| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹77.5 LAccepted-AOC | 1 | Accepted-AOC L1 | |
| 2 | 2₹88.0 L+₹10.5 L (13.5%)Rejected-AOC | 2 | Rejected-AOC L2 |
Tender Value
₹80.0 L
EMD Value
₹80,000
Closing Date
3 May 2023, 3:00 pmClosed
Project Director
DRDA Namakkal
Upgradation/ Strengthening/Periodic Renewal and Five year Maintenance of 3 Road works in Namakkal Block of Namakkal District under Mudhalvarin Grama Salaigal Membattu Thittam (MGSMT)- 2022-23.Pa.No.48 /NKL/MGSMT 2022-23
2023_RDTN_304150_20
DIPR/2018/Tender/2023
Open Tender
Civil Works - Roads
Item Rate
180 days
Namakkal
Required documents as per schedule
4 documents required · 4 mandatory
₹0
₹80,000
Yes
DRDA Namakkal
4 Jul 2023
20 Apr 2023
3 May 2023
20 Apr 2023
3 May 2023
25 Apr 2023
25 Apr 2023
Amount
Strenthening to the Road From Avalnaickenpatty to Avalnaickenpatty Union Road Km 0/0-0/560 (R-51) H/O.Avalnaickenpatty
Clearing Scrub Jungles and removing them by burrying or burning etc., completed as per Sl. No.2
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for shoulder.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 23.232Kg of bitumen and 1.168 Kg of Plastic waste for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface - Providing and Laying of hot applied Thermoplastic Compound 2.5mm thick including relectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC : 35. The finished surface to be level, uniform and free streaks and holes etc complete as per MORTH & H specification Nos. 803. (Excluding GST)
Strenthening to the Road From Vandrampatty Burial Ground Road Km 0/0 -0/420 (R-52) H/o.Avalnaickenpatty
Clearing Scrub Jungles and removing them by burrying or burning etc., completed as per Sl. No.2
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for shoulder.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 23.232Kg of bitumen and 1.168 Kg of Plastic waste for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface - Providing and Laying of hot applied Thermoplastic Compound 2.5mm thick including relectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC : 35. The finished surface to be level, uniform and free streaks and holes etc complete as per MORTH & H specification Nos. 803. (Excluding GST)
Strenthening to the Road From Namakkal Nainamalai road to Karattupatti Road Km 0/0 - 1/200 H/o.Marurpatty.
Clearing Scrub Jungles and removing them by burrying or burning etc., completed as per Sl. No.2
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for spreading and compaction with power roller etc.complete, for shoulder.
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Applying PRIMECOAT over WMM surface at 7.00Kg of SS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
Applying TACK COAT over Primed WMM surface at 2.5Kg of RS-1 Bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc. Comp.
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface - Providing and Laying of hot applied Thermoplastic Compound 2.5mm thick including relectorising glass beads @ 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass beads as per IRC : 35. The finished surface to be level, uniform and free streaks and holes etc complete as per MORTH & H specification Nos. 803. (Excluding GST)
Towards the charges for routline maintenance of the road work executed under MGSMT including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
R. Subramanian
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .