| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹13.0 LAccepted-Finance | 1 | Accepted-Finance Below As per Estimate | |
| 2 | 2₹13.1 L+₹5,849 (0.45%)Rejected-Finance | 2 | Rejected-Finance Above As Per Estimate |
Tender Value
₹16 L
EMD Value
₹16,000
Closing Date
15 Jun 2023, 3:00 pmClosed
Executive Officer
Koradachery L.F.Road Kodavasal
Relaying Of BT Road At Mela Adichery Street in Kodavasal Town Panchayat
2023_DTP_325775_1
145/2023
Open Tender
Civil Works
Works
Kodavasal Town Panchayat
I, II
3 documents required · 3 mandatory
₹6,720
Executive Officer Kodavasal Town Panchayat
₹16,000
Yes
21 Jul 2023
10 Jun 2023
16 Jun 2023
10 Jun 2023
15 Jun 2023
10 Jun 2023
Amount
Providing and laying Tack Coat over existing B.T Surface using 2.00 Kg of Bitumen Emulsion (RS1) per 10 sqm for prparatory to another bituminous construction over it, including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm &below and with 53.20 Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMPsite,heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory/Pneumatic Roller to the required density etc.,including labou for attending to paver at site etc.,including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory/Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc.,complete a sper specification using CMP as per clause 505 MORTH Rev-5
Providing and laying Bituminus Concrte to 30 mm thick using 0.13 cum of 19.00-9.50mm 0.17 cum 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all marerials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity,conveying the mix by tipper trucks to paver site spreading the mix to uniform thickness of 40mm with mechanical paver tothe specified grades and cross sections and consolidated by 8-10 tonne Vibratory /Pneumatic Roller to the required density etc., including labour for attending to paver to site etc.,including hire charges and fuel charges for 20-30 t CMP with bitumen boiler,tippertrucks,paver Finisher /9m paver finisher,Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc.,complete as per specification using CMP as per clause 507 of MORTH Rev-5.
senthil
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .