Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹25.8 LAccepted-Finance | ₹25.8 L | L-1 | Accepted-Finance Accept |
| 2 | L-2₹25.9 LRejected-Finance | ₹25.9 L | L-2 | Rejected-Finance Reject |
Tender Value
₹24.7 L
EMD Value
₹45,000
Closing Date
17 Apr 2026, 5:00 pmClosed
Executive Engineer
Bharwain Division HPPWD Bharwain
Const of Health Sub Center building at Chowar Tehsil Amb Distt Una HP SH Const of Main Building, WS and SI Septic Tank Rain water Harvesting Tank and site developmentAgainst Deposit
2026_PWD_133504_1
HSC Building at Chowar Job No. 5
Open Tender
Civil Works
180 days
Bharwain
As per tender documents
2 documents required · 2 mandatory
₹500
₹45,000
23 Apr 2026
7 Apr 2026
18 Apr 2026
7 Apr 2026
17 Apr 2026
7 Apr 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount | Item Code |
|---|---|---|---|---|---|---|
| 1 | Excavation in earth work in foundation and trenches etcetera in all kind and classification of soil such as pick work, jumper work, pick jumper work, blasting work and hard blasting work and saturated soil any other mixed verity of soil in dry or saturated condition upto any depth and lift upto any height including chiseling/wedging out rocks where blasting prohibited dewatering pumping or bailing out water where required and/ removal of slush seprately as directed which may arise during the execution including stacking the serviceable and unserviceable material and then returning stacked soil in any thickness of layers when required into plinth side of foundation etcetera consolidating each deposited layers by ramming and watering then disposing of all surplus unserviceable excavated earth as specified dumping place as per CPWD specifications 2019 complete and direction of Engineer-in- charge including carriage of materials/machinery required to execute the work in all leads and lifts and other incidentials.The rate includes octroi , royality , Malkhana , toll tax, goods service tax , labour cess or other taxes imposed by the Govt. | - | Cubic meter | - | - | BI01010001010000000000000515BI0100001113 |
| 2 | Excavation in all kind of soil work in by mechanical means (Hydraulic excavator)/manual means including saturated soil comprising of ordinary soil, soft rocks, hard rocks, chiselling/wedging out of rock (where blasting is prohibited) and their intermediate classification of soil setting our true to the required line, grades width cutting and trimming of side slopes and level as shown on the drawing and as directed by the Engineer-in-Charge at site. Any loss to the public/private property during the course of execution shall be absolute responsibility of the contractor which shall have to be duly compensated by him in all cases as per CPWD specifications 2019 complete and as per direction by the Engineer in charge including entire carriage of materials with in all leads and lifts and other incidentials . The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Cubic meter | - | - | BI01010001010000000000000515BI0100001114 |
| 3 | Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering any lead and lift as per CPWD specifications 2019 complete and as per direction by the Engineer in charge including entire carriage of materials with in all leads and lifts and other incidentials The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Cubic meter | - | - | BI01010001010000000000000515BI0100001115 |
| 4 | Providing form work with steel plates 3.15mm (three point fifteen millimeter) thick welded with angle iron in frame 30×30×5mm (thirty into thirty into five millimeter) so as to give a fair finish including centring, shuttering, strutting and propping etcetera with wooden battens and ballies upto any height in all floor level of propping and centring below supporting floor to ceiling upto any height and removal of the same for in-situ reinforced cement concrete and plain concrete work as per CPWD specifications 2019 in Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc. as per the direction by the Engineer in charge including entire carriage of materials with in all leads and lifts and other incidentials . The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Square meter | - | - | BI01010001010000000000000515BI0100001116 |
| 5 | Providing form work with steel plates 3.15mm (three point fifteen millimeter) thick welded with angle iron in frame 30×30×5mm (thirty into thirty into five millimeter) so as to give a fair finish including centring, shuttering, strutting and propping etcetera with wooden battens and ballies upto any height in all floor level of propping and centring below supporting floor to ceiling upto any height and removal of the same for in-situ reinforced cement concrete and plain concrete work as per CPWD specifications 2019 in Suspended floors, roofs, landings, balconies and access plateform as per the direction by the Engineer in charge upto any floor level including entire carriage of materials with in all leads and lifts and other incidentials . The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Square meter | - | - | BI01010001010000000000000515BI0100001117 |
| 6 | Providing form work with steel plates 3.15mm (three point fifteen millimeter) thick welded with angle iron in frame 30×30×5mm (thirty into thirty into five millimeter) so as to give a fair finish including centring, shuttering, strutting and propping etcetera with wooden battens and ballies upto any height in all floor level of propping and centring below supporting floor to ceiling upto any height and removal of the same for in-situ reinforced cement concrete and plain concrete work as per CPWD specifications 2019 in Lintels, beams, plinth beams, girders, bressumers and cantilevers as per the direction by the Engineer in charge upto any floor level including entire carriage of materials with in all leads and lifts and other incidentials . The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Square meter | - | - | BI01010001010000000000000515BI0100001118 |
| 7 | Providing form work with steel plates 3.15mm (three point fifteen millimeter) thick welded with angle iron in frame 30×30×5mm (thirty into thirty into five millimeter) so as to give a fair finish including centring, shuttering, strutting and propping etcetera with wooden battens and ballies upto any height in all floor level of propping and centring below supporting floor to ceiling upto any height and removal of the same for in-situ reinforced cement concrete and plain concrete work as per CPWD specifications 2019 in Edges of slabs and breaks in floors and walls under 20cm (twenty centimeter) wide as per the direction by the Engineer in charge including entire carriage of materials with in all leads and lifts and other incidentials . The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government | - | Running meter | - | - | BI01010001010000000000000515BI0100001119 |
| 8 | Providing form work with steel plates 3.15mm (three point fifteen millimeter) thick welded with angle iron in frame 30×30×5mm (thirty into thirty into five millimeter) so as to give a fair finish including centring, shuttering, strutting and propping etcetera with wooden battens and ballies upto any height in all floor level of propping and centring below supporting floor to ceiling upto any height and removal of the same for in-situ reinforced cement concrete and plain concrete work as per CPWD specifications 2019 in Chullah hoods, Weather shade, Chajjas, corbels, etc. including edges as per the direction by the Engineer in charge including entire carriage of materials with in all leads and lifts and other incidentals. The rates are inclusive octroi, royality, Malkana, toll tax, sale tax, goods service tax, labour cess or other taxes imposed by the Government. | - | Square meter | - | - | BI01010001010000000000000515BI0100001120 |
| 9 | Providing and laying in position cement concrete 1:4:8(one cement: four coarse sand: eight graded/crushed stone aggregate 40mm (forty miillmeter) nominal size mechanically mixed and curing complete excluding cost of centering and shuttering in foundation and plinth level as per CPWD specifications 2019 complete and direction of Engineer-in- charge including carriage of materials/machinery required to execute the work in all leads and lifts and other incidentials.The rate includes octroi , royality , Malkhana , toll tax, goods service tax , labour cess or other taxes imposed by the Govt. | - | Cubic meter | - | - | BI01010001010000000000000515BI0100001121 |
| 10 | Providing and applying a coat of residual petroleum bitumen of grade of VG-10 of approved quality using 1.70 kg (one point seventy kilogram) per square metre on damp proof course after cleaning the surface with brushes and finally with a piece of cloth lightly soaked in kerosene oil as per CPWD specifications 2019 complete and direction of Engineer-in- charge including carriage of materials/machinery required to execute the work in all leads and lifts and other incidentials.The rate includes octroi , royality , Malkhana , toll tax, goods service tax , labour cess or other taxes imposed by the Govt. | - | Square meter | - | - | BI01010001010000000000000515BI0100001122 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.35 MB
Tendernotice_2.pdf
PDF • 0.05 MB
CHCChowarJobNo5.pdf
Tender Documents • 1.31 MB
BOQ_197383.xls
BOQ • 0.39 MB