| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.1 CrAccepted-AOC | ₹5.1 Cr | L1 | Accepted-AOC BID ACCEPTED BEING OVERALL REASONABLE |
| 2 | L2₹5.2 Cr+₹10.3 L (2.02%)Rejected-Finance | ₹5.2 Cr+₹10.3 L (2.02%) | L2 | Rejected-Finance Other than L1 |
| 3 | L3₹5.3 Cr+₹23.2 L (4.53%)Rejected-Finance AT BARIMAL PO HATIBARI PS SUKINDA DIST JAJPUR PIN 755018 | JAJAPUR | ODISHA | 755018 | ₹5.3 Cr+₹23.2 L (4.53%) | L3 | Rejected-Finance Other than L1 |
| 4 | L4₹5.6 Cr+₹48.3 L (9.45%)Rejected-Finance | ₹5.6 Cr+₹48.3 L (9.45%) | L4 | Rejected-Finance Other than L1 |
| 5 | L5₹5.7 Cr+₹53.9 L (10.5%)Rejected-Finance | ₹5.7 Cr+₹53.9 L (10.5%) | L5 | Rejected-Finance Other than L1 |
| Sl No | Description | Qty | Unit | Agarwal Jagdish Construction Company Private Limited L7 | Mahaveer Engineering Co. L4 | ANIL KUMAR BISWAL L3 | M/S ABINASH KUMAR JAIN L2 | r.s.jain & sons L6 | CMRGS Infrastructure Projects Ltd L1 | SNG BUILDERS AND ENGINEERS L5 |
|---|---|---|---|---|---|---|---|---|---|---|
| 1.00SCHEDULE "A" Part-I (Building/Structures) (To be quoted by the tenderer) | ||||||||||
| 2.00 | Item No 01 A :
Design and construction of Block of Major's Married ACCN including sevant qtr and garrages with permanent specification complete all specified in soil bearing capacity report, design basis report, drawings and tender documents. | 1 | Each BLOCK | 2,42,00,000 ₹2,42,00,000 | 1,95,00,000 ₹1,95,00,000 | 1,84,00,000 ₹1,84,00,000 | 1,70,00,000 ₹1,70,00,000 | 1,50,00,000 ₹1,50,00,000 Lowest | 1,60,00,000 ₹1,60,00,000 | 1,51,00,000 ₹1,51,00,000 |
| 3.00 | Item No 01 B:
Design and construction of Block of Captain Married ACCN including servant qtrs and garrages with permanent specification complete all specified in soil bearing capacity report, design basis report, drawings and tender documents. | 1 | Each BLOCK | 1,46,60,000 ₹1,46,60,000 | 1,15,00,000 ₹1,15,00,000 | 1,09,00,000 ₹1,09,00,000 | 1,00,00,000 ₹1,00,00,000 | 1,40,00,000 ₹1,40,00,000 | 1,25,00,000 ₹1,25,00,000 | 90,00,000 ₹90,00,000 Lowest |
| 6.00 | Item No 01E :
Design and construction of Transit Accm for JCOs single living accn including garrages complete all specified in soil bearing capacity report, design basis report, drawings and tender documents. | 1 | Each BLOCK | 1,09,84,000 ₹1,09,84,000 | 95,00,000 ₹95,00,000 | 93,00,000 ₹93,00,000 | 90,00,000 ₹90,00,000 | 1,50,00,000 ₹1,50,00,000 | 50,00,000 ₹50,00,000 Lowest | 1,21,00,000 ₹1,21,00,000 |
| 7.00 | Sch 'A' Part-II (INTERNAL ELECTRIFICATION) Lump sum price worked out by the contractor for ((INTERNAL ELECTRIFICATION) as listed in Schedule 'A' Part-II against the lump sum price inserted by the MES. | 1 | Lump sum | 19,07,450.23 ₹19,07,450.23 | 20,00,000 ₹20,00,000 | 19,07,450.23 ₹19,07,450.23 | 22,54,259.36 ₹22,54,259.36 | 17,34,045 ₹17,34,045 Lowest | 22,00,000 ₹22,00,000 | 22,54,260 ₹22,54,260 |
| 8.00 | Sch 'A' Part-III (External Electric Supply) Lump sum price worked out by the contractor for (External Electric Supply) as listed in Schedule 'A' Part-III against the lump sum price inserted by the MES. | 1 | Lump sum | 9,91,453.47 ₹9,91,453.47 | 1,20,000 ₹1,20,000 Lowest | 10,38,665.54 ₹10,38,665.54 | 10,85,877.61 ₹10,85,877.61 | 11,00,000 ₹11,00,000 | 12,00,000 ₹12,00,000 | 11,42,533 ₹11,42,533 |
| 9.00 | Sch 'A' Part-IV (External Water supply) Lump sum price worked out by the contractor for (External Water supply) as listed in Schedule 'A' Part-IV against the lump sum price inserted by the MES. | 1 | Lump sum | 1,76,684.11 ₹1,76,684.11 Lowest | 2,00,000 ₹2,00,000 | 1,96,315.68 ₹1,96,315.68 | 1,96,315.68 ₹1,96,315.68 | 2,60,000 ₹2,60,000 | 2,00,000 ₹2,00,000 | 1,82,725 ₹1,82,725 |
| 10.00 | Sch 'A' Part-V (Road, Path Curvert) Lump sum price worked out by the contractor for (Road, Path Curvert) as listed in Schedule 'A' Part-V against the lump sum price inserted by the MES. | 1 | Lump sum | 27,95,875 ₹27,95,875 | 25,00,000 ₹25,00,000 | 21,95,108.83 ₹21,95,108.83 Lowest | 27,72,769.04 ₹27,72,769.04 | 25,00,000 ₹25,00,000 | 30,00,000 ₹30,00,000 | 25,87,918 ₹25,87,918 |
| 11.00 | Sch 'A' Part-VI (Sewage Disposal) Lump sum price worked out by the contractor for (Sewage Disposal) as listed in Schedule 'A' Part-VI against the lump sum price inserted by the MES. | 1 | Lump sum | 4,80,669.05 ₹4,80,669.05 | 4,00,000 ₹4,00,000 Lowest | 4,93,208.25 ₹4,93,208.25 | 4,59,770.4 ₹4,59,770.4 | 6,40,000 ₹6,40,000 | 5,15,000 ₹5,15,000 | 4,93,209 ₹4,93,209 |
| 12.00 | Sch 'A' Part-VII (Area Drainage) Lump sum price worked out by the contractor for (Area Drainage) as listed in Schedule 'A' Part-VII against the lump sum price inserted by the MES. | 1 | Lump sump | 22,10,608.46 ₹22,10,608.46 | 18,00,000 ₹18,00,000 Lowest | 19,93,171.57 ₹19,93,171.57 | 19,93,171.57 ₹19,93,171.57 | 22,00,000 ₹22,00,000 | 22,30,000 ₹22,30,000 | 21,92,489 ₹21,92,489 |
Tender Value
₹4.7 Cr
EMD Value
₹5.4 L
Closing Date
12 Dec 2025, 6:00 pmClosed
Chief Engineer Jabalpur Zone
HQ Chief Engineer Jabalpur Zone Ridge Road Jabalpur Cantt 482001
CONSTRUCTION OF MD ACCN AT BHUBANESHWAR MIL STN TRANSIT ACCN FOR JCOs AT GOPALPUR MIL STN
2025_MES_734377_1
753003A CONSTRUCTION OF MD ACCN AT BHUBANESHWAR MIL STN TRANSIT ACCN FOR JCOs AT GOPALPUR MIL STN
Open Tender
Civil Works
Lump-sum
550 days
GOPALPUR
AS PER NIT
8 documents required · 8 mandatory
₹2,000
GE I Gopalpur on Sea
₹5.4 L
Yes
18 Jun 2026
7 Nov 2025
19 Dec 2025
7 Nov 2025
12 Dec 2025
5 Dec 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | SCHEDULE "A" Part-I (Building/Structures) (To be quoted by the tenderer) | - | - | - | - |
| 2 | Item No 01 A :
Design and construction of Major's Married ACCN with permanent specification, (Plinth Area: 171 Sqm Height required 0.30 M) RCC Framed Construction, Provn of ATT, Provn of Mosquito proofing, exterior emulsion (weather coat in external finish), Provn of UPVC Windows in lieu of steel windows, Complete all specified in soil bearing capacity report, design basis report drawings and tender documents. | 1 | Each BLOCK | - | - |
| 3 | Item No 01 B:
Design and construction of Capt's Married ACCN with permanent specification, (Plinth Area: 171 Sqm Height required 0.30 M) RCC Framed Construction, Provn of ATT, Provn of Mosquito proofing, exterior emulsion (weather coat in external finish), Provn of UPVC Windows in lieu of steel windows, Complete all specified in soil bearing capacity report, design basis report drawings and tender documents. | 1 | Each BLOCK | - | - |
| 4 | Item No 01C :
Design and construction of Servent Qtrs with permanent specification, (Plinth Area: 171 Sqm Height required 0.30 M) RCC Framed Construction, Provn of ATT, Provn of Mosquito proofing, exterior emulsion (weather coat in external finish), Provn of UPVC Windows in lieu of steel windows, Complete all specified in soil bearing capacity report, design basis report drawings and tender documents. | 1 | Each BLOCK | - | - |
| 5 | Item No 01D :
Design and construction of Single Story Garrage for Vehicles Plinth Area: 171 Sqm Height required 0.30 M) RCC Framed Construction, Provn of ATT, Provn of Mosquito proofing, exterior emulsion (weather coat in external finish), Complete all specified in soil bearing capacity report, design basis report drawings and tender documents. | 1 | Each BLOCK | - | - |
| 6 | Item No 01E :
Design and construction of 10 x Transit commisioned officers (JCOs) (Plinth Area : 0.90 m in plinth ht due to low lying area), Disign Mix M-30, RCC Framed Construction, Provn of ATT, exterior emulsion (weather coat in external finish), Aluminium Joinery, Complete all specified in soil bearing capacity report, design basis report drawings and tender documents. | 1 | Each BLOCK | - | - |
| 7 | Sch 'A' Part-II (INTERNAL ELECTRIFICATION) Lump sum price worked out by the contractor for ((INTERNAL ELECTRIFICATION) as listed in Schedule 'A' Part-II against the lump sum price inserted by the MES. | 1 | Lump sum | - | - |
| 8 | Sch 'A' Part-III (External Electric Supply) Lump sum price worked out by the contractor for (External Electric Supply) as listed in Schedule 'A' Part-III against the lump sum price inserted by the MES. | 1 | Lump sum | - | - |
| 9 | Sch 'A' Part-IV (External Water supply) Lump sum price worked out by the contractor for (External Water supply) as listed in Schedule 'A' Part-IV against the lump sum price inserted by the MES. | 1 | Lump sum | - | - |
| 10 | Sch 'A' Part-V (Road, Path Curvert) Lump sum price worked out by the contractor for (Road, Path Curvert) as listed in Schedule 'A' Part-V against the lump sum price inserted by the MES. | 1 | Lump sum | - | - |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.86 MB
BOQ_827211.xls
BOQ • 0.90 MB
2Transit.rar
Additional Documents • 2.72 MB
1md.rar
Additional Documents • 5.10 MB
1T.pdf
Tender Documents • 19.81 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .