Loading…
Loading…
Tender Value
₹7.5 Cr
EMD Value
₹15.1 L
Closing Date
27 Jul 2026, 3:00 pmClosed
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
SR. DEN 5
14 conditions · 2 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover.
The tenderer must have successfully completed or substantially completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or One similar work each costing not less than the amount equal to 60% of advertised value of the tender. In case of tenders for composite works (e.g. works involving more than one distinct component, such as Civil Engineering works, S&T works, Electrical works, OHE works etc. and in the case of major bridges - substructure, superstructure etc.), tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: (i) Three similar works each costing not less than the amount equal to 30% of advertised value of each component of tender, or (ii) Two similar works each costing not less than the amount equal to 40% of advertised value of each component of tender, or (iii) One similar work each costing not less than the amount equal to 60% of advertised value of each component of tender. Note: Separate completed works of minimum required values shall also be considered for fulfillment of technical eligibility criteria for different components.
Definition of Similar Work for different components of this composite work (Total advertised value- Rs. 75462431.02) shall be as defined in the sub-paras: (i) For P-Way Related Works (Advertised Value of this component- Rs. 36003272.88): "Any P-Way Works", AND (ii) For Building related works at Station (Advertised Value of this component- Rs. 39459158.14): "Any building works with framed structure"
82 conditions · 18 needing a document upload
" No post tender correspondence will be done with the participant tenderer(s) for deficient credentials noted during scrutiny of tender/offer nor any credential will be accepted after opening of the tender and the offer shall be decided on the basis of submitted/Credentials downloaded with offer only"
If it is NOT mentioned in the submitted tender that tender is being submitted on behalf of a Sole Proprietorship firm / Partnership firm / Joint Venture / Registered Company etc., then the tender shall be treated as having been submitted by the individual who has signed the tender.
After opening of the tender, any document pertaining to the constitution of Sole Proprietorship Firm / Partnership Firm / Registered Company/ Registered Trust / Registered Society/HUF etc. shall be neither asked nor considered, if submitted.Further, no suo moto cognizance of any document available in public domain (i.e., on internet etc.) or in Railway's record/office files etc. will be taken for consideration of the tender, if no such mention is available in tender offer submitted
No post tender correspondence will be done with the participant tender(s) for deficient credentials noted during scrutiny of tender/offer nor any credential will be accepted after opening of the tender and the offer shall be decided on the basis of submitted/Credentials downloaded with offer only.
Tenderers attention is invited to clause I of Section VII and other relevant clauses of Section I and II whereby in case of non- submission/non compliance, the tender offer is likely to be rejected.
The tenderer/s shall submit a duly filled Tender form as per "ANNEXURE-I" OF STANDARD TENDER DOCUMENT"
In case of other than Company/Proprietary firm, Annexure-V (A) shall be submitted by each member of a Partnership Firm/ Joint Venture (JV)/Hindu Undivided Family (HUF)/ Limited Liability Partnership (LLP) etc. as the case may be. Non submission of above Certificate(s) by the bidder shall result in summarily rejection of his/their bid. It shall be mandatorily incumbent upon the tenderer to identify, state and submit the supporting documents duly self attested/digitally signed by which they/he is qualifying the Qualifying Criteria mentioned in the Tender Document.
The following documents should be specified for submission along with tender:
A. List of Personnel, Organization available on hand and proposed to be engaged for the subject work.
B. List of plant Machinery available on hand own and proposed to be inducted own hired to be given separately for the subject work.
C. The tenderer must have successfully completed or substantially completed any of the following during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or One similar work each costing not less than the amount equal to 60% of advertised value of the tender. Description of work, organization for whom executed, approximate value of contract at the time of award, date of award and date of scheduled completion of work, Date of actual start, actual completion and final value of contract should also be given.
D. List of works on hand indicating description of work, contract value, and approximate value of balance work yet to be done and date of award.
The tenderers whether sole proprietor , a limited company or a partnership firm he/they should submit authentic proof in terms of partnership deed, proprietorship documents etc. along with the tender. If he/they want to act through agent or individual partners should submit a power of attorney duly stamped and authenticated by Notary Public or by Magistrate in favour of specific person whether he/she/they are partners of the firm or any other person specifically authorizing him/her name to submit the tender, sign the agreement , receive money, witness measurements, sign measurement books , compromise, settie, relinquish any claims, preferred by firm and also sign No Claim Certificate and refer all or any disputes arbitration.
Bid Security: (a)Subject to exemptions provided under para 4(iv)) of this document, the tender must be accompanied by a Bid Security as mentioned in tender documents, failing which the tender shall be summarily rejected. (b)The Tenderer(s) shall keep the offer open for a minimum period of 60 days (in case of two packet system of tendering 90days) from the date of closing of the Tender. It is understood that the tender documents have been issued to the Tenderer(s) and the Tenderer(s), is / are permitted to tender in consideration of the stipulation on his / their part that after submitting his / Their tender subject to the period being extended further, if required by mutual agreement from time to time, he will not resile from his offer or modify the terms and conditions thereof in a manner not acceptable to North East Frontier Railway. Should the tenderer fail to observe or comply with the foregoing stipulation, the amount deposited or Bank guarantee bond submitted as Bid Security for the due performance of the above stipulation, shall be forfeited to the Railway. (c)If his tender is accepted, (i)the Bid Security mentioned in sub para(a) above deposited in cash through e- payment gateway will be retained as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of the Standard General Conditions of Contract; (ii)the Bid Security mentioned in sub para(a) above submitted as Bank guarantee bond, will be encashed as part security for the due and faithful fulfillment of the contract in terms of Clause 16 of the Standard General Conditions of Contract. The Bid Security of other Tenderers shall, save as herein before provided, be returned to them, but the Railway shall not be responsible for any loss or depreciation to the Bid Security that may happen thereto while in their possession, nor be liable to pay interest thereon. (d)In case Contractor submits the Term Deposit Receipt/Bank Guarantee Bond towards either the Full Security Depositor the Part Security Deposit equal to or more than Bid Security, the Railway shall return the Bid Security so retained as per sub para(c) above, to the Contractor.
The payment towards earnest money (EMD) against the works tenders should be made as brought out in GCC April 2022, Para 5: (Bid Security) PART I Instructions to Tenderers (ITT) & Para 6 (a to d) of Tender Form (Second Sheet)
Any firm recognized by Department of Industrial Policy and Promotion (DIPP) as 'Startups' and Labour Cooperative Societies shall submit Registration Certificate issued by appropriate authority.
The Bid Security shall be deposited either in cash through e- payment gateway or submitted as Bank Guarantee bond from a scheduled commercial bank of India or as mentioned in tender documents. The Bank Guarantee bond shall be as per Annexure- VIA and shall be valid for a period of 90days beyond the bid validity period
In case, submission of Bid Security in the form of Bank Guarantee, following shall be ensured:
A scanned copy of the Bank Guarantee shall be uploaded on e- Procurement Portal (IREPS) while applying to the tender.
The original Bank Guarantee should be delivered in person to the official nominated as indicated in the tender document before closing date for submission of bids (i.e. excluding the last 6.3.2 date of submission of bids). (Corrigendum: Para 5(3) ii Part I of GCC has been modified vide Advance Correction Slip No. 5 Railway Board's letter no. 2022/CE-l/CT/GCC-2022/Policy Dated 20.10.2023)
Non submission of scanned copy of Bank Guarantee with the bid on e-tendering portal (IREPS) and/or non submission of original 6.3.3 Bank Guarantee within the specified period shall lead to summary rejection of bid.
The Tender Security shall remain valid for a period of 90 days beyond the validity period for the Tender.
The details of the BG, physically submitted should match with the details available in the scanned copy and the data entered during bid submission time, FAILING WHICH THE BID WILL BE REJECTED.
The Bank Guarantee shall be placed in an envelope, which shall be sealed. The envelope shall clearly bear the identification "Bid 6.3.6 for the ***** Project" and shall clearly indicate the name and address of the Bidder. In addition, the Bid Due Date should be indicated on the right hand top corner of the envelope.
The envelope shall be addressed to the officer and address as mentioned in the tender document.
The following documents should be specified for submission along with tender:
A. List of Personnel, Organization available on hand and proposed to be engaged for the subject work.
B. List of plant Machinery available on hand own and proposed to be inducted own hired to be given separately for the subject work.
C. List of Works completed in the last three financial years giving description of work, organization for whom executed, approximate value of contract at the time of award, date of award and date of scheduled completion of work, Date of actual start, actual completion and final value of contract should also be given.
D. List of works on hand indicating description of work, contract value, and approximate value of balance work yet to be done and date of award.
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Clause regarding GST - (a) Tenderer should furnished their GSTIN numbers representing the States in which they are registered for GST, along with address of Registered Office, place of business in State etc. (b) The contract is under GST act & rules as applicable time to time. (c) All the bidders/tenders should ensure that they are GST compliant and their quoted tax structure/rates are as per GST Law.
The tenderers whether Sole Proprietor, a limited company or a partnership firm he/they should submit authentic proof in terms of partnership deed, proprietorship documents etc. along with the tender. If he/they want to act through agent or individual partners should submit a power of attorney duly stamped and authenticated by Notary Public or by Magistrate in favour of specific person whether he/she/they are partners of the firm or any other person specifically authorizing him/her name to submit the tender, sign the agreement, receive money, witness measurements, sign measurement books, compromise, settie, relinquish any claims, preferred by firm and also sign No Claim Certificate and refer all or any disputes arbitration.
(a) At the time of creation of any new tender in IREPS works module, an option has been provided to the tendering authority for obtaining Bid Security Declaration in lieu of Bid Security/Earnest Money Deposit. In case this option is selected, the Bid Security/Earnest Money Deposit amount for the tender shall be NIL. (b) If the tendering authority decides to take Bid Security/Earnest Money Deposit, it shall be mandatory for the tendering authority to provide reasons, and upload the approval of competent authority for the same. The Competent Authority shall be the next higher authority to the authority competent to finalise the particular tender. (c) In case Bid Security Declaration in lieu of Bid Security/Earnest Money Deposit is allowed against a tender, the provision has been made in IREPS for the bidder to mandatorily submit the following declaration along with his offer : If the bidder fails to submit the Bid security declaration, the bid will be rejected irrespective of winning the bid and qualifying for the tender.
Conversion of Dullabcherra (DLCR) station from DK Class in to B Class station under the jurisdiction of Sr. DEN/V/LMG.
SCL-ENGG-53-2026
SCL-ENGG-53-2026
Open
Works - General
12 Months
Hojai, Assam
₹0
₹15.1 L
27 Jul 2026
2 Jul 2026
13 Jul 2026
158 items across 2 schedules · ₹6,29,43,368.56 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| Earthwork in filling in embankment, guide bunds, around buried type abutments, bridge gaps, trolley refuges, platforms etc. with contractor's own earth conforming to Soil Quality Class SQ1/SQ2/SQ3, after preparation of foundations as applicable, benching in existing banks wherever required, spreading in layers with motor grader, bringing the moisture content to OMC, mechanical compaction to specified density a n d dressing of bank to final profile as per RDSO Specifications: RDSO/2020/GE: IRS-0004 with latest correction slips. Note: 1) Foundation preparation, Benching including additional earthwork on account of this, wherever required, shall be paid extra under relevant schedule item for benching. 2) Payment for Earthwork under this item shall be made based on the cross section measurements calculated (i) with original ground profile of existing bank based on initial ground levels before doing benching and (ii) final profile of the bank worked out with final levels as per prevailing guidelines. | — | — | — | — | |
| 1 | Using Soil Class SQ1 | cum | 21500.00 | 391.59 | 84,19,185 |
| Earthwork in cutting in formation, trolley refuges, side drains, level crossing approaches, platforms, catch water drains, diversion of nallah & finishing to required dimension and slopes to obtain a neat appearance to standard profile inclusive of all labour, materials, plant & machinery, leading all cut spoils either to make spoil dumps or for filling in embankment with leads within 2 km on either side of edge of the cutting(s) including all lifts, ascent, descent, loading, unloading, bailing & pumping out water, if required, clearance of site and all other works incidental thereto for completing the work as per RDSO Specification No. RDSO/2020/GE: IRS-0004 with latest updated correction slips and to the satisfaction of the Engineer-in-Charge. Note: (i) All usable earth arising from cut spoils shall be led into bank formation and Unusable spoils shall be dumped / stacked away from toe of embankment. (ii) All hard rock /and boulders not fit for filling will be stacked by the contractor and will be property of the Railways. (iii)Cut trees shall be property of Railways and to be deposited in the railway godown unless specified otherwise in the Conditions of Contract. | — | — | — | — | |
| 2 | In all conditions and classifications of soil except rock | cum | 7500.00 | 105.58 | 7,91,850 |
| 3 | Foundation preparation in cutting - ploughing and pulverizing 15 cm of top of soil with tractor trolley, mixing water to achieve OMC with water sprinkler or allowing for natural drying, as required, and compaction with vibratory roller of suitable capacity to achieve 98% MDD for laying blanketing layer. | 100 Sqm | 9500.00 | 382.25 | 36,313.75 |
| 4 | Manufacturing of blanketing material by wet mixing of naturally available suitable soil including additional blending with naturally available or manufactured material as required to achieve specified gradation, in designed proportion in Pug mill or wet mix plant to have uniform gradation including all incidental transportation, laying over finished formation in uniform layer(s) with motor grader, compaction with suitable vibratory roller to specified density and finishing to correct profile, complete as per RDSO Specification No. RDSO/2020/GE: IRS- 0004 with latest correction slips. | cum | 4710.00 | 1,202.73 | 56,64,858.3 |
| Laying and linking of turnouts of all types including diamond crossings & Derailing switches with 52Kg / 60Kg rail section on PSC sleepers on prepared ballast bed for New lines or during total closure of section at indicated location as per standard drawing, duly leading sleepers, rails, switches, crossings, fastenings including rail cutting, drilling, fixing of all components, fittings with housing of tongue rails as per requirement of signaling, preparing ballast bed, filling and spreading of ballast as required, linking of turnout with track, attending track parameters including lifting, providing one round of packing to make track fit for 20 kmph speed including lubrication of fittings/fastenings, complete as directed by Engineer in-charge. | — | — | — | — | |
| 5 | 1 in 12 Turnouts | Set | 6.00 | 59,305.9 | 3,55,835.4 |
| Manual deep screening of Plain track/ turnouts under traffic as per procedure prescribed in IRPWM, June 2020 or latest, in other than PSC sleepers of any density and throwing away screened muck arising out of screening on toe of bank or on cess, if low or on spoil banks above top of cutting (including throwing and leveling, if required beyond minimum 5m from the edge of cutting which are up to 3m deep or alternatively carting it up to 50m for disposing it off beyond cutting or platforms) as per direction of Engineer in- charge, including cutting cess for effective drainage on both sides, one round of kutcha packing with screened ballast and further attending to track parameter to make track fit for 20 kmph speed complete in all respect. Note : Payment shall be made for length along main line only for turnouts. | — | — | — | — | |
| 6 | Depth of 250 mm below bottom of sleeper of Plain Track | TRM | 1311.00 | 466.29 | 6,11,306.19 |
| 7 | Boxing and profiling of ballast as per procedure prescribed in latest edition of IRPWM including cess dressing on both sides of track. The work will include removing excess ballast from track and putting the same in crib and shoulder by leading to a maximum of 50m including crossing of track, deweeding on ballast section etc and as directed by Engineer-In charge. | TRM | 1311.00 | 29.56 | 38,753.16 |
| Unloading of ballast from Railway's Hopper Wagons, quantity distribution as per pre-defined site requirement, clearing infringements/jammed ballast, distributing the unloaded ballast uniformly over the track, profiling and boxing following all prescribed safety norms. | — | — | — | — | |
| 8 | Under Traffic Block Conditions: | cum | 3737.00 | 59.02 | 2,20,557.74 |
| Manufacturing, supply and stacking of machine crushed Track Ballast conforming to RDSO Specification (IRS-GE-1) with latest correction slips at Railway depot or nominated location. Note: Distance of nearest quarry mentioned in each sub- item is only for the purpose of selecting the items for preparation of estimates/tender schedule, based on the minimum distance between nearest quarry and centre of supply points and will not affect the selection of quarry during physical supply in any way till prescribed specification is met fully. | — | — | — | — | |
| 9 | When distance of nearest quarry is more than 50 km and up to 100 km | cum | 3737.00 | 2,791.85 | 1,04,33,143.45 |
| Manufacturing and Supply of Alumino thermic welding portions of 52Kg/60 Kg/60EI-R260 as approved by RDSO for welding of rails 52Kg/60Kg/60EI-R260 kg for 25mm gap by the process of AT welding along with complete accessories confirming to the specification laid down in Indian Railway Standard specification No.IRST-19-2020 up to date correction slips with Single shot crucible fitted with Automatic Tapping Thimble, 3 pieces pre fabricated mould (Zircon washed) manually pressed using compressed air petrol/LPG pre heating for execution of welding of rail joint as directed by the engineer in charge at site. Note: 1. The accessories along with welding portion shall be supplied as per Annexure-I of the IRUSSOR - 2021. 2. Rate is inclusive of transportation of above to SSE/P.Way stores. | — | — | — | — | |
| 10 | For 52Kg 90 UTS Rails | Each | 85.00 | 4,739.76 | 4,02,879.6 |
| 11 | 25mm gap 'in-situ' welding during traffic block using Railway's welding portion & Welder and finishing of weld to meet the prescribed tolerances and pass all stipulated tests with all required labour, materials, consumables, tools, equipments etc. to complete the work in all respect as per IR's "Manual for Fusion Welding of Rails by Alumino - Thermic Process" with latest correction slips, including marking of welded joint, painting weld collar with anticorrosive paint, restoration of track near weld joint to original position and fixing of joggled fish plate at new weld, to be removed after passing of weld in USFD test as directed by Engineer in charge. Note: 1. Only welding portion and related accessories as per Annexure - I and Welder shall be supplied by Railways. 2. Hydraulic Weld trimmer shall be used for chipping and profile Grinder for finishing. 3. Required nos. of Joggled fish plates shall be supplied by Railway at nearest P. Way Stores and the same shall be returned at nearest P. Way Store or at other location as per direction of Engineer-in-Charge after release from track. | Each | 120.00 | 1,851.75 | 2,22,210 |
| Flash Butt Welding of 90 UTS rails and finishing of weld to meet the prescribed tolerances and pass all stipulated tests, conforming to IR's Manual for Flash Butt Welding of Rails with latest amendment, using contractor's self-propelled rail cum road / Mobile FBW Plants, tools, equipments and consumables. Item also includes painting with anticorrosive paint as approved and marking of welded joints, pre-straightening & post-straightening of panels and USFD testing of finished weld as directed by Engineer in-charge. | — | — | — | — | |
| 12 | 52 Kg 'in-situ' under traffic block | Each | 121.00 | 11,116.12 | 13,45,050.52 |
| 13 | Dismantling of existing LWR/SWR track of any structure, removing rails, sleepers, fish plates, cutting of rails, segregation and stacking of released Rails, Sleepers and fitting at nominated location in countable manner within a free lead of 500m, levelling of ballast to correct profile for laying new track over it, all as per direction of Engineer-in-Charge. | TRM | 100.00 | 210.69 | 21,069 |
| 14 | Spreading of ballast, from existing stacks available along formation on top or at c e s s , in required uniform thickness, compaction of ballast layer laid on new formation at all the locations with smooth wheeled power roller of 8-10 tonne capacity to sufficient number of passes to form consolidated ballast bed of approximately 250mm thickness to a width of 4m symmetrical to centre line of proposed track in correct line & level with all ascents & descents, as directed by Engineer in-charge. Note: Item is inclusive of (a) providing ramp for taking roller to formation and removing the same & making good formation after completion of work; (b) redistribution & leveling of excess ballast while rolling to obtain uniform plane cambered surface. | cum | 3737.00 | 44.5 | 1,66,296.5 |
| Linking of BG track (except at LC, Bridges and SEJs) with any type of rail section and sleeper of specified density, on ballast bed spread and compacted with suitable roller, over prepared formation including leading free rails/welded panels available along the alignment on to formation, leading and spreading all fittings and fastenings, spreading of sleepers at specified spacing, squaring, placing of rails over sleepers and fixing rails to sleepers with all types of fittings and fastenings to correct gauge & alignment, lubrication of fittings and fastenings with contractor's grease as per IRPWM standards with contractors labour, tools, consumables, with all lead, lifts etc. complete and raising, levelling and initial packing of track to make it fit for 30 kmph and meet other prerequisites prescribed in Indian Railway Track Machine Manual for deployment of Tamping Machine. Note: 1.Rail cutting and Hole drilling shall be paid separately. 2.Spreading of ballast and compaction shall be paid separately under relevant item. | — | — | — | — | |
| 15 | For sleeper density of 1660 sleepers per km | TRM | 1311.00 | 333.78 | 4,37,585.58 |
| Through packing of track, as per procedure prescribed in latest edition of Indian Railways Permanent Way Manual | — | — | — | — | |
| 16 | For PSC sleeper Track with Sleeper Density of 1540 Sleepers/Km or more | TRM | 1311.00 | 117.26 | 1,53,727.86 |
| Picking up of slacks in track of all sleeper density, duly opening up ballast, gauging, alignment, correcting longitudinal & cross levels, packing, boxing of ballast and dressing the same under traffic conditions as per procedure prescribed in latest edition of IRPWM and as directed by Engineer in-charge. Note: In-charge section Engineer should identify locations requiring packing and obtain prior approval of DEN/XEN before execution of the work when there is no Zonal Track Maintenance agency deployed in the section. | — | — | — | — | |
| 17 | For PSC Sleeper | TRM | 750.00 | 100.51 | 75,382.5 |
| First or Second Through Packing of track of all sleeper density including giving a general lift, as desired to eliminate sag after Deep Screening work, lifting of track, lowering of track and major realignment of curves and formation rehabilitation as per procedure prescribed in latest edition of IRPWM. Note: General lift is normally 25 mm and isolated lift may be up to 50 mm. | — | — | — | — | |
| 18 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 1311.00 | 154.78 | 2,02,916.58 |
| Third or subsequent Through Packing of track for all sleeper density including picking of slacks, as required after second through packing, subsequent to Deep Screening work as per procedure prescribed in latest edition of IRPWM. This item can also be used after lifting/regrading/realignment works also. Note: General lift is normally 25 mm and isolated lift may be up to 50 mm. | — | — | — | — | |
| 19 | For PSC Sleeper Track with Sleeper Density of 1660 | TRM | 1311.00 | 119.06 | 1,56,087.66 |
| Systemic overhauling of track under t r a ffi c as per procedure prescribed in latest edition of IRPWM , including removing the crib ballast in 50mm to 75mm depth below bottom of sleeper and complete shoulder ballast without breaking core under the bottom of sleeper, to recover clean ballast by screening on wire mesh and disposing off the muck including throwing & leveling, if required beyond minimum 5m from the edge of cutting which are up to 3m deep or alternatively carting it up to 50m for disposing it off beyond cutting or platforms away from the track, as directed by Engineer in-charge including cutting & making up the cess and ensuring proper drainage slope and then re-inserting cleaned ballast into track and compaction of shoulder and crib ballast by wooden mallet and dressing / profiling ballast as per railway specifications. | — | — | — | — | |
| 20 | For PSC sleeper Track with Sleeper Density of 1540 sleepers/Km or more | TRM | 600.00 | 200.06 | 1,20,036 |
| Pulling back of rails / panels on running track for creep adjustment or other incidental activities by removing and re- fixing all the fittings, and fastenings including squaring of sleepers and slack picking of displaced sleepers, as directed. | — | — | — | — | |
| 21 | For rail panel above 13 metre & up to 40 metre length | TRM | 500.00 | 44.64 | 22,320 |
| De-stressing of LWR/CWR track of any density under traffic line block with contractor's labours, tools, equipments and consumables inclusive of all lead & lift. Activities include cutting of LWR/CWR into convenient panels of specified length, removal of ERCs, liners, greasing of ERCs and liner contact area, lifting rails and keeping them on rollers provided at every 15 sleepers, working out elongation of rail ends depending on prevailing site conditions, pulling rails with the help of Hydraulic Tensor to achieve the desired elongation, cutting rails, as required, removing rollers and placing rail in position, re-fixing ERCs & liners and adjustment of gap at SEJs : Note: (1) Welding of rail joints will be paid separately. (2) Rail cutting and Hole drilling shall be paid separately. (3) Opening and closing of LC if required will be paid separately. (4) As per procedure prescribed in latest edition of IRPWM & CE's Circulars for destressing of LWR/CWR, if any. | — | — | — | — | |
| 22 | Without Rail tensor | TRM | 1200.00 | 50.06 | 60,072 |
| Anti-corrosive painting of rail outside track on rail bottom, web, foot and fishing plane with two coats of thickness of 100 microns each by bituminous black paint confirms to IS-9862 of reputed make including surface preparation, as a complete job as per procedure prescribed in latest edition of IRPWM. | — | — | — | — | |
| 23 | For 52 Kg Rails | RM | 2622.00 | 70.18 | 1,84,011.96 |
| 24 | Anti-corrosive painting to weld collar for Thermit welded rail joints on track or on cess for new welded joints to protect against normal corrosion for any rail section with two coats of ready mixed bituminous black paint of reputed make confirming to latest IS:9862 on welded area up to 10cm on either side including on the underside of rail foot by brush including surface preparation as per Railway's AT Weld Manual including lettering / weld numbering with approved enamel paint as directed Note: Before painting, dust, loose rust and mill scale and dirt shall be removed thoroughly by wire brushing. Scrubbing welded area with water to make it free from slag and other water soluble compounds to make it dry. | Each | 150.00 | 26.78 | 4,017 |
| Quick cutting with abrasive rail cutter of all types of rail sections including wear resistant, head hardened rails up to 110 UTS, with contractors tools & plants, equipment, consumable with all lead & lift etc. complete as directed by Engineer in- charge. Abrasive Rail Cutter will be as per RDSO Specification No. TM/SM/1 (Rev. 01 of 2012) with latest status of RDSO; Rail Cutting Wheel Abrasive Disc will be as per RDSO Specification No.TM/SM/2 (Rev. 01 of 2020) | — | — | — | — | |
| 25 | 52 Kg - 90 UTS - Outside Track | Each | 100.00 | 300.22 | 30,022 |
| 26 | 52 Kg - 90 UTS- On Running Line | Each | 100.00 | 334.53 | 33,453 |
| Drilling holes of 16 mm to 32 mm dia. with Rail Drilling machine including chamfering with appropriate chamfering tools in all types of rail section with contractor's tools & plants, equipment, consumable with all lead & lift etc. complete, as directed by Engineer in- charge. Rail Drilling Machine will be as per RDSO Specification No. TM/SM/3, dated 24.04.1991. | — | — | — | — | |
| 27 | Outside Track | Each | 120.00 | 63.07 | 7,568.4 |
| 28 | On Running Line | Each | 120.00 | 81.15 | 9,738 |
| Loading, leading and unloading of 52Kg / 60Kg rail up to 13 metre length by Railway's Rail Dolly / Dip Lorry to the nominated location under traffic with line protection in case road carriage is not possible with different lead with a lift up to 5 metre during block period. | — | — | — | — | |
| 29 | For lead beyond 500 metre and up to 1 Km. | MT | 145.00 | 556.19 | 80,647.55 |
| 30 | Extra to Item no. 171031 and 171032 with contractor's Rail Dolly / Dip Lorry | MT | 145.00 | 98.95 | 14,347.75 |
| Loading of 52kg / 60kg PSC normal line and special sleepers up to 2.75 metre length in Depot / Station / Mid-section between stations in a neat manner to departmental material train (DMT) or contractor's / Railway's Truck/Trailer with crane or any other means including crossing of one track with free lead up to 250 metre and lift up to 5 metre, if required with contractor's labour, tools & plants, machinery, consumables etc. Note: In case of any damage to sleeper during loading, penalty @ 50% of the all inclusive cost of sleeper shall be levied. | — | — | — | — | |
| 31 | I n Wagon where mechanical handling is possible a n d traffic block is not required or in Truck / trailer | MT | 692.00 | 138.1 | 95,565.2 |
| Loading, leading and unloading of PSC Sleepers of 52Kg / 60Kg by Railway's Rail Dolly/ Dip Lorry to the nominated location under traffic in case road carriage is not possible for different leads and lift up to 5 metres. | — | — | — | — | |
| 32 | For lead beyond 500 metre and up to 1 Km | MT | 692.00 | 498.05 | 3,44,650.6 |
| 33 | Extra to Item no. 172031 and 172032 with contractor's Rail Dolly/Dip Lorry. | MT | 692.00 | 104.02 | 71,981.84 |
| Loading, leading and unloading of all types of P.Way fittings and all other miscellaneous m a t e r i a l except Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: Lead shall be the shortest motorable road length between the points of loading and unloading. | — | — | — | — | |
| 34 | Lead beyond 20 Km and up to 30 km | MT | 25.00 | 367.37 | 9,184.25 |
| 35 | Lead beyond 30 Km and up to 50 km | MT | 20.00 | 471.16 | 9,423.2 |
| 36 | Lead beyond 100 Km and up to 150 Km | MT | 60.00 | 1,036.09 | 62,165.4 |
| 37 | Extra for every Km per MT beyond 150 Km over item no. 172047 | MT- Km | 65031.68 | 3.46 | 2,25,009.61 |
| Transportation of Rails, sleepers, switches, crossings, SEJs and Glued Joints by road vehicles for different leads. Note: 1 . Lead shall be the shortest motorable road length between the points of loading and unloading. 2. Loading and unloading shall be paid extra under relevant items. | — | — | — | — | |
| 38 | Lead up to 5 Km | MT | 45.00 | 57.09 | 2,569.05 |
| 39 | Lead beyond 30 Km and up to 50 km | MT | 300.00 | 341.6 | 1,02,480 |
| 40 | Lead beyond 50 Km and up to 100 Km | MT | 370.00 | 567.89 | 2,10,119.3 |
| 41 | Lead beyond 100 Km and up to 150 Km | MT | 986.00 | 906.53 | 8,93,838.58 |
| 42 | Extra for every Km per MT beyond 150 Km over item no. 172057 | MT- Km | 1035300.00 | 3.46 | 35,82,138 |
| 43 | Manufacturing and fixing buffer stop with Railway supplied rails, cutting, including bending of rails as per plan ,with all contractor's labour, materials, tools, plants etc. and all lead and lift including crossing of track where necessary and as directed by Engineer in charge at site. Note: Excavation, fixing rails in cement concrete, drilling of holes will be paid separately. | Each | 4.00 | 18,226.35 | 72,905.4 |
| Schedule total | ₹3,60,03,272.88 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
UPDATED GCC
ATTACHMENT
ACS11GCCWorks2026March1_compressed_1.pdf ACS 11 GCC Works 2026 March
ATTACHMENT
tenderSchedule53.pdf
ATTACHMENT
TenderdocumentDLCR.pdf
ATTACHMENT
GCC-2022-updated1512_compressed1-compressed_1.pdf
ATTACHMENT
ACS11GCCWorks2026March1_compressed_1.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .