| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹2.8 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹2.8 L+₹4,198.35 (1.50%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹2.9 L+₹10,299.96 (3.68%)Admitted-Finance | L3 | Admitted-Finance |
Tender Value
₹2.8 L
EMD Value
₹5,600
Closing Date
19 Sept 2026, 1:00 pmClosed
OFFICE OF EE(CIVIL)
THE KOLKATA MUNICIPAL CORPORATION 97 AND 98 GARFA MAIN ROAD
MAINTENANCE OF DRAINAGE SYSTEM BY REMOVAL OF CHOKAGES, REPLACING OF DAMAGED S/W PIPE , PIT / MANHOLE COVER ETC. AT BAGHAJATIN COLONY,CENTRAL PARK ETC. IN WARD NO.- 102,BR-XII.
2026_KMC_1041124_3
KMC/EE(C)/BR-XII/26-27
Open Tender
CIVIL WORKS
Percentage
90 days
BOROUGH XII
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹5,600
1 Oct 2026
8 Sept 2026
21 Sept 2026
8 Sept 2026
19 Sept 2026
8 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm | 72 | MTR | 334 | ₹24,048 |
| 2 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.14 & 3rd Corrigenda Addenda dtd-04.06.18,P-1) | 41.9 | SQM | 361 | ₹15,125.9 |
| 3 | Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (b) 1:4:8 proportion ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.23 & 3rd Corrigenda Addenda dtd-04.06.18, P-9 & 10) | 11.3 | M3 | 4,566 | ₹51,595.8 |
| 4 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth | 2.31 | M3 | 5,575 | ₹12,878.25 |
| 5 | (C) III: Labour Rate for Sanitary and Plumbing 4.Methor Mazdoor NOTE:The above rates are exclusive of 10 % profit and 1% Labour welfare cess, which would be admissible to the Contractor, but contractual percentage will not be applicable on the above rates.Page 113 of 124 | 200 | EA | 325.6 | ₹65,120 |
| 6 | Raising cover and frame of Catch Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) | 17 | EA | 1,507.28 | ₹25,623.76 |
| 7 | Raising cover and frame of Special Inspection Pit with CBW (1:4), 250 mm thick up to 100mm high with 20mm thick sand and cement plaster (1:4) including finishing with neat cement after cutting the asphaltum pavement taking out and re-fixing the existing cover and frame with cement concrete (1:1.5:3) with stone chips all round the frame surface including removal of surplus spoils. ( Ref :Rate based on PWD Current SOR, PWD(R&B) 2018, p-233 (it -2.05), p-332(it-18.06), p-222 sl-5(a), p-332 (it -18.05)), pg-227, I-1.03, pg-230,Table-I , Table III-2 pg-226, PWD(B) 2017 , p-189 (it -1) and 3rd corria. & Adda., p-49&50, Date 04.06.2018, p-192 (it -15), p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, p-303, p-269 (it -1) and 1st Corria & Adda, Page-4, Date 08.01.2018, page-12 (item -13)) | 11 | EA | 1,758.9 | ₹19,347.9 |
| 8 | SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size (viii) 5 MT load bearing capacity gully pit cover with frame and hinge arrangement for opening of size Cover: 470 mm X 420 mm X 80 mm Frame: 590 mm X 550 mm X 170 mm opening: 380mm x 305mm Weight: 100 kg (approx) | 6 | EA | 2,001 | ₹12,006 |
| 9 | SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (iv) 15 MT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of size Cover: 460 mm X 75 mm Frame: 620 mm X 150 mm opening: 360mm Weight: 100 kg (approx) | 2 | EA | 2,536 | ₹5,072 |
| 10 | SANITARY AND DRAINAGE WORKS (B)-(IV)INSPECTION PIT,SEPTIC TANK,SOAK PIT ETC.8.Supplying, fitting and fixing in position reinforced cement polymer concrete manhole /gully pit cover with matching frame.As per I.S-12592(M.D) (i) 35 MT load bearing capacity round manhole cover provided with two lifter hooks fitted with matching frame of size.Cover: 700 mm X 100 mm Frame: 910 mm X 185 mm opening: 560mm Weight: 245 kg (approx) | 1 | EA | 4,034 | ₹4,034 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.45 MB
FORM-102_05.pdf
Tender Documents • 0.58 MB
BOQ_2556594.xls
BOQ • 0.28 MB
PREQUE.pdf
Additional Documents • 0.17 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .