| 1 | L1₹1.1 CrAccepted-AOC KUMBAKONAM | ₹1.1 Cr | L1 | Accepted-AOC Lowest Rate |
| 2 | L2₹1.1 Cr+₹36,541.19 (0.33%)Rejected-Finance | ₹1.1 Cr+₹36,541.19 (0.33%) | L2 | Rejected-Finance Highest Rate |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
7 Jul 2023, 3:00 pmClosed
Additional Collector (Dev)/Project Director
DRDA Office, 2nd Floor, New Collectorate, Thanjavur
Thanjavur District - Package No.20 - Strengthening and 5 years Maintenance of 4 Road works in Thiruppanandal Block under MGSMT - 2022-2023.
2023_RDTN_330839_1
DIPR/2987/Tender/2023
Open Tender
Civil Works - Roads
Item Rate
180 days
Thiruppanandal
As per Tender document
9 documents required · 9 mandatory
₹0
₹1.1 L
9 Sept 2023
22 Jun 2023
7 Jul 2023
22 Jun 2023
7 Jul 2023
22 Jun 2023
Amount
Part.1. Strengthening and 5 years maintenance of Irumoolai Melaveli Road (R-50) @ Irumoolai- Panchayat Km 0/0-0/710.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing B.T surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer. complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
60cm Equilateral triangle Cautinary Sign board (pedestrain crossing,major road ahead.speed breaker ahead ,school zone,side road left and right,X-junction ahead,curve ahead)
Pedestrain Crossing
Major road Ahead
School Zone
Side road Left and Right
Caution Board
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Providing and laying of hot applied Thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 gms per sq.m area, thickness of 2.5 mm is exclusive of surface apllied glass beads as per IRC : 35. The finished surface to be level , uniform and free from streaks and holes etc complete as per MORT &H specification No.803.
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part.2. Strengthening and 5 years maintenance of Maharajapuram ADC Road (R-82) @ Maharajapuram- Panchayat Km 0/0-0/560.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing B.T surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer. complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
60cm Equilateral triangle Cautinary Sign board (pedestrain crossing,major road ahead.speed breaker ahead ,school zone,side road left and right,X-junction ahead,curve ahead)
Pedestrain Crossing
Major road Ahead
Side road Left and Right
Caution Board
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Providing and laying of hot applied Thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 gms per sq.m area, thickness of 2.5 mm is exclusive of surface apllied glass beads as per IRC : 35. The finished surface to be level , uniform and free from streaks and holes etc complete as per MORT &H specification No.803.
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part.3. Strengthening and 5 years maintenance of Karuppur Srirengarajapuram Road (R-58) @ Karuppur- Panchayat Km 0/0-0/600.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing B.T surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer. complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
60cm Equilateral triangle Cautinary Sign board (pedestrain crossing,major road ahead.speed breaker ahead ,school zone,side road left and right,X-junction ahead,curve ahead)
Pedestrain Crossing
Major road Ahead
Side road Left and Right
Caution Board
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Providing and laying of hot applied Thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 gms per sq.m area, thickness of 2.5 mm is exclusive of surface apllied glass beads as per IRC : 35. The finished surface to be level , uniform and free from streaks and holes etc complete as per MORT &H specification No.803.
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
Part.4. Strengthening and 5 years maintenance of Serukadambur Andiramapuram Road (R-78) @ Koilramapuram- Panchayat Km 0/0-1/490.
Clearing and grubbing road land including uprooting wild vegetation, grass, bushes ,scrubs,saplings and trees of girths upto 300mm, removal of stumps of such trees cut earlie and disposal of unserviceable material and stacking of serviceable materials to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150mm thickness as per technical specification clause 201 in all etc complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A.
Picking the existing B.T surface and sectioning upto 50 mm - 100 mm thick including all labour charges including all labour charges etc,. complete.
Providing and laying 75 mm compacting thick WBM Gr.III using 1 cum of 63 mm to 11.20 mm IRC metal and 0.24 cum of Gravel for blindage 10 sqm. Of 75 mm compacted thick (the blindage material shall have PI value less than 6%) Including cost and conveyance of all material from approved quarry to worksite and stacking to departmental metric gauge for pre – measurement as directed by the departmental officers including labour charges for spreading metal and gravel hand packing to proper camber and grade line blinding with required quantity of gravel forming edge bunds watering with all leads for good water slurring rolling and consolidation by power roller and finishing as per MORT & H 404 including hire and fuel charges for power roller and water sprinkler and all other tools and plants employed there for and all other incidental charges etc., complete for top layer. complete.
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. complete.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 25mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Providing & laying gravel soling to compacted thick including cost & conveyance of gravel from approved source to work site including labour for spreading and compacting by power roller to achieve the required Proctor density at 100% compaction of optimum moisture content and hire & fuel charges for power roller , water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete.
60cm Equilateral triangle Cautinary Sign board (pedestrain crossing,major road ahead.speed breaker ahead ,school zone,side road left and right,X-junction ahead,curve ahead)
Pedestrain Crossing
Side road Left and Right
Supplying and fixing Kilo Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Hecta Metre stones including painting and lettering as directed by the departmental officers etc., complete.
Supplying and fixing Name board including painting and lettering as directed by the departmental officers etc., complete.
Providing and laying of hot applied Thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 gms per sq.m area, thickness of 2.5 mm is exclusive of surface apllied glass beads as per IRC : 35. The finished surface to be level , uniform and free from streaks and holes etc complete as per MORT &H specification No.803.
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRCSP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost.
For the First Year from the date of completion of work
For the Second Year from the date of completion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}.
K MANIKANNAN
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .