| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹28.6 LAccepted-AOC GORAKHPUR GORAKHPUR UTTAR PRADESH | GORAKHPUR | UTTAR PRADESH | 273001 | ₹28.6 L | L1 | Accepted-AOC AOC |
Tender Value
Refer Docs
EMD Value
₹3 L
Closing Date
30 Mar 2026, 9:00 amClosed
ee cd jaunpur
ee cd jaunpur
kodupur bhikhapur link road 2x3x3 m rcc box culvert ka nirman
2026_CEUVZ_1117455_6
302/9A Dated 09.02.2026
Open Tender
Civil Works - Bridges
Fixed-rate
120 days
ee cd jaunpur
plz prfer nit
2 documents required · 2 mandatory
₹944
₹3 L
Yes
22 Jul 2026
25 Mar 2026
30 Mar 2026
25 Mar 2026
30 Mar 2026
25 Mar 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 2Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying the requirements laid down in clause 2504.2.2. of MORTH specifications to a thickness of not less than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm condition complete as per drawing and Technical Specification. As per MORTH Sr.No. 13.10 and 710.1.4.of IRC:78 and 2200 Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 3Plain cement concrete in open foundation complete and as per drawing technical specifications. (M- 15) As per MORTH Sr.No. 12.8 and Specification No. 1500, 1700 Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 4RCC Grade M25 Plain/Reinforced Cement Concrete in Open Foundation complete as per Drawing and Technical Specifications. Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 5Supplying, fitting and placing HYSD reinforcement complete in sub-structure drawing as per and Technical Specification As per MORTH Sr.No. 12.40 and Specification No. 1600 Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 6Providing weepholes in brick masonry/stone masonry, plain/reinforced concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending through the full width of the structures with slope of 1(V):20(H) towards drawing face complete as per drawing clause 2706 & 2200 Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 7Providing and laying Pitching on slopes laid including boulder apron laid dry in front of toe of embankment complete as per drawing and Technical specifications. As per MORTH Sr.No. 15.4 and Specification No. 2504 Including All material T&P, Labour cess etc But Excluding cost of GST (Part-A Box Culvert) | |||||
| 8Construction of Embankment with Material Obtained from R.O.W. Construction of embankment with approved material obtained from borrow pits with a lift upto 1.5 m, transporting to site, spreading, grading to required slope and compacting to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 & Diversion Including All material T&P, Labour cess etc But Excluding cost of GST (Part B+C Approach & Addi. Approach) | |||||
| 9Providing, laying and spreading Material on a prepared sub grade, adding cement @ 2% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of sub-base. Including All material T&P, Labour cess etc But Excluding cost of GST (Part B+C Approach & Addi. Approach) | |||||
| 10Providing, laying and spreading Material on a prepared sub base, cement @ 4% by weight to the spread Material manually, mixing in place with rotavator and compacting with the road roller at OMC to achieve the desired unconfined compressive strength and to form a layer of base. (Part B+C Approach & Addi. Approach) | |||||
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.87 MB
BOQ_2107034.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .