| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.8 LAccepted-Finance | ₹4.8 L | L1 | Accepted-Finance Responsive |
| 2 | L2₹4.9 LAccepted-Finance | ₹4.9 L | L2 | Accepted-Finance Responsive |
| 3 | L3₹5.0 LAccepted-Finance | ₹5.0 L | L3 | Accepted-Finance Responsive |
| 4 | L4₹5.0 LAccepted-Finance | ₹5.0 L | L4 | Accepted-Finance Responsive |
| 5 | L5₹5.3 LAccepted-Finance | ₹5.3 L | L5 | Accepted-Finance Responsive |
Tender Value
₹7.9 L
EMD Value
₹15,860
Closing Date
6 May 2026, 6:55 pmClosed
Executive Engineer
Shalimar
Construction of Storage Godown Under (ICAR) at KVK Budgam at Haran, SKUAST-K.
2026_SKUST_309045_1
E-NIT-06 of 2026-27
Open Tender
Electrical Works
60 days
KVK Budgan at Harran
Please refer Tender documents.
5 documents required · 5 mandatory
₹500
Assistant comptroller
₹15,860
25 May 2026
29 Apr 2026
7 May 2026
29 Apr 2026
6 May 2026
29 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing cement concrete manually/by mechanical means including disposal of material within 50 meters lead as per direction of Engineer-in- charge: 1:3:6 or richer mix (i/c equivalent design mix) | 4.33 | CUM | 1,725.2 | ₹7,470.12 |
| 2 | Centering and shuttering including strutting, propping etc. and removal of form for: Foundations, footings, bases of columns etc. for mass concrete. Foundations, footings, bases of columns etc. for mass concrete. | 21.93 | SQM | 286.35 | ₹6,279.66 |
| 3 | Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts,struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchors blocks, plain window sills, fillets etcupto floor V level, including curing but excluding the cost of centring, shuttering and finishing with. 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) | 6.91 | CUM | 8,422.45 | ₹58,199.13 |
| 4 | Steel work in built up tubular (round, square or rectangular hollow tubes etc.) trusses etc., including cutting , hoisting , fixing in position and applying a priming coat of approved steel primer, including welding and bolted with special shaped washers etc. complete. | 649.79 | KG | 156.95 | ₹1,01,984.54 |
| 5 | Structural steel work in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all
complete. | 3,264 | KG | 138.2 | ₹4,51,084.8 |
| 6 | Providing corrugated G. S. sheet roofing including vertical/curved surface fixed with polymer coated J or L hooks, bolts and nuts 8mm diameter with bitumen and G.I limpet washers or with G.I. limpet washers filled with white lead, including a coat of approved steel primer and two coats of approved paint on overlapping of sheets complete (upto any pitch in horizontal/vertical or curved surface)excluding the cost of purlins, rafters and trusses and including cutting to size and shape wherever required. 0.5mm thick | 163.57 | SQM | 852.5 | ₹1,39,443.43 |
| 7 | Supplying and fixing rolling shutters of approved make, made of required size M.S. laths, interlocked together through their entire length and jointed together at the end by end locks, mounted on specially designed pipe shaft with brackets, side guides and arrangements for inside and outside locking with push and pull operation complete, including the cost of providing and fixing necessary 27.5 cm long wire springs manufactured from high tensile steel wire of adequate strength confirming to IS:4454 part-1 and M.S. top cover of required thickness for rolling shutters.80x1.20 mm M.S. laths with 1.20 mm thick top cover | 7.43 | SQM | 3,305 | ₹24,556.15 |
| 8 | Providing and fixing ball bearing for rolling shutters. | 2 | EACH | 531.55 | ₹1,063.1 |
| 9 | Painting with synthetic enamel paint of approved band and manufacture of required colour to give an even shade on New work (two or more coats) including a coat of approved steel primer | 16.36 | SQM | 149.05 | ₹2,438.46 |
stage.html
html • 0.06 MB
tech_eval.pdf
fin_eval.pdf
finance_1000745.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.18 MB
BOQ_1000745.xls
BOQ • 8.25 MB
Download all tender documents and submit your bid