| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.1 LAccepted-AOC | ₹10.1 L | L1 | Accepted-AOC WORK AWARDED |
| 2 | L2₹11.5 L+₹1.5 L (14.4%)Rejected-AOC | ₹11.5 L+₹1.5 L (14.4%) | L2 | Rejected-AOC REJECTED |
| 3 | L3₹11.6 L+₹1.5 L (15.3%)Rejected-AOC | ₹11.6 L+₹1.5 L (15.3%) | L3 | Rejected-AOC REJECTED |
| 4 | L4₹12.2 L+₹2.2 L (21.4%)Rejected-AOC | ₹12.2 L+₹2.2 L (21.4%) | L4 | Rejected-AOC REJECTED |
| 5 | L5₹12.5 L+₹2.4 L (23.7%)Rejected-AOC | ₹12.5 L+₹2.4 L (23.7%) | L5 | Rejected-AOC REJECTED |
Tender Value
₹17.1 L
EMD Value
₹34,152
Closing Date
22 Aug 2026, 5:00 pmClosed
EE BCD PAKUR
EE BCD PAKUR
LAYING OF PAVER BLOCK IN SP RESIDENCE PAKUR DIST PAKUR
2026_BCD_117342_1
11/2026-27/EE/BCD/PAKUR
Open Tender
Civil Works
Percentage
30 days
PAKUR
Please refer Tender documents.
6 documents required · 6 mandatory
₹5,000
₹34,152
9 Sept 2026
17 Aug 2026
24 Aug 2026
17 Aug 2026
22 Aug 2026
17 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation in foundation trenches in ordinary soil ( vide classification of soil item A) and disposal of excavated earth as obtained to a distance upto 50M including all lifts leveling ramming the foundation treanches, removing roots of trees, and shrubs all complete as per approved design, building specification and direction of E/I. | 401.27 | cum | 151.82 | ₹60,920.81 |
| 2 | Providing coarse clean sand in filling in in foundation trenches or in plinth including ramming and watering in layers not exceeding 150mm thick with all leads and lifts including cost of all materials labour, royalty and taxes all complete as per building specification and direction of E/I (Mode of measurement compacted volume) | 271.28 | cum | 589.51 | ₹1,59,922.27 |
| 3 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level : 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) | 3.79 | cum | 4,598.23 | ₹17,427.29 |
| 4 | Providing and laying factory made chamfered edge Cement Concrete paver blocks in footpath, parks, lawns, drive ways or light traffic parking etc, of required strength, thickness & size/ shape, made by table vibratory method using PU mould, laid in required colour & pattern over 50mm thick compacted bed of sand, compacting and proper embedding/laying of inter locking paver blocks into the sand bedding layer through vibratory compaction by using plate vibrator, filling the joints with sand and cutting of paver blocks as per required size and pattern, finishing and sweeping extra sand. complete all as per direction of Engineer-in-Charge. 60mm thick cement concrete paver block of M-35 grade with approved colour, design & pattern. | 1,316.82 | sqm | 793.21 | ₹10,44,514.79 |
| 5 | CARRIAGE OF MATERIALS - (A) Sand - 30 km | 272.91 | cum | 546.9 | ₹1,49,254.48 |
| 6 | (B) S/Chips - 7 km | 3.26 | cum | 219.16 | ₹714.46 |
| 7 | GST @ 18% | 1 | Rs | 2,57,897.69 | ₹2,57,897.69 |
| 8 | LABOUR CESS 1% | 1 | Rs | 16,906.63 | ₹16,906.63 |
stage.html
html • 0.07 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_158596.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
BOQ_158596.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .