| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹4.2 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | L2₹4.4 L+₹16,138.30 (3.84%)Admitted-Finance | L2 | Admitted-Finance | ||
| 3 | L3₹5.2 L+₹95,049.83 (22.6%)Admitted-Finance | L3 | Admitted-Finance |
Tender Value
₹5.9 L
EMD Value
₹11,860
Closing Date
25 May 2026, 4:30 pmClosed
Executive Engineer University of Kashmir
Construction Division
Upgradation/Renovation of Office Chamber of Executive Engineer, Construction Division at Main Campus, U.O.K
2026_UDJK_309707_1
F(UCD)(Upgrad. Exen Office)KU/04/26
Open Tender
Civil Works
Percentage
30 days
Main Campus
As per NIT
4 documents required · 4 mandatory
₹300
Registrar University of Kashmir
₹11,860
1 Jun 2026
14 May 2026
26 May 2026
14 May 2026
25 May 2026
14 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Demolishing brick work in cement mortar up to floor V level including stacking of serviceable material and disposal of unserviceable material within the campus as per directions of EIC. | 6.64 | CUM | 1,458.45 | ₹9,684.11 |
| 2 | Demolishing cement concrete work, including disposal of unserviceable material within the campus as per directions of EIC
1:3:6 or richer mix. | 1.57 | CUM | 1,725.2 | ₹2,708.56 |
| 3 | Dismantling tiles with old plaster or skirting raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within the campus as per directions of EIC. | 25.57 | SQM | 57 | ₹1,457.49 |
| 4 | Providing and laying in position specified grade of reinforced cement concrete including the cost of centering, shuttering, finishing and reinforcement all work up to all levels.
1:2:4 (1 cement: 2 coarse sand: 4 graded stone aggregate 20mm nominal size) Crushed | 0.91 | CUM | 7,604 | ₹6,919.64 |
| 5 | Steel Work
Reinforcement for RCC works including straightening, cutting, bending placing in position and binding all complete up to all floors.
Thermo mechanically heated bars | 58.63 | K.G | 123.2 | ₹7,223.22 |
| 6 | Removing mortar from bricks and cleaning bricks including stacking within the campus. (stacks of cleaned bricks shall be measured) (brick work in cement mortar) | 950 | NO. | 4.94 | ₹4,693 |
| 7 | Labour for Brick work with FPS bricks of class designation 75 in super structure up to all floors.
In cement mortar 1cement: 6 fine sand mortar. | 2 | CUM | 5,500 | ₹11,000 |
| 8 | Brick work with FPS bricks of class designation 75 in super structure up to all floors.
In cement mortar 1cement: 6 coarse sand mortar. | 1.98 | CUM | 9,500 | ₹18,810 |
| 9 | Wood Work.
Providing wood work in frames of doors, windows, clerestory windows and other frames, wrought framed and fixed in position including a coat of black Jaipan.imported wood. | 0.36 | CUM | 68,000 | ₹24,480 |
| 10 | 12mm thick cement plaster on brickwork / concrete wall of mix 1:6 (1cement: 6 coarse sand) | 64.52 | SQM | 266.2 | ₹17,175.22 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.83 MB
BOQ_1002393.xls
BOQ • 0.52 MB
IMG_20260520_0001.pdf
PDF • 0.99 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .