Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹7.5 LAccepted-Finance | L1 | Accepted-Finance BEING L1 | |
| 2 | L2₹7.5 L+₹750 (0.10%)Rejected-Finance | L2 | Rejected-Finance NOT L1 | |
| 3 | L3₹7.5 L+₹900 (0.12%)Rejected-Finance | L3 | Rejected-Finance NOT L1 |
Tender Value
Refer Docs
Closing Date
21 Dec 2022, 6:00 pmClosed
GE (P) NO. 2 (AF) CHABUA
GE (P) NO. 2 (AF) CHABUA PO-CHABUA AIRFIELD
Topographical Survey for Provn of Four (ORP) Blast pens with Link taxi track and allied work services and soil investigation for provn of Work services for induction of two SU-30 MK-I Sqn (Phase-II) at AF Stn Chabua.
2022_MES_566562_1
3004/04/E3
Limited
Civil Works
Works
30 days
GE (P) NO. 2 (AF) CHABUA
Please refer Tender documents
2 documents required · 2 mandatory
₹0
Exempted
4 Jan 2023
1 Dec 2022
23 Dec 2022
1 Dec 2022
21 Dec 2022
8 Dec 2022
Amount
1. Carrying out detailed topographical survey using digital Total station instrument marking all existing fearures, boundaries, building, carriage ways, trees, electric / telephone lines, footpath, drains sewer lines, ponds, hillrocks, marshy lands, approach road, main road etc using total station digital instruments, Including preparation of layout plan for building of Approx 40000 Sqm area marking of Bench Mark and planning and finalisation of layout for external services like drain, road, sewage etc. (Qty - 40000 Sqm) Note : Area cleaning of grass & bushes necessary for survey to be carried out as per site requirement. 2. Preparation of drawings maintaining all the above parameters and with all dimension of perimeter, calculation of the land area in 3.0m x 3.0m grid interval and 0.3m contour interval, submission soft copy in CD and hardcopy in 5 sets. 3. Mobilisation of men and machinery to site and return back after completion of L/S work. Note:- (i) Submission of soft copy and hard copy in five sets of report with detailed description for field investigation as mentioned above shall be submitted by contractor.
BOREHOLES (20 Nos) The following works are to be carried out for sub surface investigation report:- (a) Boring through sand/clays/soft strata from ground level to 10 m depth or depth of refusal wherever is met earlier. (b) Conducting standard penetration test in the bore as per IS : 2131-1985 including collecting disturbed samples at every 0.5 mtr or change of strata including packing and handling all complete ,and collecting undisturbed soil samples at 1.0 mtr or change of strata including packing and handling all complete as per IS : 2132-1985. (c) Carrying out laboratory test for :- (i) Specific gravity, bulk and dry density. (ii) Grain size analysis. (iii) Natural Moisture content. (iv) Liquid and plastic limits, swelling index. (v) Shear characterstics of undistrubed samples using direct shear/triaxial shear test. (vi) Unconfined compression test. (vii) Consolidation test for consolidation properties. (viii) Chemical tests for availability of soluble chloride and sulphate.
(d) Subsurface investigation report to include clearly following parameters:- (i) Lay out of trial pits & bore holes on proposed site plan. (ii) Record of boring as per Appx 'D' of IS 1892. (iii) Soil/Rock Properties as per detailed exploration ( Table 3 of IS 1892 and sub para vi above). (iv) Soil properties based on above field tests. (v) Evaluation of safe bearing capacity based on shear failure and settlement failure criteria(Refer IS 1904-1986),(IS 8009 Part 1 &2).Allowable bearing capacity at various depths of 1.5 mtr, and 2 mtr as required below GL is to be given with suggestion for economical width and type of foundation .The report shall be include detailed calculations for SBC. In case of low bearing capacity recommendation may be include bearing capacity calculation SBC & Settlement calculation for raft foundation also. (vi) Recommendation for pile with pile capacity in case weaker strata is encountered. (vii) Other relevant recommendations for foundation and improvement of soil if necessary. (viii) Recommendation of existing soil for backfill purpose. (e) Testing method shall be strictly in accordance to relevant IS code. Notes : (i) All the reports/results will be got vetted from any of the IIT's or Govt Engineering Colleges. (ii) Submission of (04) four copies of test report with detailed description for field investigation as mentioned above shall be submitted by contractor.
CARD HOUSE
S.G. Foundation & Engineers
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
finance_634510.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .