Tender ID
Tender Value
₹32.4 L
EMD Value
₹40,500
Closing Date
3 May 2026, 5:00 pmClosed
STAFF OFFICER (CIVIL), LINGARAJ AREA
SO (CIVIL), OFFICE OF THE GM, LINGARAJ AREA TALCHER, ANGUL_759102, ODISHA, INDIA
Making base of transformer and other miscellaneous works at Shantinagar Substation, Lingaraj OCP, Lingaraj Area.
2026_MCL_358631_1
MCL/GM(LA)/e-Tender/ SO(C)/26-27/006 dt.21.04.2026
Open Tender
Civil Works - Others
Percentage
90 days
Lingaraj OCP
Please refer Tender documents.
3 documents required · 3 mandatory
₹40,500
29 Apr 2026
23 Apr 2026
4 May 2026
23 Apr 2026
3 May 2026
23 Apr 2026
23 Apr 2026 - 26 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| - | Earth work in excavation by mechanical means (Hydraulic excavator)/ manual means over areas (exceeding 30 cm in depth, 1.5m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and for all lift, as directed by Engineer-in-charge. All kinds of soil | - | cum | - | - |
| - | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. All kinds of soil. | - | cum | - | - |
| - | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | - | cum | - | - |
| - | Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth. 1:4:8 (1 Cement : 4 coarse sand (zone-Ill) derived from natural sources: 8 graded stone aggregate 40 mm nominal size derived from natural sources) | - | cum | - | - |
| - | Brick work with Fly Ash Brick (230x115x75 mm size) bricks of class designation 10 in foundation and plinth in: Cement mortar 1:6 (1 cement : 6 coarse sand). | - | cum | - | - |
| - | Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth 1:2:4 (1 cement : 2 coarse sand (zone-Ill) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources) | - | cum | - | - |
| - | Brick work with Fly Ash Brick (230x115x75 mm size) bricks of classdesignation 10 in superstructure above plinth level up to floor V level in all shapes and sizes in : Cement mortar 1:6 (1 cement : 6 coarse sand) | - | cum | - | - |
| - | Dismantling old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 metres lead. | - | sqm | - | - |
| - | 20 mm cement plaster of mix: 1:6 (1 cement: 6 fine sand) | - | sqm | - | - |
| - | Neat cement punning. | - | sqm | - | - |
stage.html
html • 0.02 MB
cancelled_1.pdf
pdf • 0.19 MB
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.46 MB
Tendernotice_2.pdf
PDF • 1.34 MB
BOQ_371502.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .