| 1 | L1₹12.8 LAccepted-AOC | L1 | Accepted-AOC L1 Accepted | |
| 2 | L2₹15.6 L+₹2.6 L (19.7%)Rejected-AOC KRAL PORA BAGH I MEHTAB NEAR MANCHOWA PETROL PUMP DISTRICT BUDGAM 190019 J K | BUDGAM | BUDGAM | J K | 190019 | L2 | Rejected-AOC L2 |
Tender Value
Refer Docs
EMD Value
₹30,000
Closing Date
28 Sept 2020, 6:00 pmClosed
GE(AF) Srinagar
GE(AF) Srinagar, Air Force Station, Srinagar-190007
REPAIR/MAINT OF CENTRAL AC PAKAGE TYPE, HEATING PLANT AND HOT WATER PLANT UNDER GE (AF) SRINAGAR
2020_MES_373870_1
GE(AF)-22/2020-21
Open Tender
Electrical and Maintenance Works
Item Rate
180 days
Srinagar
Please refer Tender documents.
9 documents required · 9 mandatory
₹500
GE AF Srinagar
₹30,000
Yes
27 Oct 2020
1 Sept 2020
30 Sept 2020
1 Sept 2020
28 Sept 2020
14 Sept 2020
1 Sept 2020 - 7 Sept 2020
Amount
S&F ‘V’ belts of following cross section, pitch length & size A-28, including disconnection and taking down of ‘V’ belts from motors complete all as specified and directed, Make : Fenner / Hilton. (a) Cross section 13 x 08 mm & pitch length 740 mm of size A-28.
(b) V-belt of size B-66 for hot water blower at Bison APTT
(c)V-belt of size B-72 for AC Palnt AHU blower at WWR
(d)V-belt B –82 for hot water blower at Mig Bison APTT
(e)V-belt B –60 for hot water blower at Kopyo Lab
Disconnecting, dismantling and strip opening of the existing air handling unit of any description and in any position and of capacity 3000 CFM for overhauling and servicing including taking out existing shaft, blower, drum, pulley and dehumidifier pump etc. of air handling unit, checking thoroughly the serviceability of the parts, dismantling the parts, fixing the serviceable parts in position, replacement of the defective/non-functional /unserviceable parts /spares, reassembling, commissioning, fixing in position and testing of the air handling unit on full load for its smooth and trouble free operation complete all as directed and directed by Engineer-in-Charge. Note :- (i) The quoted rates of the contractor includes for fixing the serviceable parts in position and replacement of unserviceable parts with new parts. The new replaced parts shall be measured and paid for separately under appropriate item of Sch `A’ as `supply only (ii) Remetaling & grinding of the crank shaft, wherever applicable shall be measured and paid for separately under appropriate item of Schedule `A' (iii) Rates quoted by the contractor shall include the cost of transportation of any part of the AHU unit to and fro approved workshop for their repair and alignment.
Supply only the following spares / parts suitable for Air handling units repaired under respective Sch ‘A’ for servicing / overhauling of AHU. (Note (i) Cost element of removing unserviceable parts, fixing and testing of the new items/ parts is deemed to be included in the respective rates quoted by the contractor under respective Sch ‘A’ item for servicing / overhauling of AHU. (ii) Contractor shall have no claim on account of variation in quantities of these items/non execution of any of the above items and contractor shall be paid for at as quoted rates only for the parts actually replaced.)
Pedestal bearing no NTN 205 J (Japan) or equivalent of make SKF /NBC
Disconnecting and taking out existing unserviceable solenoid valve and supply & fix new solenoid valve ¼ “ with strainer 3 way. Cat part No. S 180 with Drier of Make : SPORLON. or equivalent make as approved by the GE complete all as specified and directed.
Disconnecting and taking out existing unserviceable liquid line valve of any description and in any position and supply, fixing and testing of new liquid line valve Teflon sheathed brass of size 5/8 “ complete all as specified and directed by Engineer-in-Charge. Make : BAP/KIM
All as per item No 4 above but of size 7/8 “ –do-
Supply and fixing strip heater 3 KW, 230 volts fin type Make : Daspas or equivalent make as approved by the GE
Dismantling , taking down existing worn out and rusted unserviceable duct including its insulation, supports etc complete.
M & L for fabriction of Supply air ducting made out of GI sheet of thickness 22 SWG (Zinc coating 120 gm/Sqm) and fabricated as per IS-655 including necessary bend and locking arrangements complete.
M & L for f Duct insulation for unconditioned space as under:- (a) Cleaning the external surfaces of ducts to remove dust & existing treatment mortar etc. and removal from site. (b) Applying a coat of hot blown bitumen grade 85/25 confirming to IS-702 @ 1.2 Kg/Sqm on the external surfaces of ducts. (c) Providing & fixing 50 micron thick PVC sheet on the external surfaces of ducts with suitable adhesive as per manufacturer instructions. (d) Applying a coat of hot black bituminous paint of grade 85/25 confirming to IS-702 on the PVC sheet @1.2 Kg/Sqm & sprinkling dry sand on the surface while paint is still wet. (e) Providing a 2” thick layer of Glass wool all over the surface having density 24 Kg per cum (Make : UP Twiga/Llyod) (f) Providing Aluminum sheet of thickness 26 gauge over glass wool and fixed with aluminium screws.
Material and labour for duct cleaning by opening of joints( Elbow, corner etc) and refixing in same position after cleaning internally of any shape and any size all as specified and directed by Engineer-In-Charge
Disconnecting & taking out Rusted/corroded unserviceable existing Thermofluid MS flanged pipe line of any description and in any size and supply & fixing MS flanged pipe Heavy grade for Thermofluid pipe line flanged type with and including all fittings & fixtures of the following sizes complete all as specified and directed by Engineer-In-Charge
32mm bore pipe line.
40mm bore pipe line.
50mm bore pipe line.
80mm bore pipe line.
Taking up or down cast iron butterfly valve/sluice valve of any description and supplying, fixing and testing new butterfly valve complete all as specified and directed of following bores in existing pipe line after necessary cleaning etc. :-
50 mm bore
65 mm bore
80 mm bore
S&F Push button unit for relay complete as in repairs including testing all as specified and directed by Engineer-in-Charge.
S&F LED indicator 22.5mm suitable for operating at 240/220 volts as in repairs including testing complete all as specified and directed by Engineer-in-Charge.
S&F in repair including testing of Auxillary contact block suitable for following contractor 1 NO + 1 NC auxiliary contacts as in repairs including testing complete all as specified and directed by Engineer-in-Charge.
For power contractor 3 pole 32 Amps
S&F Spare coil 220 volts suitable for following contractor as in repairs including testing complete all as specified and directed by Engineer-in-Charge.
For power contactor 3 pole upto 2 to 5 Amps
S&F Spare contact kit without coil suitable for following power contactor as in repairs including testing complete all as specified and directed by Engineer-in-Charge.
For power contactor 3 pole upto 2 to 5 Amps
For power contactor 3 pole 5 Amps
S&F Current transformer round/ring type of following capacity and description as in repairs including testing complete all as specified and directed by Engineer-in-Charge.
Ratio 100/5 to 150/5 Amp rated burden 5 VA, accuracy class 1.0
Comprehensive maintenance on monthly basis of package type AC plant3x11 TR+ 2x7.5 TR (05 Units) installed at KOPYO Lab Make Voltas, (i) One unit comprising of following:- (a) Condensor - 02 Nos (b) Compressor - 02 Nos (c) Blowers Motor - 01 Nos (d) Evaporator - 02 nos (e) Micro processer control panel - 01 Nos Note :- (i) Maintenance includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only (ii) No extra cost will be paid to the contractor for T&P and trade as required. (iii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iv) The setting of design parameter of air conditioning in microprocessor control panel & maint of soft ware is include in this rate.
Comprehensive maintenance on monthly basis of package type AC plant3x7.5 TR (03 Units) installed at BISON APTT Make Voltas, (i) One unit comprising of following:- (a) Condensor - 02 Nos (b) Compressor - 02 Nos (c) Blowers Motor- 1 Nos (d) Evaporator- 02 nos (e) Micro processer control panel - 01 Nos Note :- (i) Maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only (ii) No extra cost will be paid to the contractor for T&P and trade as required. (iii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iv) The setting of design parameter of air conditioning in microprocessor control panel & maint of soft ware is include in this rate.
Supply only for the 11 TR air cooled package type AC Plant Make :- Voltas (a) Microprocessor sensing panel (LCD) type
(b) Filter dryer
(c) Emerson thermostatic Exapn-valve
(d) Compressor scroll type
(e) Motor suitable for blower
(f) Aluminium fan blade as per existing size
(g) fan motor of out door unit
Supply only for the 7.5 TR air cooled package type AC plant Voltas make :- (a) Filter dryer
(b) Emerson thermostatic Exapn-valve
(c) Compressor scroll type
(d) Motor suitable for blower
(e) Aluminium fan blade as per existing size
(f) fan motor of out door unit
Comprehensive maintenance of Hot Water plant on monthly basis for 04 plants (SNCO MESS -02, Airmen MESS No 1- 02 Nos) Note :- (i) Comprehensive maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) No extra cost will be paid to the contractor for T&P and trade as required. . (ii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iii) The setting of designe parameter is include in this rate.
Supply only following components for Hot Water Plant
(a) Fuel pump
(b) Ignition coil
(c) ignition coil rod
(d) Nozel
(e) Photo cell
(f) Solonoid valve
(g) Contactor
(h) controller
(j) Thermostate
(k) sequance controller
Maintenance of Hot Air plant Diesel Operated with thermic fluid on monthly basis for 06 plants HQ -02, Crash Bay- 04 Note :- (i) Maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) No extra cost will be paid to the contractor for T&P and trade as required. . (ii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iii) The setting of design parameter is include in this rate. (iv) Each Plant comprises of following :- (a) Aquatherm Hot water boiler 200000 kcal fully automatic model No AT 200W Make thermex Pvt (Stn HQ and Crash way) (b) Water cercular pump 5 HP Make- Kirloskar (c) Monoblock fuel pumping set 1 HP -03 Make- kirloskar (d) water circulating pump 3 HP -04 Make -Kirloskar (e) Air handling unit 9700 ,5700,3100 cum/hrs -02 Nos Make indoair (f) Hot storage tank 800 ltrs
Supply only following components for Hot Air Plant
(a) Fuel pump
(b) Iginition coil
(c) ignition coil rod
(d) Nosel
(e) Photo cell
(f) Solonoid vavle
(g) Contractor
(h) controller
(j) Thermostate
(k) sequance controller
Supply and filling Thermic fluid specific quality all asper specified and directed by Engineer-in-Charge. Make Shell/HP or equivalent as approved by GE.
Comprehensive maintenance of Hot Air plant electrically operated on monthly basis- 02 plant(WSA - 02Nos) as directed by Engineer-in-charge Note :- (i) Maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (ii) The setting of designe parameter is include in this rate. (iii) No extra cost will be paid to the contractor for T&P and trade as required.
Supply Only following componenets of HotAir Plant
(a) Heating element 25 KW
(b) Thermostate
(c) Controller
(d) sub zero controller
(f) Contactor
(g) time delay
(h ) Over load relay
(j) MCCB 200 A
(k) MCB TP 100 A
Comprehensive maintenance of Hot Air plant Diesel Operated with Hot Water on monthly basis- 01 plant SMC & plant at WSA DB6) Note :- (i) Maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) No extra cost will be paid to the contractor for T&P and trade as required. . (ii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iii) The setting of designe parameter is include in this rate. (iv) Each Plant comprises of following :- (a) Aquatherm Hot water boiler 200000 kcal fully automatic model No AT 200W Make thermex Pvt (SMC & WSA DB6) (b) Water cercular pump 5 HP Make- Kirloskar (c) Monoblock fuel pumping set 1 HP -03 Make- kirloskar (d) water circulating pump 3 HP -03 Make -Kirloskar (e) Air handling unit 9700 cum/hrs -01 Nos (f) Hot storage tank 800 ltrs
Supply components Only for HotAir Plant deisel operated with hot water
(a) Fuel pump
(b) Iginition coil
(c) Solonoid valve
(d) Sequence controller
(e) Fuel nosel
(f) Contractor
(g) Thermostat
(h) Photocell
(j) PCB controller
Checking of all joints, elbows etc and make it leak proof Brazing of blower units for crash bay and garrage blowers, Leaking thermofluid oil feeder pipe lines and gate valves all as specified and directed by Engineer-In-Charge.
Repair and cleaning indoor unit hot air blowers for crash bay and garrage blowers all as specified and directed by Engineer-In-Charge.
Comprehensive maintenance of Hot Air plant Diesel Operated with Thermic fluid on monthly basis- 02 plant (45 WEU), 02 plant(MLH) Note :- (i) Comprensive maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) No extra cost will be paid to the contractor for T&P and trade as required. . (ii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iii) The setting of designe parameter is include in this rate. (iv) Each Plant comprises of following :- (a) Aquatherm Hot water boiler 200000 kcal fully automatic model No AT 200W Make thermex Pvt (45 WEU MLH) (b) Water cercular pump 5 HP Make- Kirloskar (c) Monoblock fuel pumping set 1 HP -03 Make- kirloskar (d) water circulating pump 3 HP -03 Make -Kirloskar (e) Air handling unit 9700 cum/hrs -01 Nos (f) Hot storage tank 800 ltrs
Supply components Only for HotAir Plant deisel operated with hot water
(a) Fuel pump
(b) Iginition coil
(c) Solonoid valve
(d) Sequence controller
(e) Fuel nosel
(f) Contractor
(g) Thermostat
(h) Photocell
(j) PCB controller
Comprehensive maintenance of Hot air plants on monthly basis for 04 plants (Saudamani-04 Nos), Note :- (i) Comprensive maintence includes ;- (a) Cleaning of all components and parts of plant, (b) Greasing of all components and parts of plant (c) Tightening of all nuts, bolts and washers etc (d) Cleaning of all filters (e) Oiling of all components and parts of plant (f) Replacement of spares as required which will be measured and paid separately under respective item as Supply only Note - (i) No extra cost will be paid to the contractor for T&P and trade as required. . (ii) The replacement of defective / non-functional parts shall be measured & paid for separately as “Supply only” under appropriate item of Sch ‘A’ and fixing rate for new items are deemed to include under this item. (iii) The setting of designe parameter is include in this rate.
Supply only following components for Hot Air Plant
(a) Fuel pump
(b) Ignation coil
(c) ignation coil rod
(d) Nozel
(e) Photo cell
(f) Solonoid valve
(g) Contactor
(h) PCB controller
(j) Thermostate
(k) sequance controller
Supply and fixing in repairs Oil fired air heaters complete with oil burner for thermo fluid air heating plant to delever output heat 200000K cal /hr with suitable capacity for HQ plant Make: ECOFLAM complete all as specified and directed by Engr-in-Charge.
Supply and fixing in repairs Oil fired air heaters complete with oil burner for thermo fluid air heating plant to delever output heat 200000K cal /hr with suitable capacity for crash bay plant Make: ECOFLAM complete all as specified and directed by Engr-in-Charge.
Supply and fixing in repairs oil fired air heaters complete with automation oil burner for K oil air heating plant with suitable capacity for WSA /saudamani auditorium complete all as specified and directed by Engineer-in-charge.
Disconnecting electric motor from foundation and taking down AC electric motors single phase/ 3 Phase 240/415 volts of any make of following capacity from site and removing the old winding wire, cleaning surface area, rewinding of starter/ motor with the existing size of super enemelled copper winding wire of superior quality of existing SWG including insulation material as fibre glass, insulation PVC and cotton tape etc as per manufacturer norms re-assembling the motor after repair, installing and testing complete all as specified and directed by Engineer-in-Charge (a) .50 HP to 1.5 HP single phase motor 50 Hz
(b)3.00 HP to 5.00 HP Three phase motor 50 Hz
(c)7.50 HP to 10.00 HP Three phase motor 50 Hz
Note for srl item no 1 to 41 : (i) All repair work shall be carried out only by authorised person qualified in the relevant trade (ii) Make of components replacement if not specifically mentioned in the relevant item same shall be of the existing make.
M/S RATHER CONSTRUCTION CO
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .