Loading…
Loading…
Tender Value
Refer Docs
EMD Value
₹1.2 L
Closing Date
28 Jul 2023, 3:00 pmClosed
Executive Officer
Sankari Town Panchayat, Bhavani Main Road, Sankari
Restoration of BT Road at Ward No 7 Korikadu Cross Streets Ward No 6 Old Edappadi Road 1st West Cross Street Saravana Therature Ward No 11 Kasthuripatty Kozhikkalnathan Road to Ellaikuttu and Ward No 3 MGR Nagar Areas in Sankari Town Panchayat
2023_DTP_343804_1
337/2023
Open Tender
Civil Works - Roads
Works
180 days
Sankari Town Panchayat
As Per Norms
3 documents required · 3 mandatory
₹0
₹1.2 L
Yes
Sankari Town Panchayat
4 Aug 2023
14 Jul 2023
28 Jul 2023
14 Jul 2023
28 Jul 2023
14 Jul 2023
14 Jul 2023 - 28 Jul 2023
17 Jul 2023
Amount
Picking the existing surface 3 to 5 cm deep removal of picked up staff to the side berms and using the useful metal to the road hand packing to camber sectioning levelling etc.,complete as per including labour charges for picking and other tools and plants etc., complete as per standard specifications. 404 of MORTH
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 100mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH
Providing and laying Prime Coat over WBM/ WMM Surface using 7Kg of Emulsion Bitumen (SSI) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 502 of MORTH Rev-5
Providing and laying Tack Coat over WBM/ WMM Surface (treated with primer) using 2.50 Kg of Bitumen Emulsion (RS1) per 10 sqm for preparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50mm Consolidated thick Dense Bituminous Mecadam using 0.24 cum of 26.50 – 13.20 mm Graded metal and 0.25 cum of 13.20 – 2.36 mm Grade metal and 0.23 cum of 2.36 mm & below with 53.20 kgs of 60/70 Grade Bulk bitumen for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 50 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 505 of MORTH Rev-5
Providing and laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 45.27 kgs of 60/70 Grade Bulk bitumen and 5.03 kg of shredded Plastic waste for premixing per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5
Providing and laying of Hot applied Thermo Plastic Compound of 2.5mm thick including reflectorising glass beads @ 250 gm per sqm is exclusive of surface applied glass beads as per IRC : 35, the finished surface to be level uniform and free from steaks and holes etc as per MORTH 803 Rev. 5
Providing and laying Well Gravel to the specified thick including cost and conveyance of well gravel from approved quarry and stocking the same at road side to Departmental gauage for premeasurement as directed by the Departmental Officers including labour charges for spreading in layers not exceeding 75 mm thick (or) as specified by the departmental officers, leveling, Sectioning etc., and all other charges for tools and plants employed for the work and all other incicental charges such as barricading and providing danger lights etc., complete as per standard specification as per clause 301 & 305 of MORTH
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .