| 1 | 1₹38,337Accepted-AOC | ₹38,337 | 1 | Accepted-AOC L1 - AOC Awarded |
| 2 | 2₹38,468Rejected-Finance | ₹38,468 | 2 | Rejected-Finance Rejected |
| Sl No | Description | Qty | Unit | MILESTONE DEVELOPERS L2 | karthik s L1 |
|---|---|---|---|---|---|
| 1.00 | Dismantling, clearing away and carefully stacking materials useful for re-use for any thickness of walls Dismantling Plain Cement Concrete ( As per SOR 2025-26 , page no:30 W-0034 ) | 1 | 1M3 | 502 ₹502 | 500 ₹500 |
| 2.00 | Providing granolithic floor finish of the For 25mm thick with plain cement concrete 1:2:4 (One Cement, Two Crushed Stone Sand and Four aggregate) using 6 to12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trowel, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) As per data 2025 26 | 24 | 1M2 | 332 ₹7,968 | 330 ₹7,920 |
| 3.00 | Plastering the surface of walls with Cement Mortar 1:4 (One cement and Four plastering sand), 12mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curing etc., complete complying with standard specification and as directed by the departmental officers. As per data 2025 26 | 35 | 1M2 | 291 ₹10,185 | 290 ₹10,150 |
| 4.00 | Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum. As per data 2025 26 | 2 | 1M3 | 165 ₹330 | 165 ₹330 |
| 5.00 | Supply and delivery 450mm dia NP3 RCC non pressure spun pipe with socket and spigot ends as per IS 458/2003 manufactured with sulphate resistant cement with 12 mm HI -alumina lining with rubber ring joints. ( As per TWAD data 2025-26 , page no: 66 , WD-M1040 ) | 5 | 1M | 2,430 ₹12,150 | 2,425 ₹12,125 |
| 6.00 | Lowering of 450mm dia RCC pipes and specials into the trenches and laying to proper grade and alignment. ( As per TWAD data 2025-26 , page no: 188 , WD-W0371) | 5 | 1M | 144 ₹720 | 144 ₹720 |
| 7.00 | Jointing of 450mm dia RCC pipes with cement using necessary collars including the cost of jointing materials. ( As per TWAD data 2025-26 , page no: 189 ,WD-W0388) | 1 | 1No | 745 ₹745 | 744 ₹744 |
| 8.00 | GST 18% | 1 | 1No | 5,868 ₹5,868 | 5,848 ₹5,848 |
Tender Value
₹40,000
Closing Date
8 Jan 2026, 3:00 pmClosed
COMMISSIONER
NO 01 , TRICHY ROAD , PALLADAM MUNICIPALITY OFFICE
RETENDER - Repair and maintenance of storm water drain and providing RCC pipeline at Thiruvalluvar street in ward No 11 , in palladam Municipality
2026_MAWS_638677_1
3143/2025/E1-11,32,48
Open Tender
Civil Works
15 days
PALLADAM MUNICIPALITY LIMIT
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
6 May 2026
3 Jan 2026
8 Jan 2026
3 Jan 2026
8 Jan 2026
3 Jan 2026
Dismantling, clearing away and carefully stacking materials useful for re-use for any thickness of walls Dismantling Plain Cement Concrete ( As per SOR 2025-26 , page no:30 W-0034 )
Providing granolithic floor finish of the For 25mm thick with plain cement concrete 1:2:4 (One Cement, Two Crushed Stone Sand and Four aggregate) using 6 to12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trowel, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers. (The rate is inclusive of necessary planking for panelling wherever necessary and as directed by the departmental officers) As per data 2025 26
Plastering the surface of walls with Cement Mortar 1:4 (One cement and Four plastering sand), 12mm thick in all floors including mortar plasticizer at 200ml per 50Kg of cement used, curing etc., complete complying with standard specification and as directed by the departmental officers. As per data 2025 26
Earth work excavation for foundation in Hard stiff clay, stiff black cotton, hard red earth, shales murram, gravel,stoney earth and earth mixed with small size boulders SS.20B and Sand, silt or other loose soil, wet sand,or silt not under water, light black cotton soil, sandy loam ordinary soil and to full depth as may be directed except in hardrock requiring blasting inclusive of shoring shuttering and baling out water and cleaning and levelling the site etc.,complete 10 cum. As per data 2025 26
Supply and delivery 450mm dia NP3 RCC non pressure spun pipe with socket and spigot ends as per IS 458/2003 manufactured with sulphate resistant cement with 12 mm HI -alumina lining with rubber ring joints. ( As per TWAD data 2025-26 , page no: 66 , WD-M1040 )
Lowering of 450mm dia RCC pipes and specials into the trenches and laying to proper grade and alignment. ( As per TWAD data 2025-26 , page no: 188 , WD-W0371)
Jointing of 450mm dia RCC pipes with cement using necessary collars including the cost of jointing materials. ( As per TWAD data 2025-26 , page no: 189 ,WD-W0388)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
BOQ_764355.xls
BOQ • 0.37 MB
Download all tender documents and submit your bid