Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹137.7 CrAdmitted-Finance 14 BILASIPARA P O P S BILASIPARA DIST DHUBRI ASSAM PIN 783348 | DHUBRI | ASSAM | 783348 | ₹137.7 Cr | L1 | Admitted-Finance |
| 2 | Rejected-Technical 4B TOWN SQUARE CHINAR PARK RAJARHAT KOLKATA 700 136 | - | - | Rejected-Technical Did not emerge as Technically Qualified Bidder |
| Sl No | Description | Qty | Unit | SHREE GAUTAM CONSTRUCTION CO. LTD. L1 |
|---|---|---|---|---|
| 1.01 | CoE Guwahati Total Value | 1 | Nos | 1,37,65,90,820 ₹137.7 Cr |
Updated dates
Tender Value
Refer Docs
EMD Value
₹2.6 Cr
Closing Date
18 Feb 2026, 2:00 pmClosed
Project Director
As per bid document
Design and Construction of Centre of Excellence (CoE) in Nursing, Guwahati, Assam
2026_MDRDE_50017_1
IN-AHIDMS-526519-CW-RFB
Open Tender
Civil Works - Building
1095 days
As per bid document
Please refer Tender documents.
4 documents required · 4 mandatory
₹25,000
₹2.6 Cr
Yes
As perbid document
16 Mar 2026
9 Jan 2026
18 Feb 2026
9 Jan 2026
18 Feb 2026
11 Feb 2026
10 Jan 2026 - 17 Jan 2026
19 Jan 2026
CoE Guwahati Total Value
SURVEY AND GEOTECHNICAL INVESTIGATION
Carry out Topographic survey of the entire land and thorough Geotechnical investigation surveys including report preparation as per the specifications as required at the site for construction of permanent structure. Necessary clearance to be obtained from the respective agencies. The contractor shall submit comprehensive Geotechnical Investigation Report and ensure that the final report is reviewed and vetted by Authority Engineer/ approved by the EIC.
Salvage
CIVIL & ALLIED SERVICES
Planning, Designing, and Construction on EPC Basis RCC framed structure HOSTEL BLOCK- 2 SEATER BUILDING (PARTIAL BASEMENT +G+4), with support services, allied & lift facilities with stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms, IS Codes and latest INC (Indian Nursing Council) guidelines complete in all respect. Note :- Plinth Area shall be measured for the actual constructed.
Planning, Designing, and Construction on EPC Basis RCC framed structure HOSTEL BLOCK- 3 SEATER BUILDING (PARTIAL BASEMENT+G+4), with support services, allied & lift facilities with stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms, IS Codes and latest INC (Indian Nursing Council) guidelines complete in all respect. Note :- Plinth Area shall be measured for the actual constructed.
Planning, Designing, and Construction on EPC Basis RCC framed structure ACADEMIC AND ADMIN BUILDING (G+2), with support services, allied & lift facilities with stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms, IS Codes and latest INC (Indian Nursing Council) guidelines complete in all respect. The scope of works also includes complete premium interior & Exterior finishes, acoustic wall treatment, decorative wall panels, murals, Exterior 3D wall art / 3D painting, signage & branding, canteen interiors, , conference room furnishing, multipurpose hall finishing and all decorative interior elements. Note :- Plinth Area shall be measured for the actual constructed.
Planning, Designing, and Construction on EPC Basis RCC framed structure P.G HOSTEL BUILDING (G+3), with support services & allied & lift facilities incorporating stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms, IS Codes and latest INC (Indian Nursing Council) guidelines complete in all respect. Note :- Plinth Area shall be measured for the actual constructed.
Planning, Designing, and Construction on EPC Basis RCC framed structure DIRECTOR BUNGALOW (G+1), with support services & allied by incorporating stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms & IS Codes and guidelines complete in all respect. Note :- Plinth Area shall be measured for the actual constructed.
Planning, Designing, and Construction on EPC Basis RCC framed structure SUB-STATION BUILDING (GR. FLOOR), with support services, by incorporating stipulated specifications including handing over complete as per scope of work and directions of Engineer-in-charge by incoprating stipulated specification and adopting NBC-2016 norms & IS Codes and guidelines complete in all respect. Note :- Plinth Area shall be measured for the actual constructed.
EXTERNAL SITE DEVELOPMENT
Planning, Designing and Construction on EPC Basis of INFRASTRUCTURE & EXTERNAL DEVELOPMENT – Electrical Works such as Electrical sub station, HT/LT Panel, DG set with synchronizing panels, UPS System, solar photo voltaic power generation system, IP based CCTV system, LAN System, IP based EPABX System, Audio Visual/Conference System, Street lighting with LED , High mast lights, Emergency Light and Illuminated digital signages, PHE & Fire fighting works & all services including handing over complete as per scope of work and directions of Engineer In charge.
CENTRALIZED HVAC SYSTEM
Planning, Designing, and Construction on EPC Basis of HVAC system for academic and administrative block alongwith hostel blocks (warden and visitor rooms) with support services & allied facilities by incorporating stipulated specifications, The scope further specifies centralized HVAC system, comprising VRV–VRF units ,Air Handling Units (AHU), Fresh Air Units (FAHU), Axial fan wherever required including handing over complete as per scope of work and directions of Engineer In charge.
Total Amount
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.05 MB
Tendernotice_1.pdf
PDF • 0.14 MB
ANNEXUREILayoutPlan.pdf
Additional Documents • 4.46 MB
ANNEXUREIIITechnicalspecificationsCivil.pdf
Additional Documents • 1.45 MB
GEOTECHNICALREPORT.pdf
Additional Documents • 4.28 MB
BOQ_79561.xls
BOQ • 0.34 MB
FinalRFBCoEfinal.pdf
Tender Documents • 3.78 MB
ANNEXUREIVTechnicalSpecificationElectricalandLVS.pdf
Additional Documents • 1.37 MB
ANNEXUREVIIILOM.pdf
Additional Documents • 0.73 MB
ANNEXUREVIITechnicalspecificationsPlumbling.pdf
Additional Documents • 0.69 MB
FinishingSchedule.pdf
Additional Documents • 0.51 MB
ANNEXUREVITechnicalSpecificationsHVAC.pdf
Additional Documents • 0.72 MB
ANNEXUREVTechnicalspecificationsFF.pdf
Additional Documents • 0.33 MB
Designbasedreport.pdf
Additional Documents • 5.00 MB
ANNEXUREIIDrawing.pdf
Additional Documents • 7.74 MB
Download all tender documents and submit your bid