| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.0 LAccepted-AOC 28 1 16 | ₹9.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹9.4 L+₹41,100 (4.56%)Rejected-AOC | ₹9.4 L+₹41,100 (4.56%) | L2 | Rejected-AOC L2 |
| 3 | L3₹9.9 L+₹84,302 (9.36%)Rejected-AOC | ₹9.9 L+₹84,302 (9.36%) | L3 | Rejected-AOC L3 |
| Sl No | Description | Qty | Unit | PITCHAIMANI N L3 | P THAVAMANI L2 | G ILANGUMARAN L1 |
|---|---|---|---|---|---|---|
| 1.01 | Earth work excavation in all kinds of soils except hard rock requiring blasting, inclusive of shoring, strutting and baling out water wherever necessary refilling the sides of foundation with excavated earth in layers of 15cm thick well rammed and consolidated depositing the surplus earth within compound in places as shown by the deptl.officers, clearing and leveling the site with initial lead of 10M and lift of 2M etc.Comp.SI.No.62-rate for 10m3 MDU-CORP-BUILDING DATA-P-18-SL No:1 | 36 | M3 | 225 ₹8,100 | 215.1 ₹7,743.6 | 200 ₹7,200 Lowest |
| 2.01 | Supplying and filling in foundation and basement with filling quarry dust in layers of 15cum thick well rammed and consolidated including watering complying with std. specification etc. MDU-CORP-BUILDING DATA-P-19-SL No:4 | 3 | M3 | 1,974.5 ₹5,923.5 | 1,887.7 ₹5,663.1 | 1,800 ₹5,400 Lowest |
| 3.01 | Cement concrete 1:4:8 (one cement four sand and eight aggregates) Using 40mm gauge hard broken granite jelly for foundation inc. consolidation and dewatering for foundation wherever necessary etc.complete. MDU-CORP-BUILDING DATA-P-21-SL No:10 | 5 | M3 | 6,378.9 ₹31,894.5 | 6,098.4 ₹30,492 | 5,800 ₹29,000 Lowest |
| 4.01 | Supplying and erecting shuttering with necessary supports for plith beam with all cross brancings etc..,complete(Rcc coloumn footing plinth beam and lintel sides) MDU-CORP-BUILDING DATA-P-24-SL No:14 | 108 | M2 | 1,494.6 ₹1,61,416.8 | 1,428.9 ₹1,54,321.2 | 1,400 ₹1,51,200 Lowest |
| 5.01 | Reinforced cement concrete 1:1 1/2 :3 (One cement One and half sand and three aggregate) using 20mm machine broken gauge bard granite jelly for RCC worksthe rate excluding the cost of reinforcement grills,centering and shuttering etc., complete MDU-CORP-BUILDING DATA-P-27-SL No:15 | 18 | M3 | 10,399.5 ₹1,87,191 | 9,942.2 ₹1,78,959.6 | 9,500 ₹1,71,000 Lowest |
| 6.01 | Supplying and erecting shuttering with necessary supports for plain surface such as RCC boxing side slab, and similar,RCC Slab with all cross bracings etc., complete in all floors of any height (The retrieved materials should be taken back by the contractor). The payment for centering shall be given after the concrete is laid. (Lintel & Sunshade) using steel plates10m2. Bottom Only MDU-CORP-BUILDING DATA-P-26-SL No:14 | 30 | M2 | 1,494.6 ₹44,838 | 1,428.9 ₹42,867 | 1,300 ₹39,000 Lowest |
| 7.01 | Reinforced cement concrete 1:1 1/2 :3 (One cement One and half sand and three aggregate) using 20mm machine broken gauge bard granite jelly for RCC worksthe rate excluding the cost of reinforcement grills,centering and shuttering etc., complete MDU-CORP-BUILDING DATA-P-27-SL No:15 | 8 | M3 | 10,399.5 ₹83,196 | 9,942.2 ₹79,537.6 | 9,500 ₹76,000 Lowest |
| 8.01 | Supplying fabricating and placing in position of MS grills for reinforcement rate inc. the cost of steel for all works (the rate to include cost of binding wire also). Below 16mm Dia MDU-CORP-BUILDING DATA-P-34-SL No:22 | 2,671 | Kg | 98.6 ₹2,63,360.6 | 94.3 ₹2,51,875.3 | 90 ₹2,40,390 Lowest |
| 9.01 | Cement concrete 1:4:8 (One cement four sand and Eight aggregate) using 40 mm gauge hard broken granite jelly for foundation including consolidation dewatering for foundation wherever necessary etc, complete | 4 | M3 | 6,378.9 ₹25,515.6 | 6,098.4 ₹24,393.6 | 5,800 ₹23,200 Lowest |
| 10.01 | Plain Cement Concrete 1:2:4 (one cement, two fine aggregates and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 3 | M3 | 7,798.8 ₹23,396.4 | 7,455.8 ₹22,367.4 | 7,000 ₹21,000 Lowest |
Tender Value
₹9.5 L
EMD Value
₹9,529
Closing Date
6 Feb 2026, 3:00 pmClosed
The Commissioner Madurai Corporation
Aringar Anna Maligai Thallakulam Madurai
Construction of Culvert at Kalkulam Kanmai Channel in Ward No.14
2026_MAWS_647665_1
Z1 / E2 / Est.79 / 25-26
Open Tender
Civil Works
Lump-sum
Madurai
Please refer Tender documents.
1 document required · 1 mandatory
₹0
₹9,529
17 Jul 2026
28 Jan 2026
6 Feb 2026
28 Jan 2026
6 Feb 2026
28 Jan 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Earth work excavation in all kinds of soils except hard rock requiring blasting, inclusive of shoring, strutting and baling out water wherever necessary refilling the sides of foundation with excavated earth in layers of 15cm thick well rammed and consolidated depositing the surplus earth within compound in places as shown by the deptl.officers, clearing and leveling the site with initial lead of 10M and lift of 2M etc.Comp.SI.No.62-rate for 10m3 MDU-CORP-BUILDING DATA-P-18-SL No:1 | 36 | M3 | - | - |
| 2.01 | Supplying and filling in foundation and basement with filling quarry dust in layers of 15cum thick well rammed and consolidated including watering complying with std. specification etc. MDU-CORP-BUILDING DATA-P-19-SL No:4 | 3 | M3 | - | - |
| 3.01 | Cement concrete 1:4:8 (one cement four sand and eight aggregates) Using 40mm gauge hard broken granite jelly for foundation inc. consolidation and dewatering for foundation wherever necessary etc.complete. MDU-CORP-BUILDING DATA-P-21-SL No:10 | 5 | M3 | - | - |
| 4.01 | Supplying and erecting shuttering with necessary supports for plith beam with all cross brancings etc..,complete(Rcc coloumn footing plinth beam and lintel sides) MDU-CORP-BUILDING DATA-P-24-SL No:14 | 108 | M2 | - | - |
| 5.01 | Reinforced cement concrete 1:1 1/2 :3 (One cement One and half sand and three aggregate) using 20mm machine broken gauge bard granite jelly for RCC worksthe rate excluding the cost of reinforcement grills,centering and shuttering etc., complete MDU-CORP-BUILDING DATA-P-27-SL No:15 | 18 | M3 | - | - |
| 6.01 | Supplying and erecting shuttering with necessary supports for plain surface such as RCC boxing side slab, and similar,RCC Slab with all cross bracings etc., complete in all floors of any height (The retrieved materials should be taken back by the contractor). The payment for centering shall be given after the concrete is laid. (Lintel & Sunshade) using steel plates10m2. Bottom Only MDU-CORP-BUILDING DATA-P-26-SL No:14 | 30 | M2 | - | - |
| 7.01 | Reinforced cement concrete 1:1 1/2 :3 (One cement One and half sand and three aggregate) using 20mm machine broken gauge bard granite jelly for RCC worksthe rate excluding the cost of reinforcement grills,centering and shuttering etc., complete MDU-CORP-BUILDING DATA-P-27-SL No:15 | 8 | M3 | - | - |
| 8.01 | Supplying fabricating and placing in position of MS grills for reinforcement rate inc. the cost of steel for all works (the rate to include cost of binding wire also). Below 16mm Dia MDU-CORP-BUILDING DATA-P-34-SL No:22 | 2,671 | Kg | - | - |
| 9.01 | Cement concrete 1:4:8 (One cement four sand and Eight aggregate) using 40 mm gauge hard broken granite jelly for foundation including consolidation dewatering for foundation wherever necessary etc, complete | 4 | M3 | - | - |
| 10.01 | Plain Cement Concrete 1:2:4 (one cement, two fine aggregates and four coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification | 3 | M3 | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.52 MB
BOQ_776462.xls
BOQ • 0.23 MB
Doc.pdf
Tender Documents • 0.79 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .