Loading…
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹1.4 LAdmitted-Fee/PreQual/Technical/Finance KHATIYAN NO 164 211 DERA PLOT NO 460 2635 COLLIERY DIST ANGUL ODISHA PIN 759103 | ANGUL | ANGUL | ODISHA | 759103 | L1 | Admitted-Fee/PreQual/Technical/Finance | ||
| 2 | L2₹1.4 L+₹2,282.24 (1.62%)Admitted-Fee/PreQual/Technical/Finance AT BANTOL NEAR SANIDEV TEMPLE PO RAILWAY STATION P S TALCHER DIST ANGUL ODISHA 759100 | TALCHER | ANGUL | ODISHA | 759100 | L2 | Admitted-Fee/PreQual/Technical/Finance | ||
| 3 | L3₹1.6 L+₹21,437.67 (15.2%)Admitted-Fee/PreQual/Technical/Finance AT BAGHUABOL TALCHER DIST ANGUL ODISHA 759100 | TALCHER | ANGUL | ODISHA | 759100 | L3 | Admitted-Fee/PreQual/Technical/Finance | ||
| 4 | L4₹2.2 L+₹80,750.25 (57.2%)Admitted-Fee/PreQual/Technical/Finance A P O JANDABAHAL DHARAMPUR TALCHER DIST ANGUL ODISHA 759100 | TALCHER | ANGUL | ODISHA | 759100 | L4 | Admitted-Fee/PreQual/Technical/Finance | ||
| 5 | L5₹2.5 L+₹1.1 L (78.7%)Admitted-Fee/PreQual/Technical/Finance | L5 | Admitted-Fee/PreQual/Technical/Finance |
Tender Value
₹3.0 L
EMD Value
₹3,800
Closing Date
2 Nov 2026, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
AVIJIT DAS, SO(CIVIL), TALCHER AREA, MCL
O/O STAFF OFFICER (CIVIL), TALCHER AREA, MCL
Repairing of Front Damaged Canopy of MRS Building, Talcher Area.
2026_MCL_365603_1
MCL/GM(TA)/SO(C)/ e-Tender/26-27/19 dt.21.10.26
Open Tender
Civil Works - Buildings
Percentage
30 days
TALCHER AREA
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,800
Yes
3 Nov 2026
21 Oct 2026
3 Nov 2026
22 Oct 2026
2 Nov 2026
22 Oct 2026
22 Oct 2026 - 26 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | 1.06 | cum | 2,075.2 | ₹2,199.71 |
| 2 | Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, for all lift, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.All kinds of soil. | 2 | cum | 217 | ₹434 |
| 3 | Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete. | 0.2 | cum | 910.15 | ₹182.03 |
| 4 | Providing and laying in position excluding cement concrete of level: specified grade the cost of centering and shuttering - All work up to plinth:1:3:6 (1 Cement : 3 coarse sand (zone-Ill) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources) | 0.2 | cum | 5,219.9 | ₹1,043.98 |
| 5 | Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level :1:1.5:3(1 cement: 1.5 coarse sand (zone-Ill) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | 0.78 | cum | 7,009.05 | ₹5,467.06 |
| 6 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more. | 78 | kg | 101.4 | ₹7,909.2 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for:Columns, Pillars, Piers, Abutments, Posts and Struts | 2.32 | sqm | 675.8 | ₹1,567.86 |
| 8 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | 568.11 | kg | 124 | ₹70,445.64 |
| 9 | Providing and fixing precoated galvanised iron profile sheets (size, shape and pitch of corrugation as approved by Engineer-in-Charge) of total coated thickness 0.50 mm (base metal of minimum 0.45 mm thickness with total coating thickness of 0.05mm) with zinc coating 120 grams per sqm as per IS: 277, in 240 mpa steel grade, 5-7 microns epoxy primer on both side of the sheet and polyester top coat 15-18 microns. Sheet should have protective guard film of 25 microns minimum to avoid scratches during transportation and should be supplied in single length upto 12 metre or as desired by Engineer-in-charge. The sheet shall be fixed using self drilling /self tapping screws of size (5.5x 55 mm) with EPDM seal, complete upto any pitch in horizontal/ vertical or curved surfaces, excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. | 9.41 | sqm | 917.15 | ₹8,630.38 |
| 10 | Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :Two or more coats on new work | 40.09 | sqm | 114.65 | ₹4,596.32 |
stage.html
html • 0.02 MB
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.38 MB
Tendernotice_2.pdf
PDF • 1.47 MB
BOQ_378534.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .