| # | Company | Status |
|---|---|---|
| 1 | Accepted-Technical | Accepted-Technical all valid documents uploaded |
| 2 | Accepted-Technical | Accepted-Technical all valid documents uploaded |
| 3 | Accepted-Technical | Accepted-Technical all valid documents uploaded |
| 4 | Accepted-Technical WARD NO 65 PO PS KHANDAGIRI DIST KHURDA PIN 751019 | KHANDAGIRI | KHURDA | ODISHA | 751019 | Accepted-Technical all valid documents uploaded |
| 5 | Accepted-Technical | Accepted-Technical all valid documents uploaded |
Tender Value
₹6.0 Cr
EMD Value
₹6 L
Closing Date
7 Jul 2026, 6:00 pmClosed
Addl. Chief Engineer, Drainage Circle,BBSR
O/o the Addl. Chief Engineer, Drainage Circle, Bhubaneswar
Earthwork, Cement Concrete, Reinforced Cement Concrete, RR Stone Works and Hyacinth clearance from Drainage channel
2026_CEDC_132484_1
ACEDC-BBSR/DD-KHR-17/2026-27
Open Tender
Civil Works - Others
Percentage
330 days
NAYAGARH BLOCK
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹6 L
Yes
29 Jul 2026
22 Jun 2026
8 Jul 2026
22 Jun 2026
7 Jul 2026
22 Jun 2026
22 Jun 2026 - 29 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in both wet and dry condition by mechanical means of all kinds of soil including stony earth, gravel & moorum etc. inter spread with boulders up to 1/2 cum size with all leads, lifts, delifts, handling and rehandling etc. complete including trimming of slopes & bed to design section & depositing the excavated materials away on both side of the drain including spreading, leveling the earth in layers not exceeding 22.5 cm including hire & running charges of all machineries, T& P, cess etc. complete as per direction of the Engineer-in-charge. (Measurement will be recorded in level section only) | - | 1 Cum | 49.7 | - |
| 2 | Clearing of water hyacinth (thickly grown) from canal and drainage channels including uprooting vegetation, grass, bushes, shrubs & trees, removal of stumps of trees & disposal of unserviceable materials away from work site, etc. complete as per direction of the Engineer-in-Charge. (The debris recovered from cleaning of canal & Drainage Channel to be destroyed by the agency.) | 0.29 | 1 Sqm. | 2.83 | ₹0.82 |
| 3 | Excavation of foundation by mechanical means in all kinds of soil with initial lead, lift and rehandling including rough dressing and leveling the bed and sides of foundation and disposal of the excavated materials with all leads, lifts and delfts & breaking clods to maximum 5cm to 7cm & laying in layers not exceeding 0.30m in depth including dewatering, shoring and shuttering, cess etc. complete as per direction of the Engineer-in-charge. | 0.6 | 1 Cum | 42.7 | ₹25.58 |
| 4 | Filling in foundation and plinth with sand well watered and rammed etc. complete including all cost per 1Cum as as per direction of the Engineer-in-charge. | 0.2 | 1 Cum | 515.02 | ₹102.49 |
| 5 | Random rubble hard granite stone masonry of approved quality from approved quarry in sand grouted in foundation & plinth with all leads, lifts & delfts & well watered and rammed in foundation trench including cost, conveyance, royalty, loading and unloading of all materials with cess, T&P, etc complete as per direction of the Engineer-in-charge. | 446.59 | 1 Cum | 3,657.48 | ₹16,33,393.99 |
| 6 | Cement concrete M-15 grade with crusher broken hard granite chips of size 40mm & downgraded of approved quality form approved quarry, mixing by concrete mixer and placing manually in proper position, with all leads, lifts and delifts, compacting with vibrators including cost, conveyance, royalty, loading and unloading of all materials, curing, cess, T&P, etc. complete as per direction of the Engineer-in-charge. | 0.6 | 1 Cum | 5,687.53 | ₹3,412.52 |
| 7 | Cement concrete M-25 grade with crusher broken hard granite chips of size 20mm & downgraded of approved quality from approved quarry mixing by concrete mixer and placing manually, with all leads, lifts and delifts, compacting properly, including cost, conveyance, royalty, loading and unloading of all materials, curing, cess, T&P, etc. complete as per direction of the Engineer-in-charge. | 0.6 | 1 Cum | 7,044.33 | ₹4,226.6 |
| 8 | Supplying, straightening, cutting, bending & binding and tying the grills of HYSD bars of approved quality and placing in position including cost, conveyance of HYSD bars and binding wire 18 to 20 gauge, loading, unloading, cess, T&P, etc. complete as per direction of Engineer-in-Charge. | 0.2 | 1 Qntl. | 7,869.24 | ₹1,565.98 |
| 9Rigid & smooth centering and shuttering for R.C.C. work including false work and dismantling them after casting including cost, conveyance of all materials, cess, labour, T&P, etc. complete as per direction of the Engineer –in –Charge. | |||||
| 9.01 | RCC foundation, plinth band, footings, bases of columns, mass concrete, precast slabs etc. | 2,288.28 | 1 Sqm. | 249.83 | ₹5,71,680.99 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.49 MB
17DTCNSaraUpload.pdf
Tender Documents • 4.88 MB
BOQ_597172.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .