| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹19.7 LAccepted-AOC | ₹19.7 L | L1 | Accepted-AOC Accepted |
| 2 | L2₹19.8 LRejected-AOC | ₹19.8 L | L2 | Rejected-AOC Rejected |
| Sl No | Description | Qty | Unit | R. Valarmathi L2 | SENRAMAN L1 |
|---|---|---|---|---|---|
| 1.01 | Clearing the Scrub jungle including all labour charges for burrying and burning etc., | 483.6 | sqm | 11 ₹5,319.60 | 6.3 ₹3,046.68 |
| 1.02 | Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A | 145.08 | Cum | 137 ₹19,875.96 | 131.8 ₹19,121.54 |
| 1.03 | Picking the existing metal surface 7.5 cm thich removing the picked up stuff to the sides, Collecting all useful metal levelling and sectioning to camper power roll consolidation by power roller etc as per the standard specification | 503.75 | sqm | 28 ₹14,105 | 23.3 ₹11,737.38 |
| 1.04 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 154.31 | Cum | 2,663 ₹4.1 L | 2,658 ₹4.1 L |
| 1.05 | Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it. | 1,543.13 | sqm | 87 ₹1.3 L | 85.35 ₹1.3 L |
| 1.06 | Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., | 1,543.13 | sqm | 21 ₹32,405.73 | 19.8 ₹30,553.97 |
| 1.07 | BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as
per specification using CMP as per clause 507 of MORTH Rev-5 | 38.58 | Cum | 11,822 ₹4.6 L | 11,817 ₹4.6 L |
| 1.08Collection and supply of Red gravel including cost and convenyance and stecking at road side to deptl guage for taking precentand filling to the standard specification | |||||
| 1.09 | 0/0-0/403 | 32.24 | Cum | 563 ₹18,151.12 | 557 ₹17,957.68 |
| 1.10 | Earth work excavating and depositing on bank with an initial lead of 10M and initial lift of 2M in light black cotton soil, hard stiff clay, stiff black cotton, hard red earth, shales, Muram, gravel stoney earth and etc., as per SS 20B.(TNBP SS No. 23 & 2 | 26.4 | Cum | 269 ₹7,101.60 | 263 ₹6,943.20 |
Tender Value
₹20 L
EMD Value
₹20,000
Closing Date
11 Feb 2026, 3:00 pmClosed
Block Development Office BP
Panchayat Union Office,Andipatti
Strengthening of The Road and Small Culvert in Vegavathi Asiramam Burial Ground Road at T.Rajagobalanpatti Panchayat under Mines 2025-2026
2026_RDTN_652068_8
Mines 2025-2026 11.02.2026
Open Tender
Civil Works - Others
Andipatti
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹20,000
Yes
6 Mar 2026
6 Feb 2026
11 Feb 2026
6 Feb 2026
11 Feb 2026
6 Feb 2026
Clearing the Scrub jungle including all labour charges for burrying and burning etc.,
Earth work excavation and depositing on bank within initial lead of 10m & initial lift of 2m in hard stiff clay, stiff black cotton, hard red earth, shales, murram, gravel, stoney earth and earth mixed with small size boulders SS .20.A
Picking the existing metal surface 7.5 cm thich removing the picked up stuff to the sides, Collecting all useful metal levelling and sectioning to camper power roll consolidation by power roller etc as per the standard specification
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25/30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminous Concrete to 25/30/40mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 50.30kgs of VG30 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5
Collection and supply of Red gravel including cost and convenyance and stecking at road side to deptl guage for taking precentand filling to the standard specification
Earth work excavating and depositing on bank with an initial lead of 10M and initial lift of 2M in light black cotton soil, hard stiff clay, stiff black cotton, hard red earth, shales, Muram, gravel stoney earth and etc., as per SS 20B.(TNBP SS No. 23 & 2
Cement Concrete 1:4:8 using 40MM. gauge hand brocken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15 cm. thick, compacting etc. complete complying with standard specification and as directed.
Supplying and erecting centering for sides and soffits including supports and strutting upto 3.29m height for plane surface in all floors with all cross bracings using mild steel sheets of size 90 cm. x 60 cm. and 10 gauge stiffened, welded with mild stee
Supplying and erecting centering for sides and soffits including supports and strutting upto 3.29m height for plane surface in all floors with all cross bracings using mild steel sheets of size 90 cm. x 60 cm. and 10 gauge stiffened, welded with mild stee
Cement Concrete 1:3:6 (One cement Three sand and Six hard brocken stone) using 40MM. gauge hand brocken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15 cm. thick, compacting etc. complete complying with standard specification and as directed.
Supplying and fabrication of steel including cost and conveyance of steel to site and all labour charges for straightening, cutting to length,bending to shape and tying in position and forming grills for all R.C.C works
Reinforced cement concrete 1:1.5:3 mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing etc complete for 10 cum
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.42 MB
Tendernotice_2.pdf
PDF • 0.44 MB
BOQ_782000.xls
BOQ • 0.35 MB
Download all tender documents and submit your bid