| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹39 LAccepted-AOC | ₹39 L | 1 | Accepted-AOC Approved |
| 2 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | NiranjaniConstructions L1 |
|---|---|---|---|---|
| 1.00 | Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401. | 225 | m3 | 1,764 ₹4.0 L |
| 2.00 | Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH | 225 | m3 | 2,030 ₹4.6 L |
| 3.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev V Specifications | 2,250 | m2 | 79.5 ₹1.8 L |
| 4.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the BT surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev V Specifications | 2,250 | m2 | 18 ₹40,500 |
| 5.00 | Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm, 0.25 cum of 13.20-2.36mm and 0.23 cum of 2.36mm & below and with 45.27Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to worksite, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20- 30t CMP with bitumen boiler, tipper trucks, Paver Finisher /9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5 | 112.5 | m3 | 9,687 ₹10.9 L |
| 6.00 | Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 19.00 - 9.50mm, 0.17cum of 9.50 -2.36mm and 0.26cum of 2.36 and below with 50.30kgs of VG30 / VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5. | 67.5 | m3 | 10,503 ₹7.1 L |
| 7.00 | Road marking with Hot Applied Thermo Plastic Compound with Reflectorising Glass Beads on Bituminious Surface Proving and Laying of Hot Applied thermoplastic Compound etc., complete as per specification | 120 | m2 | 890 ₹1.1 L |
| 8.00 | Earth work excavation in all classes of soils such as hard stiff clay, stiff black cotton, hard red earth, shales, murram, ordinary earth, earth mix with 50% fair sized boulders etc., with initial lead and lifts including laying, spreading, leveling, sectioning breaking clods etc., including all incidental charges etc., complete as per standard specification . for Foundations SS 20B TNDSS NO. 23 &24 V, VI (S2) VI 9 | 8.2 | m3 | 184.5 ₹1,512.90 |
| 9.00 | Plain Cement concrete of mix 1:4:8 (One Part of cement, four part of sand and eight part of aggregates) using 40mm gauge hard broken including cost conveyance of all materials to site including labour charges, transporting and placing in position including shoring, strutting forming protective bunds, cofferdams bailing out of water labour for mixing compacting, finishing and curing, working at depths, tools and plants and incidental charges such as sheeting, shoring and bracing and their subsequent removal etc., complete as per standard specification.TNDSS NO.28 V,VI S25 | 1 | m3 | 5,023 ₹5,023 |
| 10.00 | Supplying & Erecting of steel centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle of size 25 x 25 x 3mm for boarding laid over silver oak joists(Country wood) of size 10 x 6.5cm spaced @ about 90cm c/c and supported by casurina props of 10 - 13cm dia. spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. TNDSS NO.86 K, 86 A | 25.4 | m2 | 1,023 ₹25,984.20 |
Tender Value
₹39 L
EMD Value
₹78,000
Closing Date
3 Dec 2025, 3:00 pmClosed
Executive Officer
Alangayam Town Panchayat
Providing BT Road with Culvert at Ward No. 4, Munichetti eri Road in Alangayam Town Panchayat.
2025_DTP_624914_1
379-2025 KNMT 25-25 39 LAK
Open Tender
Civil Works - Roads
90 days
Alangayam Town Panchayat
Providing BT Road with Culvert at Ward No. 4, Munichetti eri Road in Alangayam Town Panchayat.
3 documents required · 3 mandatory
₹0
₹78,000
Alangayam Town Panchayat
23 May 2026
20 Nov 2025
3 Dec 2025
20 Nov 2025
3 Dec 2025
20 Nov 2025
20 Nov 2025 - 3 Dec 2025
26 Nov 2025
Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401.
Providing and laying, spreading and compacting graded stone aggregates to Wet Mix Macadam 250mm thick specification including premixing the materials with water at OMC in mechnanical mix plant carriage of mixed material by tipper to site laying in uniform layers with pavers in Sub Base/ Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev V Specifications
Providing and laying tack coat of 2.5 kgs/10 sqm over the BT surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Rev V Specifications
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm, 0.25 cum of 13.20-2.36mm and 0.23 cum of 2.36mm & below and with 45.27Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min. required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to worksite, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20- 30t CMP with bitumen boiler, tipper trucks, Paver Finisher /9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5
Providing and laying Bituminous Concrete to 30mm thick using 0.13 cum of 19.00 - 9.50mm, 0.17cum of 9.50 -2.36mm and 0.26cum of 2.36 and below with 50.30kgs of VG30 / VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10tonne Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5.
Road marking with Hot Applied Thermo Plastic Compound with Reflectorising Glass Beads on Bituminious Surface Proving and Laying of Hot Applied thermoplastic Compound etc., complete as per specification
Earth work excavation in all classes of soils such as hard stiff clay, stiff black cotton, hard red earth, shales, murram, ordinary earth, earth mix with 50% fair sized boulders etc., with initial lead and lifts including laying, spreading, leveling, sectioning breaking clods etc., including all incidental charges etc., complete as per standard specification . for Foundations SS 20B TNDSS NO. 23 &24 V, VI (S2) VI 9
Supplying & Erecting of steel centering for sides & soffiots including necessary supports & strutting upto 3.29m height for plane surfaces in all floors with all cross bracings using mild steel sheets of size 90 x 60cm & 10 gauge stiffened, welded with steel angle of size 25 x 25 x 3mm for boarding laid over silver oak joists(Country wood) of size 10 x 6.5cm spaced @ about 90cm c/c and supported by casurina props of 10 - 13cm dia. spaced @ 75cm c/c etc., complete complying with standard specifications and as directed by the departmental officers. TNDSS NO.86 K, 86 A
Plain Cement Concrete 1:2:4 (one cement, two Crushed Stone Sand (M- Sand) and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification
Providing granolithic floor finish of 25mm thickness with plain cement concrete 1:2:4 (One Cement, Two crushed sand (M-Sand) and Four aggregate) using 10 to 12mm gauge hard broken stone jelly including laying, finishing and the top rubbed smooth with power trawl, thread lining, curing etc. complete complying with standard specification and as directed by the departmental officers.
Supplying fabricating and placing in position of RTS Rods for reinforcement at all RCC works including cost of steel, binding wire, labour charges etc. complete as directed by Departmental Officers
Providing and laying in position Standardised Concrete Mix M-20 Grade in accordance with IS 456 - 2000 using 20mm and down graded hard broken granite stone jelly for all RCC items of works with minimum cement contenet of 325Kg/ cum and maximum water cement ratio of 0.55 including admixture (Plasticiser / super plasticiser) in recommended proportions as per IS 9103 to accelerate, related setting of concrete, improve workability without imparing strength and durability with about (5.0cum), 7730Kg of 20mm machine crushed stone jelly and with about (3.3 cum), 5156kg of 10 - 12mm machine crushed stone jelly and with about (4.79cum) 7670 kg of Crushed Stone Sand (M- Sand), but excluding cost of reinforcement grill and fabricating charges centering and shuttering but including laying, vibrating with mechanical vibrators, finishing, curing, etc and providing fixtures like fan clamps in the RCC floor / roof slabs wherever necessary without claiming extra cost etc., complete complying with standard specification and as directed by the departmental officers -
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.08 MB
Tendernotice_2.pdf
PDF • 0.33 MB
BOQ_747263.xls
BOQ • 0.24 MB
Tendernotice.pdf
Tender Documents • 0.06 MB
BIDDocument.pdf
Additional Documents • 0.31 MB
Download all tender documents and submit your bid