Tender Value
₹10 L
EMD Value
₹20,000
Closing Date
17 Jul 2026, 12:00 pm
EXECUTIVEV ENGINEER M AND H DIVISION DODA
KHELLANI DODA
Construction of Pre fabricated Hut size 18 x 14 with 10 feet height with Toilet under HADP Project Self Sustenance in Mutton Production at Palmar District
2026_PWDJK_314583_1
MHDD/TS/2026-27/14
Open Tender
Machineries/ Mechanical Engg Items
60 days
PALMAR KISHTWAR
AS PER SBD
2 documents required · 2 mandatory
₹1,000
EXECUTIVEV ENGINEER M AND H DIVISION DODA
₹20,000
4 Jul 2026
4 Jul 2026
17 Jul 2026
4 Jul 2026
17 Jul 2026
4 Jul 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Site Preparation
Earthwork in excavation by manual means over area for leveling purpose including disposal of excavated earth up to 50m from cutting edge and should be disposed in near-by all kind of soil
Foundation for plinth work = 64’-0”-0” x 1’-6” x 1’-6’ ’= 146.25ft3
Foundation for columns = 6 x (2’ x 2’ x 3’-0”) = 72ft3
Foundation for plinth protection = 72’-0” x 1’-6” x 0’-6” = 54 ft3
Earth Work for Protection Wall = 25’-0” x 3’-6” x 4’-6” = 393.74 ft3
Total = 665.99 ft3 = 18.84 m3
Area to be excavated keeping in view the earth quake resistance for which a ms mesh (10 mm) is to be provided in the base foundation of the plinth
(SCH – 2.8.1) | 18.84 | m3 | 100 | ₹1,884 |
| 2 | Random Rubble masonry with hard stone in foundation and plinth including leveling up with cement concrete 1:6:12 (1 Cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level and curing complete with : Cement mortar 1:6 (1 Cement : 6 coarse sand)
Area
22’-0” x 8’-0” x 2-0” = 352.0 ft3 i.e. 9.96 M3 | 9.96 | m3 | 100 | ₹996 |
| 3 | Providing and laying of cement concrete (1:5:10) using 40mm nominal size nallah stone.
Plinth work = 64’-0” x 1’-6” x 0’-6’’= 48 ft3
Flooring= 18’-0” x 14’-0” x 0’-3’’= 75.6 ft3
Foundation for columns = 6 x (2’ x 2’ x 6”) = 12 ft3
Plinth Protection= 72’-0” x 1’-6” x 0’-6” = 54 ft3
Total = 189.6 ft3 = 5.36m3 | 5.36 | m3 | 101 | ₹541.36 |
| 4 | Providing and laying in position cement concrete of specified grade including curing but excluding the cost of centring and shuttering. All work upto plinth level with 1:2:4 (one cement: Two coarse sand: Four Graded stone aggregate 20 mm nominal in size)
Plinth work = (64’-0” x 1’-6” x 1’-0’’) + (64’-0” x 1’-0” x 2’-0’’) = 224 ft3
Flooring = (18’-0” x 14’-0” x 0’-6’’) = 126 ft3
Foundation for Columns = 6 x (1’-6” x 1’-6” x 1’-6”)+ 2 x (1’-6” x 1’-0” x 2’-0”) = 26.25ft3
Plinth Protection = 72’-0” x 1’-6” x 0’-6”= 54 ft3
KITCHEN Slab = (11’-6” x 2’-6” x 0’-6”) + 4 x (3’-0” x 2’-6” x 0’-6”) = 29.37 ft3
Total = 459.62ft3 = 13.01m3 | 13.01 | m3 | 102 | ₹1,327.02 |
| 5 | Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level
Mild steel and medium tensile steel bars for Plinth beam
10 mm bar of length 387’ = 117.95 mtr = @ 0.617 kg per metre = 72.77 kg
8mm bar of length Tie beam 937’ = 285.59mtr = @ 0.395 kg per metre = 112.80 kg
Total = 185.57 kg | 185.57 | kgs | 103 | ₹19,113.71 |
| 6 | Centering and shuttering including strutting, propping etc. and removal of form work for: 4.6.1 Foundations, footings, bases for columns
Area = 2 x (64’-0” x 2’-0”) = 256 ft2 = 23.78m2 | 23.78 | m2 | 103 | ₹2,449.34 |
| 7 | 12 mm cement plaster to plinth wall of mix 1 : 3 (1 cement : 3 fine sand)
Area = (64’-0” x 2’-0”) = 128 ft2 = 11.89m2
Total = 13.38 m2 | 11.89 | m2 | 103 | ₹1,224.67 |
| 8 | Supplying and filling in plinth with fine sand under floors including, watering, ramming, consolidating and dressing complete.
SCH-2.23
Area = (18’-0” x 14’-0” x 1’-6”) = 378ft3 = 110.69m3 | 10.69 | m3 | 103 | ₹1,101.07 |
| 9 | Steel work welded in built up section/ framed work including cutting, hosting, applying a priming coat using structural steel. In gratings, frames, guard bard, ladders, railings etc. trusses including primer and enamel paint including nut bolts, kingpost, struts etc. The job is inclusive of all material cost, labour cost, transportation and taxes.
Column Square Hollow Pipe Section (100 x 100 x 4 mm) = 8 x (10’-0”) = 24.38m @ 11.84 kg/m = 288.65 kg
MS Sq. Plate of size (200 x 200 x 10 mm): = 35 kg
Rectangular Sections Truss (100 x 50 x 3.6mm) = 29 rm @ 7.9 kg/m = 229.10 kg
Rectangular Sections Truss Bracing (50 x 50 x 3.6mm) = 60 rm @ 5.07kg/m = 304.2 kg
Rectangular Sections Parlins of size (50 x 50 x 3.6mm) = 43.9 rm @ 5.07 kg/m = 222.57 kg
Side rails (50 x 25 x 2.60 mm)= 29.26 m @ 2.76 kg/m = 80.75 kg
24 MS Anchor Bolts of size 20 mm x 750 mm
24x2’-6”=60’[email protected] per metre= 75.75 kg
Total Weight = 1236.02 Kg | 1,236.02 | kgs | 103 | ₹1,27,310.06 |
| 10 | Supply and installation at site of Prefabricated PUF (Poly-Urethane Foam) Panels of size 60 mm thick Fire proof Panels for walls (PPGI finish on both sides) to make a closed structure on the outer frame including doors and windows.
Prefabricated Sandwich PUF panels with Cam toggle type fasteners fitted and self-locking PVC gaskets fitted on all sides of wall and ceiling including rivets, Silicones, Anchor fastener, self drilling screw and all other allied accessories required for the installation/erection of PUF panels.
a. Wall to wall cam locking system. Internal/External flashing to be provided.
Job includes Cladding on all walls including sunshade on all windows and outer doors. The job is inclusive of all material cost, labour cost, transportation and taxes. | 1 | job | 103 | ₹103 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 2.07 MB
BOQ_1018615.xls
BOQ • 0.31 MB
Download all tender documents and submit your bid