| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 LAccepted-AOC | L1 | Accepted-AOC Work order issued |
Tender Value
₹2.2 L
EMD Value
₹4,457
Closing Date
17 Feb 2022, 3:30 pmClosed
Executive Engineer
Executive Engineer, Buildings and Roads Division, Public Works Department, Karaikal
Construction of side drain in Vizhidiyur road near Sangaranthoppu village in Nervay Commune, Karaikal.
2022_PWDC3_9346_1
35-04/PW/BRK/KKL/2021-22
Open Tender
Civil Works
Item Rate
30 days
Sangaranthoppu village, Neravy commune
Please refer Tender documents.
5 documents required · 5 mandatory
₹525
₹4,457
4 Mar 2022
10 Feb 2022
17 Feb 2022
10 Feb 2022
17 Feb 2022
10 Feb 2022
Amount
Earthwork in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5m, including getting out the excavated soil and disposal of surplus excavated soil as directed , within a lead of 50m - all kinds of soil
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40mm nominal size)
Centring and shuttering including strutting, propping etc. and removal of form work for - foundations, footings, bases for columns
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - all work upto plith level - 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size)
Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete - 40mm thick with 20mm nominal size stone aggregate
Providing , hoisting and fixing upto floor five level precast reinforced cement concrete work in string courses, bands, copings, bed plates, anchor blocks, plain window sills and the like, including the cost of required centering, shuttering but excluding cost of reinforcement , with 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20mm nominal size)
Steel reinforcement for R.C.C.work including straightening , cutting , bending , placing in position and binding all complete upto plinth level - Thermo -Mechanically treated bars (TISCON / VIZAG / IISCO / SAIL / JSW) Fe - 415 or more
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .