/2026-27/EL/WORK_INDENT515
MESCOM/2026-27/EL/WORK_INDENT515
Open
Electrical
Two Tender Document System(Two Cover)
MESCOM Superintending Engineer Projects Corporate Office Managaluru
14 documents required · 14 mandatory
Minimum financial turnover (civil engineering construction works) not less than two times the annual payments from this contract (Rs. xxxxx Lakhs)
Satisfactoriy completed (atleast 90%) as prime contractor at-least one such similar work of value not less than Rs. xxxxxxx (80% of estimated cost of tender)
Executed in any one year the following minimum quantities of work (Cement Concrete - xxxx cum, Earthwork - xxxx cum, etc) (80% of peak rate of construction)
Tenderer or his identified Sub Contractor should possess valid Electrical License for executing building electrificatio works and should have executed similar electrical works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one year
Tenderer or his identified Sub Contractor should possess valid license for executing water supply / sanitary engineering works and should have executed similar works totallng Rs. xxxxxx (not less than 50% of electrical works) n any one year
Owning the following key and critical equipment for this work (xxxx, xxxx, xxxx)
Liquid assets and /or availability of credit facilities of no less than Rs. xxxxxx Lakhs (estimated cash flow for 3 months of peak construction period)
Total value of civl engineering works executed and payments received in the last five years (year-wise)
List of existing commitments and ongoing works
List of works for which tenders already submitted
Banker Details for reference
Construction equipment owned by the tenderer and equipment proposed to be deployed on this contract, if awarded
Reports on the financial standing of the tenderer, such as profit and loss statements and auditor’s reports for the last five years
Qualification and experience of the key technical and management personnel in permanent employment with the tenderer and those that are proposed to be deployed on this contract, if awarded
List of Financial Resources with Certificates
Requirement as per NIT
₹5,000
₹14.4 L
27 Aug 2026
19 Aug 2026
28 Aug 2026
11 Aug 2026
11 Aug 2026
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkm using Towers, 11Mtr Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No: MESCOM/2026-27/EL/WORK_INDENT515
Supply of Materials
(Amount in Rs.)
Sl. No. Particulars UOM Qty Unit Rate Total Price
1 Pre - Stressed Tubular Spun Pole 11 M Long - 500 Kg WL Nos 472 19550.40 9227788.80
2 33 KV DP Structure without Poles Nos 3 7366.80 22100.40
3 Spiral Earth Electrode Nos 472 238.80 112713.60
4 Horizontal X arm for 33kV Nos 531 2496.00 1325376.00
5 Clamps for 11 mtrs Spun Pole Nos 531 365.12 193878.72
6 HT ST Support for 33 kV Nos 412 458.40 188860.80
7 33kV M type Normal Tower+ 3 mtr Extn - 18 Nos. Design, Fabrication, Galvanising & Supply of Transmission Tower including stubs, Weight of each Tower -1.503 MT, (Weight for 18 Towers = 1.503*18=27.054MT) MT 27.05 151782.40 4106321.05
8 33kV M type Normal Tower+ 6 mtr Extn - 100 Nos. Design, Fabrication, Galvanising & Supply of Transmission Tower including stubs, Weight of each Tower -1.8185MT, (Weight for 100 Towers = 1.8185*100=181.85MT) MT 181.85 151782.40 27601629.44
9 33kV M type Normal Tower+ 9 mtr Extn - 10 Nos. Design, Fabrication, Galvanising & Supply of Transmission Tower including stubs, Weight of each Tower -2.134MT, (Weight for 10 Towers = 2.134*10=21.34MT) MT 21.34 151782.40 3239036.42
10 66KV DC Narrow based Tower - (DD+3) Normal Tower+3 mtr Extn - 7 Nos. Design, Fabrication, Galvanising & Supply of Transmission Tower including stubs, Weight of each Tower - 4.296MT, (Weight for 7 Towers = 4.296*7=30.072MT) MT 30.07 151782.40 4564400.33
11 Coyote ACSR Conductor KM 92.67 162644.40 15072256.55
12 C - Type Wedge Connector-Coyote to Coyote ACSR Nos 1209.00 1030.80 1246237.20
13 33 kV, 800 A, 25 kA Isolators, double break with manual operating mechanism, with solid core insulator, terminal connector suitable for Al. tube/conductor, marshalling box etc., complete as per technical specification-Upright without Earth Switch (Live Point Height 4750 mm) Set 3.00 107060.80 321182.40
14 H Frame for 33 KV GOS Nos 3.00 6799.52 20398.56
15 33kV Polymer Pin Insulators Nos 1782.00 907.20 1616630.40
16 33kV 70 KN Polymer Insulator (Ball & socket type) Nos 1068.00 468.00 499824.00
17 Guy set with 2 Nos. 15 Strain Insulator & concreting materials as per specification Set 178.00 1218.00 216804.00
18 Guarding Materials above 40 mtrs span Set 32.00 3744.00 119808.00
19 Grounding for towers Set 138.00 5850.88 807421.44
20 Anti Climbing Device-GI Barbed wire (12 Mtr/Kg) Kg 540.00 88.80 47952.00
21 33 KV Danger Board Nos 607.00 157.20 95420.40
22 Number Plates with Bolt & Nuts Nos 607.00 356.16 216189.12
23 Rabbit ACSR Conductor KM 2.50 78250.80 195627.00
24 Single Tension Clamps Suitable for Coyote ACSR Conductor Nos 1068.00 1682.24 1796632.32
25 Single Suspension Clamps Suitable for Coyote ACSR Conductor Nos 405.00 2064.16 835984.80
26 Galvanised Bolts & Nuts, Weight of GI Nut & Bolt for each M+3 Tower - 0.094 MT, (Weight for 18 Tower = 0.094*18= 1.692MT) MT 1.79 159913.60 286117.41
27 Galvanised Bolts & Nuts, Weight of GI Nut & Bolt for each M+6 Tower - 0.14 MT, (Weight for 100 Tower = 0.14*100= 14MT) MT 14.00 159913.60 2238790.40
28 Galvanised Bolts & Nuts, Weight of GI Nut & Bolt for each M+9 Tower - 0.1856 MT, (Weight for 10 Tower = 0.1856*10= 1.856MT) MT 1.86 159913.60 296799.64
29 Galvanised Bolts & Nuts, Weight of GI Nut & Bolt for each DD+3 66KV Tower - 0.205 MT, (Weight for Tower = 0.205*7= 1.435MT) MT 1.44 159913.60 229476.02
Amount Put to Tender (Supply+Erection +Civil) 95,941,944.54
Note: The percentage quoted in the e-procurement portal for the bid will be uniformly applied on each of the unit rates indicated above for arriving the total quoted cost.
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkm using Towers, 11Mtr Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No: MESCOM/2026-27/EL/WORK_INDENT515
Erection of Materials
(Amount in Rs.)
Sl. No Particulars Unit Qty Unit Rate Total Price
1 Erection of Poles Erection of 11 mtrs long concrete spun pole in a pit of 2.5 mtr depth Nos 472 3045.50 1437476.00 2265.997024
2 Digging of Pit 2.5 mtr depth for errection of 11mtr long tubular spun pole as per approved Drawing--Pre - Stressed Tubular Spun Pole 11 Mtr Long - 500Kg WL Nos 472 2280.77 1076523.44 1697.001488
3 Erection of DP structure excluding cost of erection of RCC poles. Including fixing of braces insulators etc., as per the approved drawings and specifications (excluding the cost of excavation, backfilling and concreting). Nos 3 4948.61 14845.83 3682.001488
4 Providing Spiral Earth Electrode type earthing (without charcoal, salt etc.,) Nos 472 111.55 52651.60 82.9985119
5 Horizontal X arm for 33kV Nos 531 306.43 162714.33 227.9985119
6 HT ST Support for 33 kV Nos 412 134.40 55372.80 100
7 Erection of 33kV M type Normal Tower+ 3 mtr Extn - 18 Nos.
a) Sorting of Tower parts, weight of tower + Bolt & Nut MT 28.84 484.96 13987.80 433
b)Setting up of stubs templates and from one location to another location (Per Location) No 18 789.60 14212.80 705
c) Assembly & Erection of Towers MT 28.84 6409.76 184877.99 5723
d) Welding of Bolts & Nuts, Total No. of Bolts & Nuts/Tower = 328, for 18 Towers No 5904 24.64 145474.56 22
e) Rivetting of Tower Bolt ends by heating using dry Acetylene gas & hammering to destroy threads to make the Tower members theft proof, Total No. of Bolts & Nuts = 10% of 5904 = 590 Nos. No 590 24.64 14537.60 22
8 Erection of 33kV M type Normal Tower+ 6 mtr Extn - 100 Nos.
a) Sorting of Tower parts, Weight of tower+ bolt & Nut MT 195.85 484.96 94979.42 433
b)Setting up of stubs templates and from one location to another location (Per Location) No 100 789.60 78960.00 705
c) Assembly & Erection of Towers MT 195.85 6409.76 1255351.50 5723
d) Welding of Bolts & Nuts, Total No. of Bolts & Nuts/Tower = 396, for 100 Towers = 39600 Nos., No 39600 24.64 975744.00 22
e) Rivetting of Tower Bolt ends by heating using dry Acetylene gas & hammering to destroy threads to make the Tower members theft proof, Total No. of Bolts & Nuts = 10% of 39600 = 3960 Nos. No 3960 24.64 97574.40 22
9 Erection of 33kV M type Normal Tower+ 9 mtr Extn - 10 Nos. a) Sorting of Tower parts, Weight of tower+ bolt & Nut MT 23.20 484.96 11249.13 433
b) Setting up of stubs templates and from one location to another location (Per Location) No 10 789.60 7896.00 705
c) Assembly & Erection of Towers MT 23.20 6409.76 148680.79 5723
d) Welding of Bolts & Nuts, Total No. of Bolts & Nuts/Tower = 474 for 10 Towers =4740 Nos., No 4740 24.64 116793.60 22
e) Rivetting of Tower Bolt ends by heating using dry Acetylene gas & hammering to destroy threads to make the Tower members theft proof, Total No. of Bolts & Nuts = 10% of 4740 = 474 Nos. No 474 24.64 11679.36 22
10 Erection of 66 kV type Normal Tower+ 3 mtr Extn - 7 Nos. a) Sorting of Tower parts, Weight of Towers + bolt& Nut MT 31.51 484.96 15279.63 433
b)Setting up of stubs templates and from one location to another location (Per Location) No 7 789.60 5527.20 705
c) Assembly & Erection of Towers MT 31.51 6409.76 201952.31 5723
d) Welding of Bolts & Nuts, Total No. of Bolts & Nuts/Tower = 570 for 7 Towers =3900 Nos., No 3900 24.64 96096.00 22
e) Rivetting of Tower Bolt ends by heating using dry Acetylene gas & hammering to destroy threads to make the Tower members theft proof, Total No. of Bolts & Nuts = 10% of 3900 = 390 Nos. No 390 24.64 9609.60 22
11 Striging of Conductor Coyote ACSR Binding of Conductor on each insulator and dead Ending on Strain or disc/strain insulator by means of Clamps KM 92.67 16128.00 1494581.76 12000
12 Erection of Isolators Assembly, Erection Alignment and Wiring including Movement from the point of Unloading to Point of Erection (Upright) Set 3 1477.28 4431.84 1319
13 Erection of H Frame Nos 3 387.07 1161.21 287.9985119
14 Digging of Pit for GUY SET Set 178 392.45 69856.10 292.0014881
15 Fixing of GUY Sets with break insulators making use of 7/3.15 mm (7/10 SWG) galvanised steel wire with turn buckle and anchoring arrangement as per approved drawing. (Excluding excavation of PIT) but using 2 strain insulators (No.15) for - Anticlimbing D - Ordinary Soil Set 178 318.53 56698.34 237.0014881
Guy concreting with Boulders, Mud & Sand (300x300x450 mm) Set 178 86.02 15311.56 64.00297619
16 Fixing guarding including fixing of necessary cross arms between HT and LT line above a span of 40 mtrs for - Anticlimbing Device - Ordinary Soil Set 32 1237.82 39610.24 920.9970238
17 Digging of pit. For providing GI Pipe type Earthing - Ordinary Soil Set 138 904.51 124822.38 672.9985119
Providing GI Pipe Earthing for lightning arresters Transformer Neutral and Transformer Metal parts (Excluding digging of pits) - Ordinary Soil Set 138 227.14 31345.32 169.0029762
18 Anti Climbing Device-GI Barbed wire (12 Mtr/Kg) (4kg/Tower-135 Nos = 540Kgs) Nos 135 49.73 6713.55 37.0014881
19 Fixing of Danger Board Nos 607 95.42 57919.94 70.99702381
20 Striging of Rabbit ACSR for Binding Mtrs 2.5 5221.44 13053.60 3885
21 Loading and unloading of poles (loading of poles to vehicles at stores and unloading at workspot) - 9 mtr RCC/PSC pole/Spun Pole 11 Mtr Nos 472 169.34 79928.48 125.9970238
22 Releasing of 9 M RCC Poles Nos 269 1198.71 322452.99 891.8973214
23 Releasing of IB pole Nos 75 1198.71 89903.25 891.8973214
24 Releasing of Iron pole Nos 5 1198.71 5993.55 891.8973214
25 Releasing of A type towers Nos 122 1366.04 166656.88 1219.678571
26 Releasing of X arms Nos 306 275.79 84391.74 205.2008929
27 Releasing of rabbit ACSR conductor KM 91 4699.30 427636.30 3496.502976
28 Releasing of RCC DP Set 38 4453.75 169242.50 3313.802083
Total (Erection Portion) 9,561,759.22
Mangalore Electricity Supply Company Limited
Re-conductoring and Re-Aliangment of 33KV Single Circuit line corridor having distance of 30.40 KM using 11 M Spun poles & Coyote Conductor from Existing Balehonnur 66/33/11KV Sub-Station to Existing 33/11KV Sub-Station, Sringeri of Koppa Division,Chikkamagaluru District to a distance of km on total turnkey basis.
Sl. No. Item Description Unit Qty Rate Total Amount
1 Excavation of earth pits as per specifications and removing the earth to a distance not more than 50 mtrs. with all lead & lifts for towers, poles, DPs etc.
a) Normal soil Cmtr 20000 313.95 6279000.00
b) Dry fissued rock Cmtr 7500 471.45 3535875.00
c) Wet Soil Cmtr 450 518.60 207438.00
d) Partially submerged Cmtr 400 570.45 199659.08
2 Concreting & curing for towers, poles etc., including cost of all materials & labours
3 Back filling excavated pits with available earth KPWDSR Cmtr 27700 211.05 5846085.00
miselanios materials L/s 0.00
Total Amount in Rs. 56982829.58
Junior Engineer (Ele) Assistant Executive Engineer (Ele)
33/11kV Muss, MESCOM, Koppa O&M Sub Division, MESCOM, Koppa
Executive Engineer (Elec)
O&M Division,MESCOM, Koppa
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkm using Towers, 11Mtr Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No: MESCOM/2026-27/EL/WORK_INDENT515
(Amount in Rs.)
Sl. No Particulars Unit Qty Unit Rate Total Price
1 Earth work excavation for Foundation by mechanical means for all works & depth upto 3 m, as per drawing and technical specifications, including setting out, shoring, strutting, barricading, caution lights, including dressing of excavated surfaces, disposing off or levelling the excavated earth or sorting & stacking the selected earth for reuse in a radius of 50 m and lift upto 1.5 m including cost of labour, tools, usage of machinery & other appurtenaces required to complete the work IN ALL KINDS OF SOIL Depth upto 3 m (for spoun pole, M type tower, DP's, Guy set 66KV DC tower etc,) Cum 2050 94.41 193540.5 84.29
2 Providing and laying in position plain cement concrete for levelling course for all works in foundation. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed, laid in layers not exceeding 150 mm thickness, well compacted using plate vibrators, including all lead & lifts, cost of all materials of quality, labour, Usage charges of machineries, curing, and all the other appurtenances required to complete the work as per technical specifications. (The cost of steel reinforcement & formwork shall be paid separately) Mix 1:4:8( M5) Using 40 mm nominal size graded crushed coarse aggregates. ( for Bed concreting) Cum 85 5189.95 441145.75 4633.88
3 Providing and laying in position Cement Concrete for all Foundation works. The granite/trap/basalt crushed graded coarse aggregates and fine aggregates as per relevant IS Codes machine mixed with super plasticizers laid in finished layers, well compacted using needle vibrators, including all lead & lifts, cost of all materials, quality confirming to the requirements of relevant IS codes, labour, Usage charges of machinery, curing and all the other appurtenances required to complete the work as per technical specifications. M20 Design Mix Using 20 mm nominal size graded crushed coarse aggregates. ( for foundation, raft, stubs and coping finishing) Cum 1310 6181.96 8098367.6 5519.61
4 Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations and other similar works etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 m and lift upto 1.5 m Cum 675 246.21 166191.75 219.83
5 Providing Thermo-Mechanically Treated bars of grade Fe-500D or more Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position, binding and anchoring to adjacent members whereever necessary complete as per Design including cost of material, labour, usage charges complete as per specifications. (The laps and wastages shall not be measured separately) (for M Type & 66kv DC tower) kgs 8250 89.61 739282.5 80.01
Total- Civil Portion 9,638,528.10
BID PROPOSAL SHEETS
Bidder’s proposal Reference No. and date
Bidder’s name and Address
Person to be contacted
SUPERINTENDING ENGINEER (ELE) (PROJECTS),
CORPORATE OFFICE,
MESCOM, 2nd FLOOR, MESCOM BHAVANA
BEJAI, MANGALURU – 575 004
Sub: Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkms using Towers, 11M Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
1.0 We, the undersigned bidder, having read examined in detail the specifications and all the bidding documents of the said 33kV line work and hereby propose to do erection, testing and commissioning of the line work including design, whenever specified, engineering, manufacture, testing, supply on FOR/FOB as applicable site basis as applicable and commissioning of the various line equipments, equipment support structures etc., as detailed in the specifications and documents.
2 PRICE AND VALIDITY:
2.1 All ex-works price components and spares, maintenance and testing equipments and other charges viz. Freight & Insurance and other charges stated in our proposal shall be firm. All the prices and other terms and conditions of this proposal are valid during the performance of the contract. We further declare that prices stated in our proposal are in accordance with your “Instructions to Bidders” included in the Volume – I of Bid documents. All the prices and other terms and conditions of this proposal are valid for a period of One Hundred and Eighty Days (180) from the opening of bid.
2.2 We do hereby confirm that our bid prices as quoted in the e-portal include all the import duties and levies applicable on bought out components, materials, equipment and other items and confirm that any such taxes, duties and levies additionally payable shall be to our account. We further understand that no taxes in any form shall be payable by the owner for bought out items, which are dispatched by our sub-suppliers directly to project site as sale-in-transit basis.
2.3 All applicable taxes on the transaction between the owner and ourselves shall be to Owner’s account. These are included in our bid price quoted in the price bid template provisioned in the e-portal.
2.4 The bid prices, the price components of the various items, price components of Mandatory spares are considered while quoting percentage in the price bid template provisioned in the e-portal.
3 CONSTRUCTION OF THE CONTRACT
We, declare that we are making the offer on the basis of a divisible supply-cum-erection contract on single source responsibility basis. The supply portion of the contract will relate to supply of equipment/material on ex-works basis and the erection portion of the contract will relate to transportation, storage, erection, testing and commissioning of equipment/ material etc as defined in Bid documents. However, we will have no objection in case owner decides to split the above mentioned package into three separate contracts, one contract for supply of all equipments on ex-works basis, second contract for all services such as transportation, insurance, handling at site storage, installation of the equipment/material as defined in bid documents and the third portion as Civil Engineering works including formation of cable duct, equipment foundation etc.We declare that the award of three contracts our responsibility for successful operation of the equipment as per bid documents and that both the contracts will have a cross fall breach clause viz. that a breach in one contract will automatically be classified as breach for the other contract which will confer on the owner the right to terminate the other contract at our risk and cost.
4 We have studied Clause – 13.0 of Section ITB, Volume– I relating to Tax and hereby declare that if any additional corporate tax is attracted under the law, we agree to pay the same.
5 BID GUARANTEE (EMD)
We have enclosed a Bid Guarantee, as detailed below,in the form of in original and one copy of the original valid for a period of six (6) calendar months from the date of opening of bids in accordance with bid documents and complete in respect of the following:
Payment Mode Transaction details Reference No. Amount in Rs.
a Value of Non-judicial stamp paper purchased in the name of executing bank is as per stamp act.
b Power of attorney no. and date as well as signature and full name & Designation of executants along with bank stamp are there.
c Signature, full name, designation and address of witness are there.
d Complete mailing address of the Head Office of the Bank is indicated.
i We declare that all the works shall be performed strictly in accordance with the technical specifications and other bid documents except for the variations and deviations, all of which have been detailed out exhaustively in the following schedules, irrespective of whatever has been stated to the contrary any where else in our proposal.
A. Commercial Deviation Schedule, Schedule-5.
B. Technical Deviation Schedule, Schedule-6.
ii We further confirm that Specified Stipulation of following Clauses are acceptable to us and No Deviation / Exceptions are taken on any account whatsoever in the following Clauses.
a) Terms of Payment Clause No. 11.0 of Section - I, IFB, Volume – I.
b) Bid security Clause No. 6.0 of Section - I, IFB & 19.0 of Section - II, ITB, Volume – I.
c) Contract Performance Guarantee Clause No. 36.0 of Section - II, ITB, Volume – I.
d) Penalty for delay in works Clause No. 12.0 of Section - I, IFB & 14.0 of Section - III, General Terms & Conditions of Contract, Volume – I.
e) Price basis, Currencies and payment Clause No.12.0 of Section - II, ITB, Volume–I
f) Guarantee Clause No. 15.0 of Section - III, Conditions of Contract, Volume – I.
iii Further, we agree that additional conditions if any, found in the proposed documents, other than those stated in Deviation Schedules, save that pertaining to any rebates offered, shall not be given effect to.
7 PERFORMANCE GUARANTEES:
We declare that the ratings and performance figures of the equipment to be furnished and erected by us are guaranteed.
8 BID PRICING :
We further declare, that the prices stated in our proposal are in accordance with your “Instructions to Bidders” included in Volume – I of the Bid Documents.
9 PRICE ADJUSTMENT: VOID
10 ADDITIONAL INFORMATION
We confirm that any additional information does not imply any additional deviation beyond those covered in Schedule-5 & 6 and in case of any contradiction between these additional information and other provisions of Bid, the latter will prevail.
11 QUALIFICATION DATA:
We confirm having submitted the qualification data in duplicate copies, as required by you in your ‘Instructions to Bidders’, Volume – I, in a separate envelope along with this proposal. Further, we have filled in the information for qualification requirements as listed in Schedule-9. In case you require any further information in this regard, we agree to furnish the same in time to your satisfaction.
12 WORK SCHEDULE:
If this proposal is accepted by you, we agree to submit engineering data, provide services and complete the entire works from time to time, in accordance with Schedules indicated in the proposal. We fully understand that the time schedule stipulated in the proposal is the essence of the Contract, if awarded.
13 CONTRACT PERFORMANCE SECURITY
We further, agree that if our proposal is accepted we shall provide an irrevocable Contract Performance Guarantee, of value equivalent to five percent (5%) of the contract price valid up to the end of ninety (90)
days after the end of the Contract warranty period in the form of
(Please specify the form of security) in your favour within thirty (30) days from the date of issue of LOI and enter into a formal contract agreement with you within fifteen (15) days from the date of acceptance of Letter of Intent of Contract.
We declare that our lumpsum price for the entire scope of the work as specified in the specifications and documents and shall be as indicated in the price bid template provisioned in the e-portal.
15 We hereby, declare that only the persons or firms interested in this proposal a principal or principals are named herein and that no persons or firms other than those herein mentioned have any interest in this proposal or in the contract to be entered into, if we are awarded the Contract and that this proposal is made without any connection with any other person, firm or party likewise submitting a proposal is in all respects for and in good faith, without collusion or fraud.
Date this day of
Thanking you, we remain,
Date : Signature
Place: Printed Name
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkms using Towers, 11M Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No. MESCOM/2026-27/EL/WORK_INDENT515
(Commercial Deviation)
Bidder’ s Name and Address: Please fill only in blue cells
SUPERINTENDING ENGINEER (ELE) (PROJ),
CORPORATE OFFICE, MESCOM,
2nd FLOOR, MESCOM BHAVANA,
BEJAI, MANGALURU – 575 004
Email: [email protected]
The following are the commercial deviations and variations from and exceptions to the specifications and documents for
These deviations and variations are exhaustive. Except these deviations and variations, the entire work shall be performed as per your specifications and documents.
Sl. No. Vol/Section Clause No. Page No: As specified in the specification Commercial Deviation and Variations to the specification
NOTE : Continuation sheets of like size and format may be used as per Bidder's requirement and shall be annexed to this schedule.
Place Printed Name
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkms using Towers, 11M Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
(Technical Deviation)
Bid Enquiry No. MESCOM/2026-27/EL/WORK_INDENT515
Bidder’ s Name and Address: Please fill only in blue cells
SUPERINTENDING ENGINEER (ELE) (PROJ),
CORPORATE OFFICE, MESCOM,
2nd FLOOR, MESCOM BHAVANA,
BEJAI, MANGALURU – 575 004
Email: [email protected]
The following are the Technical deviations and variations from and exceptions to the specifications and documents for
These deviations and variations are exhaustive. Except these deviations and variations, the entire work shall be performed as per your specifications and documents.
Sl. No. Vol./Section Clause / Page No: As per specified in the specification Technical Deviation and variations to the specification
Place Printed Name
NOTE : 1) Continuation sheets of like size and format may be used as per Bidder’s requirement and shall be annexed to this schedule. 2) The deviations and variations, if any, shall be brought out separately for each equipment and are to be submitted in five copies
Schedule - 10 (iii)
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkms using Towers, 11M Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No. MESCOM/2026-27/EL/WORK_INDENT515
Please fill only in blue cells
Bidder’ s Name and Address:
SUPERINTENDING ENGINEER (ELE) (PROJ),
CORPORATE OFFICE, MESCOM,
2nd FLOOR, MESCOM BHAVANA,
BEJAI, MANGALURU – 575 004
Email: [email protected]
We propose the following deployments of manpower for this package
Sl.No. Catergory Month after placement of the Award letter
1 Project Manager
2 Sr. Project Engr/Engr
5 Skilled Labour
6 Unskilled Labour
Date: Signature
Place Printed Name
Note : Continuation sheets of like size and format may be used as per Bidder’s requirement and shall be annexed to this schedule.
MANGALORE ELECTRICITY SUPPLY COMPANY LIMITED
Re-conductoring and Re-Alignment of 33kV Single Circuit line for a distance of 30.44Rkms using Towers, 11M Spun poles and Coyote Conductor from 66/33/11kV Balehonnur Substation to 33/11kV Sringeri Substation in Koppa Division on Total Turnkey Basis
Bid Enquiry No. MESCOM/2026-27/EL/WORK_INDENT515
(Guarantee Declaration)
Bidder’ s Name and Address: Please fill only in blue cells
SUPERINTENDING ENGINEER (ELE) (PROJ),
CORPORATE OFFICE, MESCOM,
2nd FLOOR, MESCOM BHAVANA,
BEJAI, MANGALURU – 575 004
Email: [email protected]
Dear sirs, We declare that the rating and performance figures of the equipment furnished by us against this bid enquiry are guaranteed. We also declare that in the event of any deficiencies in meeting the guarantees in respect of the characteristics as established after conducting the performance test, you may at your discretion reject the equipment, in which case we shall replace the same with equipment as per specification and meeting the guarantee, free of charge and within a reasonable time, to be mutually agrees.
Place Printed Name
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
3 Vol 2 - 33kV Balehonnuru to Sringeri.docx
Others - Volume II • 3.86 MB
BOQ Balehonnur to Sringeri.xlsx
Others - Bill of quantities • 0.04 MB
2 Vol 1 - 33kV Balehonnuru to Sringeri.docx
Others - Volume I • 0.22 MB
4 Techno-commercial sheets Sringeri.xlsx
Others - Techno Commercial Sheets • 0.04 MB
1 NIT- 33kV Balehonnuru to Sringeri.docx
Others - Tender Notification • 0.05 MB
Corrigendum 515.pdf
pdf • 0.68 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .